Paragraph 26 Construction environmental management planI1

England, Wales and Scotland

(1)

No stage of the connection works shall commence until a construction environmental management plan, drafted in accordance with the principles set out in the outline construction environmental management plan has been submitted to and approved by West Sussex County Council in consultation with the Environment Agency and, in relation to the soil management plan referred to in paragraph (2)(a) below, Natural England.

(2)

The plan shall contain in particular—

(a)

a soil management plan which shall include measures for the handling, placing, compaction and management of soil;

(b)

a construction air quality management plan which shall include measures to control fugitive emissions from construction activities and the suppression of dirt and dust;

(c)

an invasive species management plan which shall include the control and removal of invasive weed species;

(d)

a site waste management plan to control the storage, use and disposal of materials during construction;

(e)

measures to monitor and minimise vibration during construction of the connection works;

(f)

proposals for environmental management during operation of Work No. 25; and

(g)

a written scheme to deal with contamination of land including groundwater within the Order limits.

(3)

All remediation, construction and commissioning works shall be undertaken in accordance with the approved plan.