Part 3 Requirements

England, Wales and Scotland

  1. 1Time limits
  2. 2Detailed offshore design parameters
  3. 3Detailed offshore design parameters
  4. 4Detailed offshore design parameters
  5. 5Detailed offshore design parameters
  6. 6Base port travel plan
  7. 7Lighting
  8. 8Offshore decommissioning
  9. 9Stages of authorised development onshore
  10. 10Design approval onshore
  11. 11Provision of landscaping
  12. 12Implementation and maintenance of landscaping
  13. 13Highway accesses
  14. 14Permanent highway accesses in the South Downs National Park
  15. 15Public rights of way
  16. 16National Trail in the South Downs National Park
  17. 17Fencing and means of enclosure
  18. 18Temporary fencing in the South Downs National Park
  19. 19Surface and foul water drainage
  20. 20Contaminated land and groundwater
  21. 21Landfill site
  22. 22Flood risk
  23. 23Archaeology
  24. 24Archaeology in the South Downs National Park
  25. 25Scheduled monument at Tottington Mount
  26. 26Construction environmental management plan
  27. 27Watercourse crossings
  28. 28Ecological and landscape management plan
  29. 29Ecological and landscape management plan for the South Downs National Park
  30. 30Construction health, safety and environmental plan
  31. 31Construction traffic management plan
  32. 32Construction hours
  33. 33External lighting and control of artificial light emissions
  34. 34External lighting in the South Downs National Park
  35. 35Control of noise during construction
  36. 36Control of noise during operational phase
  37. 37European protected species onshore
  38. 38European protected species within the South Downs National Park
  39. 39Restoration of land used temporarily for construction
  40. 40Restoration of land within the South Downs National Park used temporarily for construction
  41. 41Onshore decommissioning
  42. 42Amendments to approved details
  43. 43Consultation with local planning authority