Paragraph 3 Secondary evidence (Category A)F1
For the purposes of paragraph 1(3)(a), the items of Category A evidence are—
(a)
dated correspondence to the relevant planning authority seeking confirmation that the plant does not require planning permission;
(b)
a dated enquiry to the local network operator about the grid connection of the plant;
(c)
detailed, dated evidence (which can be from within the applicant’s organisation) that the applicant has allocated funding for the development of the plant;
(d)
dated evidence that an estimated cost of works has been provided to the applicant.