Article 30D Offshore wind generating stations using floating wind turbinesF1
This article applies to electricity—
which is generated from wind;
which is generated by a generating station which—
is offshore;
uses only floating wind turbines;
is granted preliminary accreditation which takes effect on or before 31st March 2017; and
is commissioned before 1st October 2018; and
in respect of which a declaration has been made in accordance with paragraph (3).
The amount of electricity to be stated in each SROC issued in respect of electricity to which this article applies is 2/7 of a megawatt hour.
A declaration is made in accordance with this paragraph if—
it is made by the operator of the generating station to the Authority in writing; and
it confirms that—
to the best of the operator's knowledge and belief the electricity generated was generated by a generating station using only floating wind turbines; and
the lease in respect of which the generating station is entitled to operate at that particular area of seabed is a demonstration lease issued by the Crown Estate F3Commissioners or a relevant person in relation to that site.
In this article “floating wind turbine” means a wind turbine which is fixed or connected to the seabed by means of a chain, tension leg or other flexible mooring F4and not by any other means.
Annotations
Textual amendments
- F1
Arts. 30C, 30D inserted (1.4.2014) by The Renewables Obligation (Scotland) Amendment Order 2014 (S.S.I. 2014/94), arts. 1(1), 13 (with art. 27)
- F2
Art. 30D(3)(b) substituted (1.12.2015) by The Renewables Obligation (Scotland) Amendment Order 2015 (S.S.I. 2015/384), arts. 1(1), 10(a) (with art. 16)
- F3
Words in art. 30D(3)(b)(ii) inserted (1.4.2017) by The Crown Estate Transfer Scheme 2017 (S.I. 2017/524), art. 1(2), Sch. 5 para. 117(4)
- F4
Words in art. 30D(4) inserted (1.12.2015) by The Renewables Obligation (Scotland) Amendment Order 2015 (S.S.I. 2015/384), arts. 1(1), 10(b) (with art. 16)