OpenLegislation

Paragraph 16 Restoration of land used temporarily for constructionI1

England, Wales and Scotland

Subject to article 27 (temporary use of land for carrying out the authorised project), any land within the Order limits which is used temporarily for or in connection with construction must be reinstated to a condition fit for its former use, or such other condition as the relevant planning authority may approve, within 12 months of completion of the authorised project.

Annotations

Commencement

I1

Sch. 3 para. 16 in force at 15.9.2016, see art. 1