The River Humber Gas Pipeline Replacement Order 2016
S.I. 2016/853 · Made 25 August 2016 · Extends to England, Wales and Scotland
Infrastructure Planning
Made 25th August 2016
Coming into force 15th September 2016
An application under section 37 of the Planning Act 2008f1 (“the 2008 Act”) has been made to the Secretary of State for an order granting development consent.
The application has been examined by the Examining Authority, which has made a report to the Secretary of State under section 83(1)(b) of the 2008 Act.
The Secretary of State has considered the report and recommendation of the Examining Authority, has taken into account the environmental information in accordance with regulation 3 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2009f2 and has had regard to the documents and matters referred to in section 104(2) of the 2008 Act.
The Secretary of State, having decided the application, has determined to make an order giving effect to the proposals comprised in the application on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
Accordingly, the Secretary of State, in exercise of the powers in sections 114 and 120 of the 2008 Act, makes the following Order:
Annotations to the whole text
Footnotes
- f1
- f2
-
S.I. 2009/2263, amended by S.I. 2012/635 and 2012/787.
Contents
- Part 1: Preliminary
- 1Citation and commencement
- 2Interpretation
- 3Application, modification and disapplication of legislative provisions
- Part 2: Works Provisions
- 4Development consent, etc. granted by Order
- 5Maintenance of authorised project
- 6Operation of authorised project
- 7Limits of deviation
- 8Defence to proceedings in respect of statutory nuisance
- 9Benefit of Order
- 10Transfer of benefit of Order
- 11Street Works
- 12Power to alter layout, etc. of streets
- 13Construction and maintenance of new, altered or diverted streets
- 14Temporary stopping up of streets and public rights of way
- 15Access to works
- 16Traffic Regulation
- 17Agreements with street authorities
- 18Discharge of water
- 19Authority to survey and investigate the land
- 20Removal of human remains
- Part 3: Acquisition and possession of land
- 21Compulsory acquisition of land
- 22Compulsory acquisition of rights
- 23Extinguishment and suspension of private rights
- 24Acquisition of subsoil only
- 25Power to override easements and other rights
- 26Application of the Compulsory Purchase (Vesting Declarations) Act 1981
- 27Temporary use of land for carrying out the authorised project
- 28Temporary use of land for maintaining the authorised project
- 29Disregard of certain interests and improvements
- 30Set-off for enhancement in value of retained land
- 31No double recovery
- 32Acquisition of part of certain properties
- 33Statutory undertakers
- 34Recovery of costs of new connections
- 35Time limit for exercise of authority to acquire land compulsorily
- 36Rights under or over streets
- 37Incorporation of the mineral code
- Part 4: Miscellaneous and general
- 38Application of landlord and tenant law
- 39Deemed consent under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009
- 40Operational land for purposes of the 1990 Act
- 41Felling or lopping of trees or shrubs
- 42Protective provisions
- 43Crown rights
- 44Certification of plans etc.
- 45Service of notices
- 46Arbitration
- 47Procedure in relation to certain approvals etc.
- Signature
- Schedule 1: Authorised project
- Part 1: Authorised development
- 1Paragraph 1
- Part 2: Further associated development and ancillary works
- 2Paragraph 2
- Schedule 2: Plans
- 1Works plans
- 2Land plans
- 3Access and rights of way plans
- 4Environmental statement
- Schedule 3: Requirements
- 1Interpretation
- 2Time limits
- 3Stages of the authorised project
- 4Detailed design approval
- 5Site Water Management Plan
- 6Site Waste Management Plan
- 7Removal of trees and hedgerows
- 8Hard landscaping and drainage
- 9Agricultural land drainage
- 10Archaeology
- 11Construction hours
- 12Construction Environmental Management Plan
- 13Noise
- 14Contaminated land and groundwater
- 15Construction traffic and accesses
- 16Restoration of land used temporarily for construction
- 17Temporary external lighting
- 18Environmental mitigation land
- 19Ecological Surveys
- 20Requirement for written approval
- 21Approved details and amendments to approved details
- Schedule 4Streets subject to street works
- Schedule 5Streets subject to alteration of layout
- Schedule 6Streets and public rights of way to be temporarily stopped up
- Schedule 7Access to works
- Schedule 8Land of which temporary possession may be taken
- Schedule 9: Deemed marine licence under Part 4 (Marine licensing) of the Marine and Coastal Access Act 2009
- Part 1: Introduction
- 1Interpretation
- 2Addresses
- Part 2: Licensed activities
- 3Paragraph 3
- Part 3: Conditions
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- Schedule 10: Protective provisions
- Part 1: For the protection of electricity, gas, water and sewerage undertakers
- 1Application
- 2Interpretation
- 3On-street apparatus
- 4Acquisition of apparatus
- 5Removal of apparatus
- 6Retained apparatus: protection
- 7Cathodic protection testing
- 8Expenses
- 9Co-operation
- 10Arbitration
- Part 2: For the protection of operators of Electronic Communication Code Networks
- 1Effect
- 2Interpretation
- 3On-street apparatus
- 4Enactments and agreements in respect of apparatus in the undertaker’s land
- 5Arbitration
- Part 3: For the protection of the Environment Agency
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- Part 4: For the protection of Anglian Water
- 1Paragraph 1
- Part 5: For the protection of Centrica
- 1Paragraph 1
- 2Interpretation
- 3Creation of rights and access for Centrica
- 4Apparatus
- 5Ground Subsidence Monitoring Scheme
- 6Cathodic Protection Testing
- 7Cathodic Protection Testing
- 8Removal of apparatus
- 9Facilities and rights for alternative apparatus
- 10Costs
- 11Requirement for agreement
- 12Disputes
- Schedule 11: Modification of compensation and compulsory purchase enactments for the creation of new rights
- 1Compensation enactments
- 2Compensation enactments
- 3Application of the 1965 Act
- 4Application of the 1965 Act
- 5Application of the 1965 Act
- 6Application of the 1965 Act
- 7Application of the 1965 Act
- 8Application of the 1965 Act
- Schedule 12: Procedure in relation to certain approvals etc.
- 1Determination of applications for specified consents
- 2Fees
- 3Appeals
- 4Outcome of Appeals
- 5Interpretation of this Schedule
- Explanatory note