Part 2 REQUIREMENTS

England, Wales and Scotland

In this Part of this Schedule—

  • “the approved development plans” mean the plans submitted with the application on 4 August 2010 or later and listed at requirement 6;

  • “by-products” includes incinerator bottom ash aggregate and ferrous and non-ferrous metal compounds;

  • “commercially operate” means operate the authorised development for commercial processing of waste and production of electricity for transmission to the national electricity grid following completion of hot commissioning and “commercial operation” and “commercially operated” shall be construed accordingly;

  • “heavy goods vehicle” means—

    1. (a)

      a heavy goods vehicle of 7.5 tonnes gross vehicle weight or more; and

    2. (b)

      any other vehicle designed for the transport of waste including refuse collection vehicles;

  • “low level restoration scheme” means the scheme for the restoration of Rookery North and Rookery South Pits which has been developed as a part of the review of old minerals permissions application which was submitted to Bedford Borough Council and Central Bedfordshire Council on 5 June 2009 and bears statutory reference number BC/CM/2000/08.

  1. 1Time limits
  2. 2Type of waste to be treated
  3. 3Commencement
  4. 4Incineration, operation, etc.
  5. 5Detailed design approval
  6. 6Detailed design approval
  7. 7BREEAM Rating
  8. 8Provision of landscaping
  9. 9Implementation and maintenance of landscaping
  10. 10Highway accesses
  11. 11Fencing and other means of site perimeter enclosure
  12. 12Surface and foul water drainage
  13. 13Land stability
  14. 14Contamination and groundwater
  15. 15Archaeology
  16. 16Code of construction practice
  17. 17Control of noise during construction and operational phase
  18. 18Control of noise during construction and operational phase
  19. 19Control of noise during construction and operational phase
  20. 20Control of noise during construction and operational phase
  21. 21Control of noise during construction and operational phase
  22. 22Control of noise during construction and operational phase
  23. 23Control of noise during construction and operational phase
  24. 24Construction hours
  25. 25Combined Heat and Power
  26. 26Delivery hours and traffic management
  27. 27CCTV
  28. 28Loads to be covered
  29. 29Restoration
  30. 30Amendments to approved details
  31. 31Low level restoration scheme
  32. 32Incinerator bottom ash processing and storage
  33. 33Incinerator bottom ash processing and storage
  34. 34Incinerator bottom ash processing and storage
  35. 35Lighting strategy
  36. 36Connection to the national grid
  37. 37Visibility requirements at Green Lane/C94 junction
  38. 38Vehicle movements
  39. 39Travel plan
  40. 40Ecological management scheme
  41. 41Residual Waste Acceptance Scheme