Paragraph 5 Work No. 5I1
England, Wales and Scotland
Works including—
fencing, gates, boundary treatment and other means of enclosure;
provision of security and monitoring measures such as CCTV columns, lighting columns and lighting, a fence detection system, cameras, weather stations, and communication infrastructure;
laying of electrical cables, including but not limited to electrical cables connecting Work No. 1, Work No. 2 and Work No. 3, including works to allow electrical cables crossings of non-navigable rivers, other watercourses and drains, permissive paths, public rights of way and other highways;
works to allow installation of bridge crossings over non-navigable rivers and other watercourses and drains;
laying down of internal access tracks (including fire access tracks), improvement of existing tracks, ramps, means of access, and roads, including construction signage and information boards;
provision of water tanks and pipework connection to hydrants located at inverter stations where BESS installed; and
equipment and materials storage during construction and decommissioning phases;
Annotations
Commencement
- I1
Sch. 1 para. 5 in force at 13.11.2025, see art. 1
Notes on the whole SI
Textual amendments
- F1
Words in Preamble substituted (6.2.2026) by The Stonestreet Green Solar (Correction) Order 2026 (S.I. 2026/131), art. 1, Sch.