Paragraph 2 Expiry of development consentI1
England, Wales and Scotland
(1)
The authorised development must cease generating electricity on a commercial basis no later than the 40th anniversary of the first export date.
(2)
Confirmation of the first export date must be provided by the undertaker to the local planning authority within one month of its occurrence.
Annotations
Commencement
- I1
Sch. 2 para. 2 in force at 13.11.2025, see art. 1
Notes on the whole SI
Textual amendments
- F1
Words in Preamble substituted (6.2.2026) by The Stonestreet Green Solar (Correction) Order 2026 (S.I. 2026/131), art. 1, Sch.