Paragraph 24 Surface and foul water drainageI1

England and Wales

(1)

No stage of the connection works shall commence until for that stage written details of the surface and (if any) foul water drainage system (including means of pollution control) have, after consultation with the relevant sewerage and drainage authorities and the Environment Agency, been submitted to and approved by the relevant planning authority.

(2)

The surface and foul water drainage system for each stage must be constructed in accordance with the approved details.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 24 in force at 28.11.2014, see art. 1