Paragraph 5 Regulation of works within the shared areaF1
The undertaker must not carry out the Specified Works without the prior written consent of the NZT Undertaker obtained pursuant to, and in accordance with, the provisions of paragraph 3.
Where under paragraph 3(5) the NZT Undertaker requires any protective works to be carried out either by themselves or by the undertaker (whether of a temporary or permanent nature) such protective works must be carried out to the reasonable satisfaction of the NZT Undertaker.
Nothing in paragraph 3 or this paragraph 5 precludes the undertaker from submitting at any time or from time to time, but in no case less than 48 days before commencing the execution of any of the Specified Works, new Plans in respect of that Specified Work in substitution of the Plans previously submitted, and the provisions of this paragraph and paragraph 3 shall apply to the new Plans.
Where there has been a reference to an expert in accordance with paragraph 11 and the expert gives approval for the works concerned, the Specified Works must be carried out in accordance with that approval and any conditions applied by the decision of the expert under paragraph 11.
The undertaker must give to the NZT Undertaker not less than 28 days’ written notice of its intention to commence the construction of any of the Specified Works and, not more than 14 days after completion of their construction, must give the NZT Undertaker written notice of the completion.
The undertaker is not required to comply with sub-paragraphs (1) to (5) above in a case of emergency, (being actions required directly to prevent possible death or injury) but in that case it must give to the NZT Undertaker notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and thereafter must comply with paragraphs 3 and 5 in so far as is reasonably practicable in the circumstances.
The undertaker must at all reasonable times during construction of the Specified Works allow the NZT Undertaker and its officers, employees, servants, contractors, and agents access to the Specified Works and all reasonable facilities for inspection of the Specified Works.
After the purpose of any temporary works has been accomplished, the undertaker must with all reasonable dispatch, or after a reasonable period of notice in writing from the NZT Undertaker requiring the undertaker to do so, remove the temporary works in, on, under, over, or within the Shared Area.
If the undertaker fails to remove the temporary works within a reasonable period of receipt of a notice pursuant to sub-paragraph (8), the NZT Undertaker may remove the temporary works and may recover the reasonable costs of doing so from the undertaker.
The undertaker must not exercise the powers conferred by the Order or undertake the Specified Works to prevent or interfere with the access by the NZT Undertaker to the NZT Specified Works unless first agreed in writing by the NZT Undertaker.
If in consequence of the exercise of the powers conferred by the Order or the carrying out of the Specified Works the access to any of the NZT Specified Works is materially obstructed, the undertaker must provide such alternative means of access to the NZT Specified Works as will enable the NZT Undertaker to construct, maintain or operate the NZT Project no less effectively than was possible before the obstruction.
To ensure its compliance with this paragraph 5, the undertaker must before carrying out any of the Specified Works request up-to-date written confirmation from the NZT Undertaker of the location of any part of its then existing or proposed NZT Specified Works.