Paragraph 4 Co-operationF1
Insofar as the NZT Specified Works are or may be undertaken concurrently with the Specified Works within the Shared Area, the undertaker must—
(a)
co-operate with the NZT Undertaker with a view to ensuring—
(i)
the co-ordination of programming of all activities and the carrying out of works within the Shared Area; and
(ii)
that access for the purposes of the construction and operation of the NZT Project is maintained for the NZT Undertaker and its contractors, employees, contractors and sub-contractors; and
(b)
use reasonable endeavours to avoid any conflict arising from the carrying out of the Respective Projects.
Annotations
Textual amendments
- F1
Sch. 12 inserted (11.3.2024) by The Net Zero Teesside Order 2024 (S.I. 2024/174), art. 1, Sch. 3 para. 3 (with arts. 42, 43, Sch. 12)