Paragraph 31 Restoration of land used temporarily for constructionI1
England, Wales and Scotland
F1Within 12 months of bringing the authorised development into commercial use, a written scheme for the restoration of any land within the Order limits which has been used temporarily for construction will be submitted to the planning authority for approval.
The land must be restored within 12 months after F2the written scheme referred to in subparagraph (1) is approved, in accordance with—
the restoration scheme approved in accordance with subparagraph (1),
each landscaping scheme approved in accordance with requirement 7, and
the biodiversity enhancement and management plan approved in accordance with requirement 17.
Annotations
Textual amendments
- F1
Words in Sch. 2 para. 31(1) substituted (20.9.2018) by virtue of The Ferrybridge Multifuel 2 Power Station (Amendment) Order 2018 (S.I. 2018/1016), art. 1, 4, Sch.
- F2
Words in Sch. 2 para. 31(2) substituted (20.9.2018) by virtue of The Ferrybridge Multifuel 2 Power Station (Amendment) Order 2018 (S.I. 2018/1016), art. 1, 4, Sch.
Commencement
- I1
Sch. 2 para. 31 in force at 19.11.2015, see art. 1(2)