Schedule 3 MAXIMUM BUILDING DIMENSIONSI1
England, Wales and Scotland
| Building | Maximum length (metres) | Maximum width (metres) | Maximum height (metres above ordnance datum (Newlyn)) |
|---|---|---|---|
| Tipping hall (Work No. 1A) | 45 | 102 | 53 |
| Fuel storage bunker (Work No. 1A) | 42 | 102 | 64 |
| Entry ramp to fuel storage bunker (Work No. 1A) | 120 | 70 | 27 |
| Exit ramp from fuel storage bunker (Work No. 1A) | 120 | 70 | 27 |
| Boiler hall (Work No. 1A) | 63 | 60 | 74 |
| Turbine hall (Work No. 1A) | 40 | 40 | 44 |
| Ash storage bunker and collection bay (Work No. 1A) | 43 | 48 | 39 |
| Flue gas treatment system (Work No. 1A) | 55 | 82 | 56 |
| Air cooled condenser (Work No. 1A) | 98 | 40 | 41 |
| Electrical switchyard, including circuit breaker and transformer (Work No. 1A) | 40 | 15 | 31 |
| Workshop building (Work No. 1A) | 30 | 40 | 39 |
| Control and administrative building (Work No. 1A) | 15 | 55 | 64 |
| Security gatehouses and weighbridges (Work No. 1B) | 20 | 4 | 20 |
| Substation (Work No. 2C) | 90 | 55 | 36 |
Annotations
Commencement
- I1
Sch. 3 in force at 19.11.2015, see art. 1(2)