Schedule 4 MINIMUM BUILDING DIMENSIONSI1
England, Wales and Scotland
| Building | Minimum length (metres) | Minimum width (metres) | Minimum height (metres above ordnance datum (Newlyn)) |
|---|---|---|---|
| Tipping hall (Work No. 1A) | 31 | 58 | 31 |
| Fuel storage bunker (Work No. 1A) | 31 | 58 | 49 |
| Entry ramp to fuel storage bunker (Work No. 1A) | 55 | 25 | 24 |
| Exit ramp from fuel storage bunker (Work No. 1A) | 55 | 25 | 24 |
| Boiler hall (Work No. 1A) | 27 | 45 | 57 |
| Turbine hall (Work No. 1A) | 27 | 27 | 34 |
| Ash storage bunker and collection bay (Work No. 1A) | 13 | 13 | 29 |
| Flue gas treatment system (Work No. 1A) | 40 | 70 | 46 |
| Air cooled condenser (Work No. 1A) | 63 | 18 | 34 |
| Electrical switchyard, including circuit breaker and transformer (Work No. 1A) | 27 | 9 | 25 |
| Workshop building (Work No. 1A) | 10 | 15 | 26 |
| Control and administrative building (Work No. 1A) | 27 | 11 | 46 |
| Security gatehouses and weighbridges (Work No. 1B) | 10 | 2.5 | 19 |
| Substation (Work No. 2C) | 80 | 50 | 34 |