Paragraph 43 InterpretationI1

England and Wales

In this Part of this Schedule—

  • “Part 5 consultee” means one or more of the following bodies on matters relating to their function, where that body is not already the discharging authority or a consultee under the relevant paragraph in Part 1, Part 2 or Part 4 of this Schedule—

    1. (a)

      Buckinghamshire Council;

    2. (b)

      Central Bedfordshire Council;

    3. (c)

      Dacorum Borough Council;

    4. (d)

      the Environment Agency;

    5. (e)

      Hertfordshire County Council;

    6. (f)

      Historic England;

    7. (g)

      Luton Borough Council;

    8. (h)

      National Highways;

    9. (i)

      Natural England;

    10. (j)

      North Hertfordshire District Council;

    11. (k)

      the relevant sewerage undertaker; and

    12. (l)

      the relevant water undertaker;

  • “specified period” means a period of—

    1. (a)

      13 weeks for any application under paragraph 6 (detailed design) of Part 2 of this Schedule for detailed design approval of Works Nos. 3b(01), 3b(02), 3d, 3f, 3g and 4a;

    2. (b)

      8 weeks for all other applications for approval under Part 1, Part 2 or Part 4 of this Schedule; or

    3. (c)

      such longer period as may be agreed between the undertaker and the discharging authority.

Annotations

Commencement

I1

Sch. 2 para. 43 in force at 24.4.2025, see art. 1