Paragraph 43 InterpretationI1
England and Wales As made
In this Part of this Schedule—
-
“Part 5 consultee” means one or more of the following bodies on matters relating to their function, where that body is not already the discharging authority or a consultee under the relevant paragraph in Part 1, Part 2 or Part 4 of this Schedule—
-
Buckinghamshire Council;
-
Central Bedfordshire Council;
-
Dacorum Borough Council;
-
the Environment Agency;
-
Hertfordshire County Council;
-
Historic England;
-
Luton Borough Council;
-
National Highways;
-
Natural England;
-
North Hertfordshire District Council;
-
the relevant sewerage undertaker; and
-
the relevant water undertaker;
-
-
“specified period” means a period of—
-
13 weeks for any application under paragraph 6 (detailed design) of Part 2 of this Schedule for detailed design approval of Works Nos. 3b(01), 3b(02), 3d, 3f, 3g and 4a;
-
8 weeks for all other applications for approval under Part 1, Part 2 or Part 4 of this Schedule; or
-
such longer period as may be agreed between the undertaker and the discharging authority.
-
Annotations
Commencement
- I1
Sch. 2 para. 43 in force at 24.4.2025, see art. 1