Paragraph 43 InterpretationI1

England and Wales As made

In this Part of this Schedule—

  • “Part 5 consultee” means one or more of the following bodies on matters relating to their function, where that body is not already the discharging authority or a consultee under the relevant paragraph in Part 1, Part 2 or Part 4 of this Schedule—

    1. Buckinghamshire Council;

    2. Central Bedfordshire Council;

    3. Dacorum Borough Council;

    4. the Environment Agency;

    5. Hertfordshire County Council;

    6. Historic England;

    7. Luton Borough Council;

    8. National Highways;

    9. Natural England;

    10. North Hertfordshire District Council;

    11. the relevant sewerage undertaker; and

    12. the relevant water undertaker;

  • “specified period” means a period of—

    1. 13 weeks for any application under paragraph 6 (detailed design) of Part 2 of this Schedule for detailed design approval of Works Nos. 3b(01), 3b(02), 3d, 3f, 3g and 4a;

    2. 8 weeks for all other applications for approval under Part 1, Part 2 or Part 4 of this Schedule; or

    3. such longer period as may be agreed between the undertaker and the discharging authority.

Annotations

Commencement

I1

Sch. 2 para. 43 in force at 24.4.2025, see art. 1