Paragraph 4 Stages of authorised developmentI1

England, Wales and Scotland

(1)

The authorised development may not commence until a written scheme setting out the stages of the authorised development has been submitted to the relevant planning authority, which scheme may subsequently be amended from time to time as notified to the relevant planning authority.

(2)

The authorised development must be constructed in accordance with the written scheme setting out the stages of the authorised development submitted under paragraph (1).

Annotations

Commencement

I1

Sch. 3 para. 4 in force at 5.4.2024, see art. 1