OpenLegislation

Paragraph 5 Construction management plansI1

England, Wales and Scotland

(1)

All construction works for the authorised development must be carried out in accordance with the construction management plans referred to in paragraph (2), unless otherwise agreed with the relevant planning authority or the highway authority, as may be appropriate to the relevant plan, scheme or strategy concerned.

(2)

The construction management plans, which specify the measures to be used to minimise the impacts of construction works, are the following plans, schemes and strategies—

(a)

the code of construction practice;

(b)

the archaeological written scheme of investigation;

(c)

the biodiversity mitigation strategy;

(d)

the construction traffic management plan;

(e)

the public rights of way management plan; and

(f)

the noise and vibration management plan.

(3)

For the avoidance of doubt, all pre-commencement works must be carried out in accordance with the construction management plans and the outline soil management plan.

Annotations

Commencement

I1

Sch. 3 para. 5 in force at 5.4.2024, see art. 1