Paragraph 3 Phasing of the authorised schemeI1

England, Wales and Scotland

(1)

Taken together with works authorised and proposed to be constructed pursuant to licence 1 (transmission)—

(a)

the total number of offshore electrical platforms forming part of the authorised scheme must not exceed two;

(b)

the total amount of scour protection for the offshore electrical platforms forming part of the authorised scheme must not exceed 20,000m2 and 100,000 m3; and

(c)

the total amount of inert material of natural origin disposed within the offshore Order limits as part of the authorised scheme must not exceed 11,475,000 m3;

(d)

the total amount of disposal for drill arisings in connection with any foundation drilling must not exceed 14,137 m3;

(e)

the total length of cable and the amount of cable protection must not exceed the figures stated in condition 2 of this licence; and

(f)

in the Haisborough, Hammond and Winterton Special Area of Conservation, the total area of cable protection must not exceed 32,000m² and the total volume of cable protection must not exceed 20,800m³.

(2)

Prior to the commencement of the authorised scheme the undertaker must give notice to the MMO detailing—

(a)

whether the authorised scheme will be constructed—

(i)

in a single offshore phase under this licence; or

(ii)

in two offshore phases under this licence and licence 1 (transmission); and

(b)

where the authorised scheme will be constructed in two offshore phases, the total number of offshore electrical platforms to be constructed in each phase.