OpenLegislation

The Norfolk Vanguard Offshore Wind Farm Order 2020

S.I. 2020/706 · Made 1 July 2020 · Extends to England, Wales and Scotland

Up to date with all changes known to legislation.gov.uk, revised to 3 May 2023.

Infrastructure Planning

Made 1st July 2020

Coming into force 22nd July 2020

An application has been made to the Secretary of State for an order under section 37 of the Planning Act 2008 (“the 2008 Act”)(f1) for an order granting development consent.

The application was examined by the Examining Authority appointed by the Secretary of State pursuant to section 61f2 and 65f3 of Part 6 of the 2008 Act and carried out in accordance with Chapter 4 of that Act and with the Infrastructure Planning (Examination Procedure) Rules 2010f4. The Examining Authority has submitted a report to the Secretary of State under section 74(2)f5 of the 2008 Act.

The Secretary of State has considered the report and recommendation of the Examining Authority, has taken into account the environmental information in accordance with regulation 3 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2009f6 and, as a national policy statement has effect in relation to the proposed development, has had regard to the documents and matters referred to in section 104(2)(f7 of the 2008 Act.

The Secretary of State, having decided the application, has determined to make an Order giving effect to the proposals comprised in the application on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.

The Secretary of State is satisfied that open space comprised within the Order land, when burdened with the new rights authorised for compulsory acquisition under the terms of this Order, will be no less advantageous than it was before such acquisition, to the persons in whom it is vested, other persons, if any, entitled to rights of common or other rights, and the public and that, accordingly, section 132(3)f8 of the 2008 Act applies;

The Secretary of State in exercise of the powers conferred by sections 114, 115, 120f9, and 149A of the 2008 Act the Secretary of State makes the following Order—

Annotations to the whole text

Footnotes

f1

2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20).

f2

Section 61 was amended by section 128(2) and Schedule 13, paragraph 18 to the Localism Act 2011 and by section 26 of the Infrastructure Act 2015 (c. 7). Section 65 was amended by Schedule 13 paragraph 22(2) and Schedule 25, paragraph 1 to the Localism Act 2011 and by section 27(1) of the Infrastructure Act 2015.

f3

Section 65 was amended by Schedule 13 paragraph 22(2) and Schedule 25, paragraph 1 to the Localism Act 2011 and by section 27(1) of the Infrastructure Act 2015.

f4

S.I. 2010/103, amended by S.I. 2012/635.

f5

Section 74 was amended by sections 128(2) and 237 and by Schedule 13, paragraph 29 and Schedule 25, paragraph 1, to the Localism Act 2011.

f6

S.I. 2009/2263. Regulation 3 was amended by S.I. 2012/635 and S.I. 2012/787. S.I. 2009/2263 was revoked by S.I. 2017/572, but continues to apply to this application for development consent by virtue of transitional provisions contained in regulation 37(2) of that instrument.

f7

Section 104 was amended by section 58(5) of the Marine and Coastal Access Act 2009 (c. 23) and by section 128(2) of the and Schedule 13, paragraphs 1 and 49(1) to (6) of the Localism Act 2011.

f8

Section 132 was amended by section 24(3) of the Growth and Infrastructure Act 2013 (c. 27).

f9

Sections 114,115 and 120 were amended by sections 128(2) and 140 and Schedule 13, paragraphs 1, 55(1), (2) and 60(1) and (3) of the Localism Act 2011. Relevant amendments were made to section 115 by section 160(1) to (6) of the Housing and Planning Act 2016 (c. 22).

Contents

  1. Part 1: Preliminary
  2. 1Citation and commencement
  3. 2Interpretation
  4. Part 2: Principal Powers
  5. 3Development consent etc. granted by the Order
  6. 4Limits of deviation
  7. 5Power to construct and maintain authorised project
  8. 6Benefit of the Order
  9. 7Application and modification of legislative provisions
  10. 8Defence to proceedings in respect of statutory nuisance
  11. Part 3: Streets
  12. 9Street works
  13. 10Public rights of way
  14. 11Temporary stopping up of streets
  15. 12Access to works
  16. 13Agreements with street authorities
  17. 14Application of the 1991 Act
  18. Part 4: Supplemental Powers
  19. 15Discharge of water and works to watercourses
  20. 16Authority to survey and investigate the land onshore
  21. 17Removal of human remains
  22. Part 5: Powers of Acquisition
  23. 18Compulsory acquisition of land
  24. 19Time limit for exercise of authority to acquire land compulsorily
  25. 20Compulsory acquisition of rights
  26. 21Private rights
  27. 22Application of the 1981Act
  28. 23Application of Part 1 of the Compulsory Purchase Act 1965
  29. 24Acquisition of subsoil or airspace only
  30. 25Rights under or over streets
  31. 26Temporary use of land for carrying out the authorised project
  32. 27Temporary use of land for maintaining authorised project
  33. 28Extinguishment of private rights and restrictive covenants relating to apparatus removed from land subject to temporary possession
  34. 29Statutory undertakers
  35. 30Recovery of costs of new connections
  36. Part 6: Operations
  37. 31Operation of generating station
  38. 32Deemed marine licences under the 2009 Act
  39. Part 7: Miscellaneous and General
  40. 33Application of landlord and tenant law
  41. 34Operational land for purposes of the 1990 Act
  42. 35Felling or lopping of trees and removal of hedgerows
  43. 36Trees subject to tree preservation orders
  44. 37Certification of plans etc
  45. 38Arbitration
  46. 39Procedure in relation to certain approvals etc
  47. 40Abatement of works abandoned or decayed
  48. 41Saving provisions for Trinity House
  49. 42Crown rights
  50. 43Protective provisions
  51. Signature
  52. Schedule 1: Authorised Project
  53. 1Authorised Development
  54. 1Paragraph 1
  55. Part 2: Ancillary Works
  56. Part 3: Requirements
  57. 2Detailed offshore design parameters
  58. 3Detailed offshore design parameters
  59. 4Detailed offshore design parameters
  60. 5Detailed offshore design parameters
  61. 6Detailed offshore design parameters
  62. 7Detailed offshore design parameters
  63. 8Detailed offshore design parameters
  64. 9Detailed offshore design parameters
  65. 10Detailed offshore design parameters
  66. 11Detailed offshore design parameters
  67. 12Aviation safety
  68. 13Ministry of Defence surveillance operations
  69. 14Offshore decommissioning
  70. 15Stages of authorised development onshore
  71. 16Detailed design parameters onshore
  72. 17Landfall method statement
  73. 18Provision of landscaping
  74. 19Implementation and maintenance of landscaping
  75. 20Code of construction practice
  76. 21Traffic
  77. 22Highway accesses
  78. 23Archaeological written scheme of investigation
  79. 24Ecological management plan
  80. 25Watercourse crossings
  81. 26Construction hours
  82. 27Control of noise during operational phase and during maintenance
  83. 28European protected species onshore
  84. 29Onshore decommissioning
  85. 30Requirement for written approval
  86. 31Amendments to approved details
  87. 32Operational drainage plan
  88. 33Skills and employment strategy
  89. 34Cromer Primary Surveillance Radar
  90. Schedule 2Streets subject to Street Works
  91. Schedule 3Public Rights of Way to be temporarily stopped up
  92. Schedule 4Streets to be stopped up
  93. Schedule 5Access to Works
  94. Schedule 6Land in which only New Rights etc., may be acquired
  95. Schedule 7: Modification of compensation and compulsory purchase enactments for creation of new rights
  96. 1Paragraph 1
  97. 2Paragraph 2
  98. 3Paragraph 3
  99. 4Paragraph 4
  100. 5Paragraph 5
  101. 6Paragraph 6
  102. 7Paragraph 7
  103. 8Paragraph 8
  104. 9Paragraph 9
  105. Schedule 8Land of which temporary possession may be taken
  106. Schedule 9: Deemed Licence under the 2009 Act – Generation Assets (Licence 1 – Phase 1)
  107. Part 1: Interpretation
  108. 1Paragraph 1
  109. 2Paragraph 2
  110. 3Paragraph 3
  111. 4Paragraph 4
  112. Part 2: Licensed Marine Activities – General
  113. 5Paragraph 5
  114. 6Paragraph 6
  115. Part 3: Details of Licensed Marine Activities
  116. Part 4: Conditions
  117. 7Design parameters
  118. 8Phasing of the authorised scheme
  119. 9Notifications and inspections
  120. 10Aids to navigation
  121. 11Colouring of structures
  122. 12Chemicals, drilling and debris
  123. 13Force majeure
  124. 14Pre-construction plans and documentation
  125. 15Pre-construction plans and documentation
  126. 16Post-construction plans and documents
  127. 17Reporting of engaged agents, contractors and vessels
  128. 18Pre-construction monitoring and surveys
  129. 19Construction monitoring
  130. 20Post construction
  131. 21Reporting of impact pile driving
  132. 22Reporting of cable protection
  133. 23Decommissioning of cable protection within marine protected areas
  134. Schedule 10: Deemed Licence under the 2009 Act – Generation Assets (Licence 2 – Phase 2)
  135. Part 1: Interpretation
  136. 1Paragraph 1
  137. 2Paragraph 2
  138. 3Paragraph 3
  139. 4Paragraph 4
  140. Part 2: Licensed Marine Activities – General
  141. 5Paragraph 5
  142. 6Paragraph 6
  143. Part 3: Details of Licensed Marine Activities
  144. Part 4: Conditions
  145. 7Design parameters
  146. 8Phasing of the authorised scheme
  147. 9Notifications and inspections
  148. 10Aids to navigation
  149. 11Colouring of structures
  150. 12Chemicals, drilling and debris
  151. 13Force majeure
  152. 14Pre-construction plans and documentation
  153. 15Pre-construction plans and documentation
  154. 16Post-construction plans and documents
  155. 17Reporting of engaged agents, contractors and vessels
  156. 18Pre-construction monitoring and surveys
  157. 19Construction monitoring
  158. 20Post construction
  159. 21Reporting of impact pile driving
  160. 22Reporting of cable protection
  161. 23Decommissioning of cable protection within marine protected areas
  162. Schedule 11: Deemed Licence under the 2009 Act – Transmission Assets (Licence 1 – Phase 1)
  163. Part 1: Interpretation
  164. 1Paragraph 1
  165. Part 2: Licensed Marine Activities – General
  166. 2Paragraph 2
  167. 3Paragraph 3
  168. 4Paragraph 4
  169. 5Paragraph 5
  170. 6Paragraph 6
  171. Part 3: Details of Licensed Marine Activities
  172. Part 4: Conditions
  173. 7Chemicals, drilling and debris
  174. 8Force majeure
  175. 9Pre-construction plans and documentation
  176. 10Pre-construction plans and documentation
  177. 11Post-construction plans and documents
  178. 12Reporting of engaged agents, contractors and vessels
  179. 13Pre-construction monitoring and surveys
  180. 14Construction monitoring
  181. 15Post construction
  182. 16Reporting of impact pile driving
  183. 17Reporting of cable protection
  184. 18Restriction on cable installation construction works
  185. 19Decommissioning of cable protection within marine protected areas
  186. Schedule 12: Deemed Licence under the 2009 Act – Transmission Assets (Licence 2 – Phase 2)
  187. Part 1: Interpretation
  188. 1Paragraph 1
  189. Part 2: Licensed Marine Activities – General
  190. 2Paragraph 2
  191. 3Paragraph 3
  192. 4Paragraph 4
  193. 5Paragraph 5
  194. 6Paragraph 6
  195. Part 3: Details of Licensed Marine Activities
  196. Part 4: Conditions
  197. 7Chemicals, drilling and debris
  198. 8Force majeure
  199. 9Pre-construction plans and documentation
  200. 10Pre-construction plans and documentation
  201. 11Post-construction plans and documents
  202. 12Reporting of engaged agents, contractors and vessels
  203. 13Pre-construction monitoring and surveys
  204. 14Construction monitoring
  205. 15Post construction
  206. 16Reporting of impact pile driving
  207. 17Reporting of cable protection
  208. 18Restriction on cable installation construction works
  209. 19Decommissioning of cable protection within marine protected areas
  210. Schedule 13: Hedgerows
  211. 1Removal of Potentially Important Hedgerows
  212. 2Removal of Important Hedgerows
  213. 3Removal of Hedgerows
  214. Schedule 14: ARBITRATION RULES
  215. 1Primary objective
  216. 2Time periods
  217. 3Timetable
  218. 4Procedure
  219. 5Arbitrator’s powers
  220. 6Costs
  221. 7Confidentiality
  222. Schedule 15: Procedure for discharge of Requirements
  223. 1Applications made under requirement
  224. 2Further information
  225. 3Appeals
  226. 4Interpretation of this Schedule
  227. Schedule 16: PROTECTIVE PROVISIONS
  228. Part 1: Protection for electricity, gas, water and sewerage undertakers
  229. 1Paragraph 1
  230. 2Paragraph 2
  231. 3Paragraph 3
  232. 4Paragraph 4
  233. 5Paragraph 5
  234. 6Paragraph 6
  235. 7Paragraph 7
  236. 8Paragraph 8
  237. 9Paragraph 9
  238. 10Paragraph 10
  239. 11Paragraph 11
  240. Part 2: For the Protection of National Grid as Electricity and Gas Undertaker
  241. 12Application
  242. 13Interpretation
  243. 14Interpretation
  244. 15Apparatus of Undertakers in stopped up streets
  245. 16Acquisition of land
  246. 17Removal of apparatus
  247. 18Facilities and rights for alternative apparatus
  248. 19Retained apparatus: protection Gas Undertakers
  249. 20Retained apparatus: protection Electricity Undertakers
  250. 21Expenses
  251. 22Compensation
  252. 23Enactments and agreements
  253. 24Co-operation
  254. 25Access
  255. 26Arbitration
  256. 27Notices
  257. Part 3: For the Protection of Cadent Gas Limited as Gas Undertaker
  258. 28Application
  259. 29Interpretation
  260. 30On Street Apparatus
  261. 31Apparatus of Undertakers in stopped up streets
  262. 32Acquisition of land
  263. 33Removal of apparatus
  264. 34Facilities and rights for alternative apparatus
  265. 35Retained apparatus: protection Gas Undertakers
  266. 36Expenses
  267. 37Compensation
  268. 38Enactments and agreements
  269. 39Co-operation
  270. 40Access
  271. 41Arbitration
  272. 42Notices
  273. Part 4: Protection for Operators of Electronic Communications Code Networks
  274. 43Paragraph 43
  275. 44Paragraph 44
  276. 45Paragraph 45
  277. 46Paragraph 46
  278. 47Paragraph 47
  279. Part 5: Protection of Network Rail Infrastructure Limited
  280. 48Paragraph 48
  281. 49Paragraph 49
  282. 50Paragraph 50
  283. 51Paragraph 51
  284. 52Paragraph 52
  285. 53Paragraph 53
  286. 54Paragraph 54
  287. 55Paragraph 55
  288. 56Paragraph 56
  289. 57Paragraph 57
  290. 58Paragraph 58
  291. 59Paragraph 59
  292. 60Paragraph 60
  293. 61Paragraph 61
  294. 62Paragraph 62
  295. 63Paragraph 63
  296. 64Paragraph 64
  297. 65Paragraph 65
  298. 66Paragraph 66
  299. 67Paragraph 67
  300. 68Paragraph 68
  301. 69Paragraph 69
  302. Part 6: For the Protection of Anglian Water Services Limited
  303. 70Paragraph 70
  304. Part 7: For the protection of the Environment Agency and drainage authorities
  305. 71Paragraph 71
  306. 72Paragraph 72
  307. 73Paragraph 73
  308. 74Paragraph 74
  309. 75Paragraph 75
  310. 76Paragraph 76
  311. 77Paragraph 77
  312. 78Paragraph 78
  313. 79Paragraph 79
  314. 80Paragraph 80
  315. 81Paragraph 81
  316. Part 8: For the protection of Ørsted Hornsea Project Three (UK) Ltd
  317. 82Paragraph 82
  318. 83Paragraph 83
  319. 84Paragraph 84
  320. 85Paragraph 85
  321. 86Paragraph 86
  322. 87Paragraph 87
  323. 88Paragraph 88
  324. 89Paragraph 89
  325. 90Paragraph 90
  326. 91Paragraph 91
  327. 92Paragraph 92
  328. 93Paragraph 93
  329. 94Paragraph 94
  330. 95Paragraph 95
  331. 96Paragraph 96
  332. 97Paragraph 97
  333. Explanatory note