Schedule 2 REQUIREMENTS
England and Wales
- 1Time limits
- 2Authorised development to be carried out in accordance with certified plans and documents and with matters approved under requirements
- 3Construction Environmental Management Plan
- 4Approval of details
- 5Control of noise during solution mining and gas operation
- 6Landscaping
- 7Accesses to works
- 8Construction traffic
- 9Limits on heavy goods vehicle movements
- 10Internal roads
- 11Fencing and other means of enclosure
- 12Ground and surface water and pollution prevention
- 13Hedgerows
- 14Land Contamination
- 15Archaeology
- 16External lighting
- 17Restoration scheme
- 18Decommissioning
- 19Requirement for written approval
- 20Amendments to approved details
- 21European protected species
- 22Conveyance of gas, water and brine
- 23Environmental management system for normal operation
- 24Control of radio emissions