The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014
S.I. 2014/2384 · Made 3 September 2014 · Extends to England and Wales
Infrastructure Planning
Made 3rd September 2014
Coming into force 24th September 2014
The Examining authority appointed by the Secretary of State examined the application in accordance with Chapter 4 of Part 6 of that Act and made a recommendation under section 74 of that Act that the application should be granted.
Accordingly, the Secretary of State, having the function of deciding the application, in exercise of the powers conferred by sections 103, 114, 115, 120, 122 and 123 of that Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
- f2
Contents
- Part 1: PRELIMINARY
- 1Citation and Commencement
- 2Interpretation
- Part 2: WORKS PROVISIONS
- Principal powers
- 3Development consent etc. granted by the Order
- 4Authorisation of use
- 5Maintenance of authorised project
- 6Limits of Deviation
- 7Defence to proceedings in respect of statutory nuisance
- Benefit of order
- 8Benefit of Order
- 9Transfer of benefit of Order
- Streets and traffic regulations
- 10Street works
- 11Power to alter layout, etc., of streets
- 12Construction and maintenance of altered streets
- 13Stopping up of streets
- 14Public rights of way and permissive paths
- 15Temporary stopping up
- 16Access to works
- 17Agreements with street authorities
- 18Traffic regulation
- Supplemental powers
- 19Discharge of water
- 20Protective works to buildings and structures
- 21Remedial works to buildings, or apparatus or equipment
- 22Authority to survey and investigate the land
- 23Removal of human remains
- 24Cemex
- 25Felling or lopping of trees
- 26Trees subject to tree preservation orders
- 27Trees in conservation areas
- Part 3: ACQUISITION AND POSSESSION OF LAND
- Powers of acquisition
- 28Compulsory acquisition of land
- 29Compulsory acquisition of rights
- 30Acquisition of subsoil only
- 31Acquisition of land limited to subsoil lying more than 9 metres beneath surface
- 32Power to override easements and other rights
- 33Statutory authority to override easements and other rights
- 34Application of the Compulsory Purchase (Vesting Declarations) Act 1981
- Temporary possession of land
- 35Temporary use of land for carrying out the authorised project
- 36Temporary use of land for maintaining authorised project
- Compensation
- 37Disregard of certain interests and improvements
- 38Set-off for enhancement in value of retained land
- 39No double recovery
- 40Compulsory acquisition of land – incorporation of the mineral code
- Supplementary
- 41Acquisition of part of certain properties
- 42Statutory undertakers
- 43Apparatus and rights of statutory undertakers in stopped-up streets
- 44Recovery of costs of new connections
- 45Time limit for exercise of authority to acquire land compulsorily
- 46Private rights of way
- 47Public rights of navigation
- 48Rights under or over streets and city walkways
- Part 4: MISCELLANEOUS AND GENERAL
- 49Application of landlord and tenant law
- 50Deemed marine licence
- 51Miscellaneous provisions relating to the 1990 Act
- 52Safeguarding
- 53Provisions for protection of specified undertakers
- 54Discharge of requirements etc.
- 55Removal of consent requirements
- 56Application, disapplication and modification of legislative provisions
- 57Amendment of local legislation
- 58Application of pipe subways legislation
- 59Other legislation in the City of London
- 60Unilateral undertaking – Project-wide matters
- 61Certification of plans etc
- 62Meaning of Secretary of State
- 63Arbitration
- Signature
- Schedule 1: AUTHORISED PROJECT
- 1AUTHORISED DEVELOPMENT
- 2ANCILLARY WORKS
- Schedule 2: PLANS
- 1WORKS PLANS
- 2LAND PLANS
- 3ACCESS PLANS
- 4APPROVED PLANS
- Schedule 3: REQUIREMENTS
- 1Interpretation
- 2Project-wide requirements
- 3Acton Storm Tanks
- 4Hammersmith Pumping Station
- 5Barn Elms
- 6Putney Embankment Foreshore
- 7Carnwath Road Riverside
- 8Dormay Street
- 9King George’s Park
- 10Falconbrook Pumping Station
- 11Cremorne Wharf Depot
- 12Chelsea Embankment Foreshore
- 13Kirtling Street
- 14Heathwall Pumping Station
- 15Albert Embankment Foreshore
- 16Victoria Embankment Foreshore
- 17Blackfriars Bridge Foreshore
- 18Shad Thames Pumping Station
- 19Chambers Wharf
- 20Earl Pumping Station
- 21Deptford Church Street
- 22Greenwich Pumping Station
- 23King Edward Memorial Park Foreshore
- 24Bekesbourne Street
- 25Abbey Mills Pumping Station
- 26Beckton Sewage Treatment Works
- Schedule 4STREETS SUBJECT TO STREET WORKS
- Schedule 5STREETS SUBJECT TO ALTERATION OF LAYOUT
- Schedule 6STREETS TO BE STOPPED UP
- Schedule 7PUBLIC RIGHTS OF WAY AND PERMISSIVE PATHS TO BE EXTINGUISHED
- Schedule 8STREETS AND RIGHTS OF WAY ETC. TO BE TEMPORARILY STOPPED UP
- Schedule 9ACCESS TO WORKS
- Schedule 10: TRAFFIC REGULATION
- 1TEMPORARY
- 2PERMANENT
- Schedule 11PROTECTIVE WORKS
- Schedule 12PUBLIC RIGHTS OF NAVIGATION TO BE AFFECTED BY THE AUTHORISED PROJECT
- Schedule 13LAND OF WHICH ONLY SUBSOIL MORE THAN 9 METRES BENEATH THE SURFACE MAY BE ACQUIRED
- Schedule 14LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- Schedule 15: DEEMED MARINE LICENCE
- Part 1: GENERAL
- 1Interpretation
- 2Contacts
- 3Details of Licensed Marine Activities
- Part 2: CONDITIONS APPLYING TO CONSTRUCTION ACTIVITIES
- Chapter: NOTIFICATIONS AND INSPECTIONS
- 4Notice of Transfer of Benefit
- 5Notification of person responsible for the carrying out of licensed activity
- 6Paragraph 6
- 7Prior Approval of Licensed Activities
- 8Scour and Accretion Monitoring and Mitigation
- 9Construction Environment Management Plan
- 10Concrete and Cement
- 11Coatings and Treatments
- 12Spills etc.
- 13Percussive Piling
- 14Agents, Contractors and Sub-Contractors
- 15Vessels
- 16Notice of Completion of Licensed Activity
- 17Changes to this Licence
- Part 3: PROCEDURE FOR THE DISCHARGE OF CONDITIONS
- 18Meaning of “application”
- 19Further information regarding application
- 20Determination of application
- 21Notice of Determination
- 22Arbitration
- Schedule 16: PROVISIONS FOR PROTECTION OF SPECIFIED UNDERTAKERS
- Part 1: ELECTRICITY AND GAS UNDERTAKERS
- Chapter SECTION 1: National Grid electricity and gas
- 1Application
- 2Interpretation
- 3Interpretation
- 4Apparatus of Undertakers in stopped up streets
- 5Protective works to buildings
- 6Acquisition of land
- 7Removal of apparatus
- 8Approval of plans for Alternative Apparatus
- 9Facilities and rights for alternative apparatus
- 10Retained apparatus: protection Gas Undertakers
- 11Retained apparatus: Protection: Electricity Undertakers
- 12Expenses
- 13Indemnity
- 14Ground subsidence monitoring scheme in respect of Undertaker’s apparatus
- 15Enactments and agreements
- 16Co-operation
- 17Access
- 18Arbitration
- Chapter SECTION 2: London Power Networks plc
- 1Application
- 2Interpretation
- 3Interpretation
- 4Temporarily stopped up streets
- 5Protective works to buildings
- 6Acquisition of land
- 7Removal of apparatus
- 8Facilities and rights for alternative apparatus
- 9Retained apparatus— protection
- 10Expenses
- 11Compensation
- 12Enactments and agreements
- 13Co-operation
- 14Access
- 15Arbitration
- Chapter SECTION 3: Other electricity undertakers
- 1Application
- 2Interpretation
- 3Interpretation
- 4Temporarily stopped up streets
- 5Protective works to buildings
- 6Removal of apparatus
- 7Facilities and rights for alternative apparatus
- 8Retained apparatus— protection
- 9Expenses
- 10Enactments and agreements
- 11Co-operation
- 12Access
- 13Arbitration
- Chapter SECTION 4: Other gas undertakers
- 1Application
- 2Interpretation
- 3Interpretation
- 4Temporarily stopped up streets
- 5Protective works to buildings
- 6Removal of apparatus
- 7Facilities and rights for alternative apparatus
- 8Retained apparatus— protection
- 9Expenses
- 10Enactments and agreements
- 11Co-operation
- 12Access
- 13Arbitration
- Part 2: THE PORT OF LONDON AUTHORITY
- 1Paragraph 1
- 2Paragraph 2
- 3Definitions
- 4Time limits
- 5Tidal works: approval of detailed design
- 6Public rights of navigation
- 7General provision as to construction of works including inspection
- 8Works to river banks
- 9Discharges etc.
- 10Navigational lights, buoys, etc
- 11Removal etc of the Authority’s moorings and buoys
- 12Removal of temporary works
- 13Survey of river bed
- 14Sedimentation, etc: remedial action
- 15Protective action
- 16Obstruction in the river
- 17Scour monitoring and mitigation
- 18Abandoned or Decayed Works
- 19Permanent works where land not acquired
- 20Facilities for navigation
- 21Indemnities, costs and exercise of DCO powers and compensation
- 22Maintenance dredging
- 23Notifications
- 24Disputes
- Part 3: THE ENVIRONMENT AGENCY
- 1Paragraph 1
- 2Paragraph 2
- 3Definitions
- 4Structural integrity of flood defences
- 5Approvals
- 6Inspection and construction
- 7Protection of drainage works and flood defences
- 8Scour and accretion monitoring and mitigation
- 9Maintenance of flood defences
- 10Emergency Powers
- 11Approval of Construction Environment Management Plan
- 12Protection for Fish and Fisheries
- 13Dispute Resolution
- 14Indemnities and Costs
- 15Notices
- Part 4: TRANSPORT FOR LONDON
- Chapter SECTION 1: Protection of TfL Railway Companies
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 3AParagraph 3A
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Third party and other costs
- 15Third party and other costs
- Chapter SECTION 2: For the Protection of London River Services Limited
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 3AParagraph 3A
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- Chapter SECTION 3: Protection for Highways Structures
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 3AParagraph 3A
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- Chapter SECTION 4: Protection for Highways and Traffic
- 1Paragraph 1
- 2Paragraph 2
- Part 5: NETWORK RAIL
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- 17Paragraph 17
- 18Paragraph 18
- 19Paragraph 19
- 20Paragraph 20
- 21Paragraph 21
- Part 6: COMMUNICATIONS NETWORK OPERATORS
- 1Effect
- 2Interpretation
- 3Electronic communications apparatus installed on, under or over any land
- 4Enactments and agreements in respect of apparatus in the promoter’s land
- 5Temporary and Permanent stopping up of streets forming part of the public maintainable highway
- 6Indemnity
- 7Arbitration
- Part 7: THE CITY OF LONDON CORPORATION
- 1Application
- 2Interpretation
- 3Protective works
- 4Remedial works
- 5Inspection and monitoring
- 6Damages, costs and indemnification
- 7Dispute resolution
- Schedule 17: PROCEDURE FOR DISCHARGE OF REQUIREMENTS ETC. AND APPEALS
- 1Applications made under requirements
- 2Further information regarding requirements
- 3Fees further to requirements
- 4Appeals
- Schedule 18REMOVAL OF CONSENT REQUIREMENTS
- Schedule 19: MISCELLANEOUS CONTROLS
- Part 1: PUBLIC GENERAL LEGISLATION
- 1Introduction
- 2Highways Act 1980
- 3Building Act 1984
- 4New Roads and Street Works Act 1991
- 5Water Industry Act 1991
- 6Party Wall etc. Act 1996
- 7Planning Act 2008 - Application of the 2010 Regulations (Community Infrastructure Levy)
- 8Local Government (Miscellaneous Provisions) Act 1976
- 9Town and Country Planning Act 1990
- 10Coast Protection Act 1949
- 11Flood and Water Management Act 2010
- 12National Parks and Access to Countryside Act 1949
- 13Control of Pollution Act 1974
- 2LOCAL LEGISLATION
- Explanatory note