Section 104 Emergency safety noticesI1
This section applies if it appears to an enforcement authority that serious interference with legitimate uses of the sea is occurring, or is likely to occur, in its area as a result of—
any works for the carrying out of which a marine licence is or was needed, or
any substantial and unforeseen change in the state or position of any such works.
The enforcement authority may issue a notice (an “emergency safety notice”) to any person who is in control of the works to which the notice relates.
By issuing an emergency safety notice to a person, the enforcement authority imposes on that person such requirements as are prescribed in the notice with respect to any of the matters specified in subsection (4).
Those matters are—
the provision of lights, signals or other aids to navigation;
the stationing of guard ships.
An emergency safety notice (in addition to specifying the requirements which it imposes)—
must state the enforcement authority's grounds for believing that serious interference with legitimate uses of the sea is occurring or is likely to occur,
must state the date and time from which the requirements are to take effect (which may be a time on the date of the notice but must allow a period for compliance which is reasonable in all the circumstances of the case), and
may require the person to take such steps as the authority considers appropriate to ensure that compliance with the requirements takes place safely.
Annotations
Commencement
- I1
S. 104 in force at 6.4.2011 by S.I. 2011/556, art. 3(2)(a)
Notes on Part 4
Modifications
- C1
Pt. 4 excluded (11.3.2015) by The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 (S.I. 2015/318), arts. 1, 8(6) (with arts. 40, 41, Pt. 2 para. 4(2), Pt. 2 para. 4(3), Pt. 2 para. 19, Pt. 4 para. 3, Pt. 4 para. 4, Pt. 4 para. 16, Sch. 12 paras. 4, 9(2), 10)
- C2
Pt. 4 excluded (26.8.2015) by The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (S.I. 2015/1592), arts. 1, 8(7) (with arts. 40, 41)
- C3
Pt. 4 modified (7.9.2016) by The Hornsea Two Offshore Wind Farm Order 2016 (S.I. 2016/844), arts. 1(2), 36 (with arts. 37, 38)
- C4
Pt. 4 modified (15.9.2016) by The River Humber Gas Pipeline Replacement Order 2016 (S.I. 2016/853), arts. 1, 39 (with art. 43)
- C5
Pt. 4 modified (22.1.2021) by The Hornsea Three Offshore Wind Farm Order 2020 (S.I. 2020/1656), arts. 1, 31 (with arts. 40, 41, Sch. 9 Pt. 5 para. 18)
- C6
Pt. 4 applied (E.W.S) (1.1.2022) by The Norfolk Boreas Offshore Wind Farm Order 2021 (S.I. 2021/1414), arts. 1, 32 (with arts. 41, 42, Sch. 17 para. 66)
- C7
Pt. 4 applied (E.W.S.) (5.3.2022) by The Norfolk Vanguard Offshore Wind Farm Order 2022 (S.I. 2022/138), arts. 1, 32 (with arts. 41, 42, Sch. 16)
- C8
Pt. 4 modified (29.12.2022) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022 (S.I. 2022/1396), arts. 1, 39 (with art. 32, Sch. 10 paras. 26(2), 68)
- C9
Pt. 4 modified (28.4.2025) by The Rampion 2 Offshore Wind Farm Order 2025 (S.I. 2025/468), arts. 1, 39 (with arts. 47, 48, Sch. 10)
- C10
Pt. 4 modified (28.7.2025) by The Mona Offshore Wind Farm Order 2025 (S.I. 2025/870), arts. 1, 5 (with arts. 37, 38, Sch. 10)
- C11
Pt. 4 modified (22.9.2025) by The Morgan Offshore Wind Project Generation Assets Order 2025 (S.I. 2025/1012), arts. 1, 5 (with arts. 9, 10)
- C12
Pt. 4 modified (27.11.2025) by The Cory Decarbonisation Project Order 2025 (S.I. 2025/1227), arts. 1, 42(1) (with Sch. 12)
- C13
Pt. 4 modified (23.12.2025) by The Morecambe Offshore Windfarm Generation Assets Order 2025 (S.I. 2025/1366), arts. 1, 5 (with arts. 9, 10)
- C14
Pt. 4 modified (8.1.2026) by The Five Estuaries Offshore Wind Farm Order 2025 (S.I. 2025/1376), arts. 1, 5 (with arts. 39, 40, Sch. 9)
- C15
Pt. 4: power to amend or modify conferred (12.2.2026) by Biodiversity Beyond National Jurisdiction Act 2026 (c. 6), ss. 22(3), 32(1) (with s. 30)
- C16
Pt. 4 modified (5.6.2026) by The North Falls Offshore Wind Farm Order 2026 (S.I. 2026/567), arts. 1, 35 (with arts. 44, 45, Sch. 14)
- C17
Pt. 4 modified (5.6.2026) by The Dogger Bank South East and West Offshore Wind Farms Order 2026 (S.I. 2026/577), arts. 1, 35 (with arts. 40, 41, Sch. 15)