The Knottingley Power Plant Order 2015
S.I. 2015/680 · Made 10 March 2015 · Extends to England and Wales
Infrastructure Planning
Made 10th March 2015
Coming into force 1st April 2015
The application was examined by a single appointed person (appointed by the Secretary of State) in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3.
The single appointed person, having considered the representations made and not withdrawn and the application together with the accompanying documents, in accordance with section 83 of the 2008 Act, has submitted a report to the Secretary of State.
The Secretary of State, having considered the report and recommendation of the single appointed person, and decided the application, has determined to make an Order giving effect to the proposals comprised in the application with modifications which in the opinion of the Secretary of State do not make any substantial change to the proposals.
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 147 of the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
S.I. 2009/2264 as amended by the Localism Act 2011 (Infrastructure Planning) (Consequential Amendments) Regulations 2012 (S.I. 2012/635) and the Infrastructure Planning (Prescribed Consultees and Interested Parties etc) (Amendment) Regulations 2013 (S.I. 2013/522). There are other amendments to the Regulations which are not relevant to this Order.
- f2
-
2008 c.29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of, and Schedule 13 to, the Localism Act 2011 (c.20), and by sections 22 to 27 of the Growth and Infrastructure Act 2013 (c.27), see S.I. 2013/1124 for transitional provisions.
- f3
-
S.I. 2010/103, as amended by S.I. 2012/635.
Contents
- Part 1: PRELIMINARY
- 1Citation and commencement
- 2Interpretation
- Part 2: PRINCIPAL POWERS
- 3Development consent etc. granted by the Order
- 4Power to maintain authorised development
- Part 3: OPERATIONS
- 5Operation of generating station
- 6Limits of deviation
- 7Benefit of the Order
- 8Application and modification of legislative provisions
- 9Defence to proceedings in respect of statutory nuisance
- Part 4: STREETS
- 10Street works
- 11Stopping up of street
- 12Public rights of way
- 13Access to works
- 14Agreements with street authorities
- Part 5: SUPPLEMENTAL POWERS
- 15Discharge of water
- 16Authority to survey and investigate the land
- 17Removal of human remains
- Part 6: POWERS OF ACQUISITION
- 18Compulsory acquisition of land
- 19Compulsory acquisition of land – incorporation of the minerals code
- 20Time limit for exercise of authority to acquire land and rights compulsorily
- 21Compulsory acquisition of rights and imposition of restrictive covenants
- 22Private rights
- 23Application of the Compulsory Purchase (Vesting Declarations) Act 1981
- 24Acquisition of subsoil only
- 25Acquisition of part of certain properties
- 26Rights under or over streets
- 27Temporary use of land for carrying out the authorised development
- 28Temporary use of land for maintaining authorised development
- 29Protective provisions for specified undertakers
- 30Statutory undertakers
- 31Apparatus and rights of statutory undertakers in stopped-up streets
- Part 7: MISCELLANEOUS AND GENERAL
- 32Application of landlord and tenant law
- 33Operational land for purposes of the 1990 Act
- 34Felling or lopping of trees and hedgerows
- 35Certification of plans etc.
- 36Arbitration
- 37Procedure in relation to certain approvals etc.
- Signature
- Schedule 1: AUTHORISED DEVELOPMENT
- 1Authorised Development
- Part 2: Requirements
- 1Interpretation
- 2Time limits
- 3Detailed design
- 4Overhead lines and pylons
- 5Cooling water pipelines and pumping station
- 6Gas pipeline and AGI
- 7Provision of landscaping
- 8Implementation and maintenance of landscaping
- 9Footpath/Public Rights of Way diversions
- 10Highway accesses
- 11Temporary buildings, structures and roads
- 12Surface and foul water drainage
- 13Contaminated land and groundwater – general
- 14Contaminated land and groundwater – known contamination on the site of the generating station
- 15Archaeology
- 16Ecological management plan
- 17Construction environment management plan
- 18Common Lane improvement
- 19Air Safety
- 20Flooding – mitigation
- 21Fire prevention
- 22Waste management on site – operational phase
- 23Control of noise – operational phase
- 24European protected species
- 25Restoration of land used temporarily for construction
- 26Air quality monitoring
- 27Combined heat and power
- 28Combined heat and power
- 29CCS site
- 30CCS monitoring report
- 31Applicability of Requirements 29 and 30
- 32Decommissioning
- 33Requirement for written approval
- 34Approved details
- 35Local liaison committee
- 36Employment and Skills plan
- 37Notice of start and completion of commissioning
- 38Notice of commencement of operation
- Schedule 2STREETS SUBJECT TO STREET WORKS
- Schedule 3: STREETS TO BE STOPPED UP
- STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED
- Schedule 4: PUBLIC RIGHT OF WAY TO BE TEMPORARILY CLOSED AND PERMANENTLY STOPPED UP
- 1Claimed public right of way to be extinguished for which a replacement will be provided
- 2Rights of way for which a replacement will be provided during temporary closure
- 3Rights of way for which no replacement will be provided during temporary closure
- Schedule 5ACCESS TO WORKS
- Schedule 6: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF RESTRICTIVE COVENANTS
- 1Compensation enactments
- 2Compensation enactments
- 3Application of the 1965 Act
- 4Application of the 1965 Act
- 5Application of the 1965 Act
- 6Application of the 1965 Act
- 7Application of the 1965 Act
- 8Application of the 1965 Act
- 9Application of the 1965 Act
- 10Application of the 1965 Act
- Schedule 7: PROCEDURE FOR DISCHARGE OF REQUIREMENTS
- 1Applications made under requirement
- 2Further information
- 3Fees
- 4Appeals
- 5Interpretation of Schedule 7
- Schedule 8: PROTECTIVE PROVISIONS
- For the protection of Canal & River Trust
- 1Interpretation
- 2Powers requiring CRT’s consent
- 3Vehicles, plant and machinery
- 4Fencing
- 5Survey of waterway
- 6Approval of plans, protective works etc.
- 7Design of works
- 8Notice of works
- 9Lighting
- 10Construction of specified works
- 11Prevention of pollution
- 12Access to work – provision of information
- 13Alterations to the waterway
- 14Maintenance of works
- 15Repayment of CRT’s fees, etc.
- 16Costs of alterations, etc.
- 17Making good of detriment; compensation and indemnity, etc.
- 18Arbitration
- 19Capitalised sums
- Explanatory note