OpenLegislation

Section 59 General duty of street authority to co-ordinate works.C5C8C9C13C14C16C19C20C21C23C28C31C35C36C37C40C41C44C46C48C52C55C60C63C64C67C70C71C74C77C80C82C86C90C99C108C110C111C115C116C118C119C127C132C134C139C143C145C148C149C150C153C155C157C158C162C167C170C172C174C179C182C183C187C188C190C193C201C204C206C207C214C217C218C220C222C223C226C227C228C234C238C241C244C247C250I1C1C2C3C4C6C7C10C11C12C15C17C18C22C24C25C26C27C29C30C32C33C34C38C39C42C43C45C47C49C50C51C53C54C56C57C58C59C61C62C65C66C68C69C72C73C75C76C78C79C81C83C84C85C87C88C89C91C92C93C94C95C96C97C98C100C101C102C103C104C105C106C107C109C112C113C114C117C120C121C122C123C124C125C126C128C129C130C131C133C135C136C137C138C140C141C142C144C146C147C151C152C154C156C159C160C161C163C164C165C166C168C169C171C173C175C176C177C178C180C181C184C185C186C189C191C192C194C195C196C197C198C199C200C202C203C205C208C209C210C211C212C213C215C216C219C221C224C225C229C230C231C232C233C235C236C237C239C240C242C243C245C246C248C249C251C252C253C254C255C256C257C258C259C260C261C262C263C264C265C266C267C268C269C270C271C272C273C274C275C276C277C278C279C280C281C282C283C284C285C286C287C288C289C290C291C292C293C294C295C296C297C298C299C300C301C302C303C304C305C306

England and Wales

(1)

A street authority shall use their best endeavours to co-ordinate the execution of works of all kinds (including works for road purposes) F1and the carrying out of relevant activities in the streets for which they are responsible—

(a)

in the interests of safety,

(b)

to minimise the inconvenience to persons using the street (having regard, in particular, to the needs of people with a disability), and

(c)

to protect the structure of the street and the integrity of apparatus in it.

(2)

That duty extends to co-ordination with other street authorities where works F2or relevant activities in a street for which one authority are responsible affect streets for which other authorities are responsible.

(3)

The Secretary of State shall issue or approve for the purposes of this section codes of practice giving practical guidance as to the matters mentioned above; and in discharging their general duty of co-ordination a street authority shall have regard to any such code of practice.

(4)

If it appears to the Secretary of State that a street authority are not properly discharging their general duty of co-ordination, he may direct the authority to supply him with such information as he considers necessary to enable him to decide whether that is the case and if so what action to take.

The direction shall specify the information to be provided and the period within which it is to be provided.

(5)

If after the end of that period (whether or not the direction has been complied with) it appears to the Secretary of State that the authority are not properly discharging their general duty of co-ordination, he may direct the authority to take such steps as he considers appropriate for the purpose of discharging that duty.

The direction shall specify the steps to be taken and the period within which they are to be taken, and may include a requirement to make a report or periodic reports to the Secretary of State as to what steps have been taken and the results of taking them.

(6)

A direction under this section may be varied or revoked by a further direction.

F3(7)

In this section “relevant activities” means any activity, other than the execution of works in the street or the use of the street by traffic (including pedestrians), which—

(a)

involves the temporary occupation or use of space in a street;

(b)

is subject to regulation by the street authority by virtue of provision made by or under any Act other than this Act; and

(c)

is prescribed by regulations made by the Secretary of State.

Annotations

Textual amendments

F1

Words in s. 59(1) inserted (29.6.2007 for E. for specified purposes, 26.11.2007 for W. for specified purposes) by Traffic Management Act 2004 (c. 18), ss. 42(2), 99(1); S.I. 2007/1890, art. 2, Sch.; S.I. 2007/3174, art. 2, Sch.

F2

Words in s. 59(2) inserted (29.6.2007 for E. for specified purposes, 26.11.2007 for W. for specified purposes) by Traffic Management Act 2004 (c. 18), ss. 42(3), 99(1); S.I. 2007/1890, art. 2, Sch.; S.I. 2007/3174, art. 2, Sch.

F3

S. 59(7) inserted (29.6.2007 for E. for specified purposes, 26.11.2007 for W. for specified purposes) by Traffic Management Act 2004 (c. 18), ss. 42(4), 99(1); S.I. 2007/1890, art. 2, Sch.; S.I. 2007/3174, art. 2, Sch.

Modifications

C1

S. 59 applied (4.4.1996) by S.I. 1996/937, art. 8(4)(5)

S. 59 applied (13.1.1999) by S.I. 1998/3269, art. 4(2)(3)

S. 59 applied (27.8.1998) by S.I. 1998/1936, art. 4(3)

S. 59 applied (21.5.1997) by S.I. 1997/1266, art. 5(2)(3)

S. 59 applied (10.2.1997) by S.I. 1997/264, art. 8(6)(7)

S. 59 applied (with modifications) (30.4.1999) by S.I. 1999/1306, art. 8(4)(5)

S. 59 applied (with modifications) (21.7.1999) by S.I. 1999/2129, art. 8(5)(6)

S. 59 applied (with modifications) (20.8.1999) by S.I. 1999/2336, art. 9(5)(6)(8)

S. 59 applied (with modifications) (23.8.1999) by S.I. 1999/2981, art. 7(5)(6)

S. 59 applied (with modifications) (11.11.1996) by S.I. 1996/2714, art. 4(2)(3)

S. 59: functions of a local authority made exercisable by, or by employees of, such person as may be authorised in that behalf by the local highway authority whose function it is (23.7.1999) by S.I. 1999/2106, art. 2, Sch. 2 para. 1(c)

S. 59 applied (with modifications) (29.3.2001) by S.I. 2001/1348, art. 21(3)-(5)

S. 59 applied (with modifications) (29.3.2001) by S.I. 2001/1347, art. 3(3)

S. 59 applied (with modifications) (18.7.2001) by S.I. 2001/2870, art. 10(6)

S. 59 applied (with modifications) (24.7.2001) by S.I. 2001/3627, art. 4(3)(4)

S. 59 applied (with modifications) (9.11.2001) by S.I. 2001/3682, art. 8(6)

C2

S. 59 applied (with modifications) (14.3.2002) by The Chester Guided Busway Order 2002 (S.I. 2002/412), art. 9(4)(5) (with art. 38);

S. 59 applied (with modifications) (30.4.2002) by The Docklands Light Railway (Silvertown and London City Airport Extension) Order 2002 (S.I. 2002/1066), art. 3(3)(4);

S. 59 applied (with modifications) (31.5.2002) by The Greater Manchester (Light Rapid Transit System) (Trafford Depot) Order 2002 (S.I. 2002/1327), art. 3(3)

C3

S. 59 applied (with modifications) (28.4.2003) by The Network Rail (West Coast Main Line) Order 2003 (S.I. 2003/1075), arts. 1, 13(6)(7)(8) (with art. 40)

C4

S. 59 applied (with modifications) (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), arts. 1, 3(3)(4)

C5

Pt. 3 modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), arts. 1, 3(1)

C6

S. 59 applied (with modifications) (19.11.2004) by The Scarweather Sands Offshore Wind Farm Order 2004 (S.I. 2004/3054), arts. 1, 6(4)(5) (with art. 38)

C7

S. 59 applied (with modifications) (11.2.2005) by The Merseytram (Liverpool City Centre to Kirkby) Order 2005 (S.I. 2005/120), arts. 1, 4(4)(5) (with arts. 65, 66)

C8

Pt. 3 modified (11.2.2005) by The Merseytram (Liverpool City Centre to Kirkby) Order 2005 (S.I. 2005/120), arts. 1, 4(1)(2) (with arts. 65, 66)

C9

Pt. 3 modified (22.3.2005) by The Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), art. 3(1)(2) (with art. 51)

C10

S. 59 applied (with modifications) (22.3.2005) by The Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), art. 3(3)(4) (with art. 51)

C11

S. 59 applied (with modifications) (4.5.2005) by The Telford Railfreight Terminal (Donnington) Order 2005 (S.I. 2005/1163), arts. 1, 12(7)

C12

S. 59 applied (with modifications) (22.7.2005) by The Midland Metro (Birmingham City Centre Extension, etc.) Order 2005 (S.I. 2005/1794), arts. 1, 3(3)(4) (with art. 47)

C13

Pt. 3 modified (22.7.2005) by The Midland Metro (Birmingham City Centre Extension, etc.) Order 2005 (S.I. 2005/1794), arts. 1, 3(1)(2) (with art. 47)

C14

Pt. 3 applied (3.8.2005) by The Greater Manchester (Leigh Busway) Order 2005 (S.I. 2005/1918), arts. 1, 3(1)

C15

S. 59 applied (with modifications) (3.8.2005) by The Greater Manchester (Leigh Busway) Order 2005 (S.I. 2005/1918), arts. 1, 3(3)(4)

C16

Pt. 3 modified (26.8.2005) by The River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), arts. 1, 8(7) (with arts. 45(1), 48, Sch. 10 paras. 21, 29)

C17

S. 59 applied (with modifications) (26.8.2005) by The River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), arts. 1, 8(9)(10) (with arts. 45(1), 48, Sch. 10 paras. 21, 29)

C18

Ss. 59, 60 applied (with modifications) (8.10.2005) by The Leicestershire County Council (Ashby de la Zouch Canal Extension) Order 2005 (S.I. 2005/2786), arts. 1, 9(2)(3)

C19

Pt. 3 restricted (8.10.2005) by The Leicestershire County Council (Ashby de la Zouch Canal Extension) Order 2005 (S.I. 2005/2786), arts. 1, 10(3)

C20

Pt. 3 modified (8.10.2005) by The Leicestershire County Council (Ashby de la Zouch Canal Extension) Order 2005 (S.I. 2005/2786), arts. 1, 9(1)

C21

Pt. 3 modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), arts. 1, 3(1) (with arts. 3(5), 15(3))

C22

S. 59 applied (with modifications) (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), arts. 1, 3(4) (with arts. 3(5), 15(3))

C23

Pt. 3 applied (11.1.2006) by The Cambridgeshire Guided Busway Order 2005 (S.I. 2005/3523), arts. 1, 3(1) (with art. 52)

C24

S. 59 applied (with modifications) (11.1.2006) by The Cambridgeshire Guided Busway Order 2005 (S.I. 2005/3523), arts. 1, 3(3)(4) (with art. 52)

C25

S. 59 applied (with modifications) (3.7.2006) by The Port of Blyth (Battleship Wharf Railway) Order 2006 (S.I. 2006/1518), arts. 1, 4

C26

S. 59 applied (with modifications) (14.9.2006) by The Borough of Poole (Poole Harbour Opening Bridges) Order 2006 (S.I. 2006/2310), arts. 1, 9(5)(6) (with art. 40, Sch. 7 para. 12)

C27

S. 59 applied (with modifications) (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), arts. 1, 3(4)(5) (with art. 43)

C28

Pt. 3 modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), arts. 1, 3(1)(2) (with art. 43)

C29

S. 59 applied (with modifications) (13.12.2006) by The Network Rail (Thameslink 2000) Order 2006 (S.I. 2006/3117), arts. 1, 16(6)(7) (with arts. 34, 35(2))

C30

S. 59 applied (with modifications) (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), arts. 1, 10(5)(6)

C31

Pt. 3 modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), arts. 1, 3

C32

S. 59 applied (with modifications) (19.3.2007) by The Ouseburn Barrage Order 2007 (S.I. 2007/608), arts. 1, 8(2) (with arts. 46-48, Sch. 6 para. 23)

C33

S. 59 applied (with modifications) (23.8.2007) by The Docklands Light Railway (Capacity Enhancement and 2012 Games Preparation) Order 2007 (S.I. 2007/2297), arts. 1, 3(4)(5) (with arts. 3(6), 12(3))

C34

S. 59 applied (with modifications) (28.9.2007) by The London Gateway Logistics and Commercial Centre Order 2007 (S.I. 2007/2657), arts. 1, 3(2)(3) (with arts. 19, 28, Sch. 3 para. 13(2))

C35

Pt. 3 modified (28.9.2007) by The London Gateway Logistics and Commercial Centre Order 2007 (S.I. 2007/2657), arts. 1, 3(1) (with arts. 19, 28, Sch. 3 para. 13(2))

C36

Pt. 3 modified (16.5.2008) by The London Gateway Port Harbour Empowerment Order 2008 (S.I. 2008/1261), arts. 1, 6(6) (with arts. 41(1), 45, 54(2), 55, 56, 57, 58(6))

C37

Pt. 3 modified (16.5.2008) by The London Gateway Port Harbour Empowerment Order 2008 (S.I. 2008/1261), arts. 1, 6(1) (with arts. 41(1), 45, 54(2), 55, 56, 57, 58(6))

C38

S. 59 applied (with modifications) (16.5.2008) by The London Gateway Port Harbour Empowerment Order 2008 (S.I. 2008/1261), arts. 1, 6(3)(4) (with arts. 41(1), 45, 54(2), 55, 56, 57, 58(6))

C39

S. 59 applied (with modifications) (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), arts. 1, 4(2)(3) (with art. 36(3))

C40

Pt. 3 modified (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), arts. 1, 4(1) (with art. 36(3))

C41

Pt. 3 modified (9.6.2009) by The Nottingham Express Transit System Order 2009 (S.I. 2009/1300), arts. 1, 4(1)(2) (with Sch. 13 para. 14(2), Sch. 14 para. 19, Sch. 16)

C42

S. 59 applied (9.6.2009) by The Nottingham Express Transit System Order 2009 (S.I. 2009/1300), arts. 1, 4(4)(5) (with Sch. 13 para. 14(2), Sch. 14 para. 19, Sch. 16)

C43

S. 59 applied (with modifications) (18.9.2009) by The London Underground (Victoria Station Upgrade) Order 2009 (S.I. 2009/2364), arts. 1, 3(4)(5)

C44

Pt. 3 modified (18.9.2009) by The London Underground (Victoria Station Upgrade) Order 2009 (S.I. 2009/2364), arts. 1, 3(1)(2)

C45

S. 59 applied (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), arts. 1, 4(1)(2)

C46

Pt. 3 modified (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 3(1) (with art. 51, Sch. 10 paras. 68, 85)

C47

S. 59 applied (with modifications) (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 3(2)(3) (with art. 51, Sch. 10 paras. 68, 85)

C48

Pt. 3 modified (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 4(1)

C49

S. 59 applied (with modifications) (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 4(2)-(3)

C50

S. 59 applied (26.9.2012) by The Network Rail (Ipswich Chord) Order 2012 (S.I. 2012/2284), arts. 1, 10(2) (with art. 26(2))

C51

S. 59 applied (6.11.2012) by The Network Rail (North Doncaster Chord) Order 2012 (S.I. 2012/2635), arts. 1, 14(2)(3) (with art. 35(2))

C52

Pt. 3 modified (13.11.2012) by The Chiltern Railways (Bicester to Oxford Improvements) Order 2012 (S.I. 2012/2679), arts. 1, 4(1) (with art. 42(2))

C53

S. 59 applied (13.11.2012) by The Chiltern Railways (Bicester to Oxford Improvements) Order 2012 (S.I. 2012/2679), arts. 1, 4(2)(3) (with art. 42(2))

C54

Ss. 54-106 applied (28.2.2013) by The Rookery South (Resource Recovery Facility) Order 2011 2013 (S.I. 2013/680), art. 10(3)

C55

Pt. 3 applied (with modifications) (9.4.2013) by The Hinkley Point C (Nuclear Generating Station) Order 2013 (S.I. 2013/648), arts. 1, 9 (with arts. 48, 68, 79)

C56

Ss. 54-106 applied (9.4.2013) by The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road)) Order 2013 (S.I. 2013/675), arts. 1, 9(2)

C57

Ss. 54-106 applied (15.6.2013) by The Galloper Wind Farm Order 2013 (S.I. 2013/1203), arts. 1, 13(3) (with arts. 11, 12)

C58

Ss. 54-106 applied (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 9(3) (with art. 30)

C59

S. 59 applied (with modifications) (21.8.2013) by The Croxley Rail Link Order 2013 (S.I. 2013/1967), arts. 1, 4(1)(2)

C60

Pt. 3 modified (22.8.2013) by The Leeds Railway Station (Southern Entrance) Order 2013 (S.I. 2013/1933), arts. 1, 3(1)

C61

S. 59 applied (with modifications) (22.8.2013) by The Leeds Railway Station (Southern Entrance) Order 2013 (S.I. 2013/1933), arts. 1, 3(3)(4)

C62

S. 59 applied (with modifications) (6.11.2013) by The Transport for Greater Manchester (Light Rapid Transit System) (Second City Crossing) Order 2013 (S.I. 2013/2587), arts. 1, 4(4)(5) (with arts. 42, 43)

C63

Pt. 3 modified (6.11.2013) by The Transport for Greater Manchester (Light Rapid Transit System) (Second City Crossing) Order 2013 (S.I. 2013/2587), arts. 1, 4(1)(2) (with arts. 42, 43)

C64

Pt. 3 modified (20.11.2013) by The M1 Junction 10a (Grade Separation) Order 2013 (S.I. 2013/2808), arts. 1, 8(1)(2)

C65

S. 59 applied (20.11.2013) by The M1 Junction 10a (Grade Separation) Order 2013 (S.I. 2013/2808), arts. 1, 8(4)(5)

C66

S. 59 applied (with modifications) (21.11.2013) by The Network Rail (Redditch Branch Enhancement) Order 2013 (S.I. 2013/2809), arts. 1, 10(2)(3) (with arts. 27(2), 39, Sch. 10 para. 4)

C67

Pt. 3 modified (9.1.2014) by The National Grid (King’s Lynn B Power Station Connection) Order 2013 (S.I. 2013/3200), arts. 1, 9(1)

C68

S. 59 applied (with modifications) (9.1.2014) by The National Grid (King’s Lynn B Power Station Connection) Order 2013 (S.I. 2013/3200), arts. 1, 9(2)(3)

C69

S. 59 applied (with modifications) (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(4)(5) (with arts. 57, 58, Sch. 11 para. 19)

C70

Pt. 3 applied (with modifications) (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(9) (with arts. 57, 58, Sch. 11 para. 19)

C71

Pt. 3 modified (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(1)(2) (with arts. 57, 58, Sch. 11 para. 19)

C72

S. 59 applied (with modifications) (21.4.2014) by The Network Rail (Norton Bridge Area Improvements) Order 2014 (S.I. 2014/909), arts. 1, 12(3)(4) (with art. 34(2))

C73

S. 59 applied (with modifications) (7.5.2014) by The National Grid (North London Reinforcement Project) Order 2014 (S.I. 2014/1052), arts. 1, 13(2)(3)

C74

Pt. 3 modified (7.5.2014) by The National Grid (North London Reinforcement Project) Order 2014 (S.I. 2014/1052), arts. 1, 13(1)

C75

Ss. 54-106 applied (7.7.2014) by The East Anglia ONE Offshore Wind Farm Order 2014 (S.I. 2014/1599), arts. 1, 8(3) (with arts. 37, 38, Sch. 9 para. 19)

C76

Ss. 54-106 applied (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), arts. 1, 15(3) (with arts. 7(6), 12, 13, Sch. 12 Pt. 1 para. 19, Sch. 12 Pt. 2 para. 6, sch. 12 Pt. 3 para. 5, Sch. 12 Pt. 4 para. 4, Sch. 12 Pt. 5 para. 4)

C77

Pt. 3 restricted (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), art. 1, Sch. 12 Pt. 2 para. 3 (with arts. 12, 13, Sch. 12 Pt. 1 paras. 6(3), 19, Pt. 2 paras. 3, 6, 13, Pt. 3 para. 5, Pt. 4 para. 4, Pt. 5 para. 4)

C78

S. 59 applied (with modifications) (19.8.2014) by The Network Rail (Huyton) Order 2014 (S.I. 2014/2027), arts. 1, 4(4) (with art. 31(2))

C79

S. 59 applied (with modifications) (18.9.2014) by The A556 (Knutsford to Bowdon Improvement) Development Consent Order 2014 (S.I. 2014/2269), arts. 1, 8(4)(5)

C80

Pt. 3 modified (18.9.2014) by The A556 (Knutsford to Bowdon Improvement) Development Consent Order 2014 (S.I. 2014/2269), arts. 1, 8(1)(2)

C81

Ss. 54-106 applied (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(4), 11(5) (with arts. 55, 56)

C82

Pt. 3 modified (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(5), 11(4)

C83

Ss. 54-106 applied (2.10.2014) by The North Killingholme (Generating Station) Order 2014 (S.I. 2014/2434), arts. 1, 9(3) (with arts. 6, 9(4), 13, Sch. 8 Pt. 1 para. 6, Sch. 8 Pt. 3 paras. 4(3), 6, 17, Sch. 8 Pt. 5 para. 9)

C84

S. 59 applied (2.10.2014) by The Clocaenog Forest Wind Farm Order 2014 (S.I. 2014/2441), arts. 1, 13(2)(3) (with art. 33)

C85

S. 59 applied (with modifications) (21.10.2014) by The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014 (S.I. 2014/2637), arts. 1, 8(4)(5)

C86

Pt. 3 modified (21.10.2014) by The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014 (S.I. 2014/2637), arts. 1, 8(1)(2)

C87

Ss. 54-106 applied (29.10.2014) by The Able Marine Energy Park Development Consent Order 2014 (S.I. 2014/2935), art. 15(3) (with arts. 30(4), 53)

C88

Ss. 54-106 applied (28.11.2014) by The Walney Extension Offshore Wind Farm Order 2014 (S.I. 2014/2950), arts. 1, 10(3) (with arts. 38, 39)

C89

S. 59 applied (with modifications) (15.12.2014) by The London Underground (Northern Line Extension) Order 2014 (S.I. 2014/3102), arts. 1, 3(4)(5) (with Sch. 8 para. 45)

C90

Pt. 3 modified (15.12.2014) by The London Underground (Northern Line Extension) Order 2014 (S.I. 2014/3102), arts. 1, 3(2) (with Sch. 8 para. 45)

C91

S. 59 applied (with modifications) (31.12.2014) by The Hornsea One Offshore Wind Farm Order 2014 (S.I. 2014/3331), arts. 1, 7(1)(2) (with arts. 37, 38)

C92

Ss. 54-106 applied (7.1.2015) by The Willington C Gas Pipeline Order 2014 (S.I. 2014/3328), arts. 1, 10(3)

C93

Ss. 54-106 applied (2.2.2015) by The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015 (S.I. 2015/23), arts. 1, 9(2)

C94

S. 59 applied (with modifications) (25.2.2015) by The A160/A180 (Port of Immingham Improvement) Development Consent Order 2015 (S.I. 2015/129), arts. 1, 9(4)(5)

C95

Ss. 54-106 applied (26.2.2015) by The Cornwall Council (A30 Temple to Higher Carblake Improvement) Order 2015 (S.I. 2015/147), arts. 1, 9(3)

C96

Ss. 54-106 applied (11.3.2015) by The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 (S.I. 2015/318), arts. 1, 13(3) (with arts. 8(5), 35, 40, 41, Sch. 12 Pt. 1 paras. 4, 9(2), 10, Pt. 2 paras. 4(2)(3), 19, Pt. 4 paras. 3, 4, 16)

C97

Ss. 54-106 applied (1.4.2015) by The Knottingley Power Plant Order 2015 (S.I. 2015/680), arts. 1, 10(3) (with art. 7(6), Sch. 8 para. 10)

C98

S. 59 applied (with modifications) (21.4.2015) by The Network Rail (Ordsall Chord) Order 2015 (S.I. 2015/780), arts. 1, 4(2)(3) (with art. 36(2))

C99

Pt. 3 modified (21.4.2015) by The Network Rail (Ordsall Chord) Order 2015 (S.I. 2015/780), arts. 1, 4(1) (with art. 36(2))

C100

Ss. 54-106 applied (23.6.2015) by The Norfolk County Council (Norwich Northern Distributor Road (A1067 to A47(T))) Order 2015 (S.I. 2015/1347), arts. 1, 9(2)

C101

Ss. 54-106 applied (30.6.2015) by The Swansea Bay Tidal Generating Station Order 2015 (S.I. 2015/1386), arts. 1, 9(3) (with arts. 51, 53)

C102

Ss. 54-106 applied (7.8.2015) by The Preesall Underground Gas Storage Facility Order 2015 (S.I. 2015/1561), arts. 1, 9(3) (with art. 44)

C103

Ss. 54-106 applied (14.8.2015) by The Progress Power (Gas Fired Power Station) Order 2015 (S.I. 2015/1570), arts. 1, 10(3)

C104

Ss. 54-106 applied (26.8.2015) by The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (S.I. 2015/1592), arts. 1, 14(3) (with arts. 35, 40, 41)

C105

Ss. 54-106 applied (19.11.2015) by The Ferrybridge Multifuel 2 Power Station Order 2015 (S.I. 2015/1832), arts. 1(2), 9(3)

C106

Ss. 54-106 applied (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 9(3) (with art. 26)

C107

S. 59 applied (with modifications) (12.1.2016) by The London Underground (Bank Station Capacity Upgrade) Order 2015 (S.I. 2015/2044), arts. 1, 4(4)(5)

C108

Pt. 3 modified (12.1.2016) by The London Underground (Bank Station Capacity Upgrade) Order 2015 (S.I. 2015/2044), arts. 1, 4(1)(2)

C109

S. 59 modified (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 11(2)(3) (with art. 32)

C110

Pt. 3 modified (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 11(1) (with art. 32)

C111

Pt. 3 modified (18.2.2016) by The A19/A1058 Coast Road (Junction Improvement) Development Consent Order 2016 (S.I. 2016/73), arts. 1, 8(2) (with art. 37)

C112

S. 59 applied (18.2.2016) by The A19/A1058 Coast Road (Junction Improvement) Development Consent Order 2016 (S.I. 2016/73), arts. 1, 8(4)(5) (with art. 37)

C113

Ss. 54-106 applied (with modifications) (25.3.2016) by The Thorpe Marsh Gas Pipeline Order 2016 (S.I. 2016/297), arts. 1, 12(3) (with art. 39)

C114

S. 59 applied (with modifications) (1.6.2016) by The A14 Cambridge to Huntingdon Improvement Scheme Development Consent Order 2016 (S.I. 2016/547), arts. 1, 10(4)(5) (with arts. 4, 5(3))

C115

Pt. 3 modified (1.6.2016) by The A14 Cambridge to Huntingdon Improvement Scheme Development Consent Order 2016 (S.I. 2016/547), arts. 1, 10(1)(2) (with arts. 4, 5(3))

C116

Pt. 3 applied (14.6.2016) by The Midland Metro (Birmingham City Centre Extension, etc.) (Land Acquisition and Variation) Order 2016 (S.I. 2016/545), arts. 1, 3(1) (with art. 39)

C117

S. 59 applied (with modifications) (14.6.2016) by The Midland Metro (Birmingham City Centre Extension, etc.) (Land Acquisition and Variation) Order 2016 (S.I. 2016/545), arts. 1, 3(3)(4) (with art. 39)

C118

Pt. 3 modified (14.6.2016) by The Midland Metro (Birmingham City Centre Extension, etc.) (Land Acquisition and Variation) Order 2016 (S.I. 2016/545), arts. 1, 3(2) (with art. 39)

C119

Pt. 3 applied (with modifications) (2.8.2016) by The Midland Metro (Wolverhampton City Centre Extension) Order 2016 (S.I. 2016/684), arts. 1, 5(1)(2) (with arts. 46, 47, Sch. 8 para. 2(7), Sch. 9 para. 4, Sch. 10 para. 12(2))

C120

S. 59 applied (with modifications) (2.8.2016) by The Midland Metro (Wolverhampton City Centre Extension) Order 2016 (S.I. 2016/684), arts. 1, 5(3)(4) (with arts. 46, 47, Sch. 9 para. 4, Sch. 10 para. 12(2))

C121

Ss. 54-106 applied (2.8.2016) by The Meaford Gas Fired Generating Station Order 2016 (S.I. 2016/779), arts. 1, 11(3)

C122

Ss. 54-106 applied (10.8.2016) by The York Potash Harbour Facilities Order 2016 (S.I. 2016/772), arts. 1, 10(3) (with arts. 35, 36)

C123

Ss. 54-106 applied (19.8.2016) by The North Wales Wind Farms Connection Order 2016 (S.I. 2016/818), arts. 1, 10(5) (with art. 35)

C124

S. 59 applied (with modifications) (7.9.2016) by The Hornsea Two Offshore Wind Farm Order 2016 (S.I. 2016/844), arts. 1(2), 10(2)(d) (with arts. 37, 38)

C125

Ss. 54-106 applied (with modifications) (15.9.2016) by The River Humber Gas Pipeline Replacement Order 2016 (S.I. 2016/853), arts. 1, 11(3) (with art. 43)

C126

S. 59 applied (with modifications) (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 9(4)(5)

C127

Pt. 3 modified (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 9(2)

C128

Ss. 54-106 applied (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 11(3)

C129

Ss. 54-106 applied (27.9.2016) by The Triton Knoll Electrical System Order 2016 (S.I. 2016/880), arts. 1(2), 8(3) (with arts. 39, 40, Sch. 8 para. 19)

C130

S. 59 applied (28.10.2016) by The Brechfa Forest Wind Farm Connection Order 2016 (S.I. 2016/987), arts. 1, 8(3)(e) (with art. 37)

C131

S. 59 applied (with modifications) (24.11.2016) by The Transport for Greater Manchester (Light Rapid Transit System) (Trafford Park Extension) Order 2016 (S.I. 2016/1035), arts. 1, 4(4)(5) (with arts. 43, 44)

C132

Pt. 3 modified (24.11.2016) by The Transport for Greater Manchester (Light Rapid Transit System) (Trafford Park Extension) Order 2016 (S.I. 2016/1035), arts. 1, 4(1)(2) (with arts. 43, 44)

C133

Ss. 54-106 applied (18.3.2017) by The North London Heat and Power Generating Station Order 2017 (S.I. 2017/215), arts. 1, 10(3)

C134

Pt. 3 modified (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 12(1) (with art. 31)

C135

S. 59 applied (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 12(2)(3)(d) (with art. 31)

C136

Ss. 54-106 applied (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 10(3) (with art. 31)

C137

Ss. 54-106 applied (5.4.2017) by The Keuper Underground Gas Storage Facility Order 2017 (S.I. 2017/433), arts. 1, 10(4)

C138

Ss. 54-106 applied (8.8.2017) by The Wrexham Gas Fired Generating Station Order 2017 (S.I. 2017/766), arts. 1, 10(3)

C139

Pt. 3 applied (with modifications) (24.8.2017) by The National Grid (Richborough Connection Project) Development Consent Order 2017 (S.I. 2017/817), arts. 1, 9(1) (with art. 22)

C140

S. 59 applied (with modifications) (24.8.2017) by The National Grid (Richborough Connection Project) Development Consent Order 2017 (S.I. 2017/817), arts. 1, 11(3)(d) (with art. 22)

C141

Ss. 54-106 applied (29.8.2017) by The East Anglia THREE Offshore Wind Farm Order 2017 (S.I. 2017/826), arts. 1, 8(3) (with arts. 5(9), 36, 37, Sch. 8 para. 34)

C142

S. 59 applied (with modifications) (5.9.2017) by The London Overground (Barking Riverside Extension) Order 2017 (S.I. 2017/830), arts. 1, 3(4)(5) (with Sch. 8 para. 20)

C143

Pt. 3 modified (5.9.2017) by The London Overground (Barking Riverside Extension) Order 2017 (S.I. 2017/830), arts. 1, 3(2) (with Sch. 8 para. 20)

C144

S. 59 applied (with modifications) (19.12.2017) by The Network Rail (Buxton Sidings Extension) Order 2017 (S.I. 2017/1150), arts. 1, 4(3)(4) (with art. 32(2))

C145

Pt. 3 modified (22.12.2017) by The M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202), arts. 1, 11(1)(2) (with arts. 4, 37)

C146

S. 59 applied (22.12.2017) by The M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202), arts. 1, 11(4)(5) (with arts. 4, 37)

C147

S. 59 applied (with modifcations) (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), arts. 1, 3(4)(5) (with arts. 55-57, Sch. 8 para. 13)

C148

Pt. 3 applied (with modifications) (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), arts. 1, 3(2) (with arts. 55-57, Sch. 8 para. 13)

C149

Pt. 3 modified (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), arts. 1, 3(2) (with arts. 55-57, Sch. 8 para. 13)

C150

Pt. 3 applied (with modifications) (4.1.2018) by The Blackpool Tramway (Blackpool North Extension) Order 2017 (S.I. 2017/1214), arts. 1, 5(1)(2) (with arts. 58, 59)

C151

S. 59 applied (4.1.2018) by The Blackpool Tramway (Blackpool North Extension) Order 2017 (S.I. 2017/1214), arts. 1, 5(4)(5) (with arts. 5(7), 58, 59)

C152

S. 59 applied (18.4.2018) by The Network Rail (Hope Valley Capacity) Order 2018 (S.I. 2018/446), arts. 1, 4(3)(4) (with arts. 24(8), 33(2))

C153

Pt. 3 applied (18.4.2018) by The Network Rail (Hope Valley Capacity) Order 2018 (S.I. 2018/446), arts. 1, 4(1) (with arts. 24(8), 33(2))

C154

S. 59 applied (31.5.2018) by The Silvertown Tunnel Order 2018 (S.I. 2018/574), arts. 1(2), 7(4)(5)

C155

Pt. 3 modified (31.5.2018) by The Silvertown Tunnel Order 2018 (S.I. 2018/574), arts. 1(2), 7(2)

C156

S. 59 applied (with modifications) (24.8.2018) by The Network Rail (Werrington Grade Separation) Order 2018 (S.I. 2018/923), arts. 1, 4(2)(3) (with art. 31(2))

C157

Pt. 3 modified (24.8.2018) by The Network Rail (Werrington Grade Separation) Order 2018 (S.I. 2018/923), arts. 1, 4(1) (with art. 31(2))

C158

Pt. 3 modified (3.10.2018) by The A19/A184 Testo's Junction Alteration Development Consent Order 2018 (S.I. 2018/994), arts. 1, 9(1)(2) (with arts. 3(3), 5)

C159

S. 59 applied (3.10.2018) by The A19/A184 Testo's Junction Alteration Development Consent Order 2018 (S.I. 2018/994), arts. 1, 9(4)(5) (with arts. 3(3), 5)

C160

Ss. 54-106 applied (12.10.2018) by The Eggborough Gas Fired Generating Station Order 2018 (S.I. 2018/1020), arts. 1, 8(3) (with arts. 6, 42)

C161

S. 59 applied (with modifications) (13.3.2019) by The Port of Tilbury (Expansion) Order 2019 (S.I. 2019/359), arts. 1, 9(4)(5) (with arts. 55, 56)

C162

Pt. 3 modified (13.3.2019) by The Port of Tilbury (Expansion) Order 2019 (S.I. 2019/359), arts. 1, 9(1)(2)(8) (with arts. 55, 56)

C163

Ss. 54-106 applied (3.4.2019) by The Millbrook Gas Fired Generating Station Order 2019 (S.I. 2019/578), arts. 1, 9(3)

C164

Ss. 54-106 applied (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), arts. 1, 9(3)

C165

Ss. 54-106 applied (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), arts. 1, 9(3)

C166

S. 59 applied (with modifications) (25.2.2020) by The Network Rail (East West Rail) (Bicester to Bedford Improvements) Order 2020 (S.I. 2020/114), arts. 1, 4(3)(4) (with art. 37(2))

C167

Pt. 3 modified (25.2.2020) by The Network Rail (East West Rail) (Bicester to Bedford Improvements) Order 2020 (S.I. 2020/114), arts. 1, 4(1) (with art. 37(2))

C168

Ss. 54-106 applied (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 11(3) (with art. 3(1))

C169

S. 59 applied (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 12(4)(5)(d) (with art. 3(1))

C170

Pt. 3 applied (with modifications) (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 12(1)(2) (with art. 3(1))

C171

S. 59 applied (with modifications) (4.3.2020) by The Midland Metro (Birmingham Eastside Extension) Order 2020 (S.I. 2020/141), arts. 1, 5(3)(4) (with arts. 47, 48, Sch. 10 para. 19)

C172

Pt. 3 applied (with modifications) (4.3.2020) by The Midland Metro (Birmingham Eastside Extension) Order 2020 (S.I. 2020/141), arts. 1, 5(1)(2) (with arts. 47, 48, Sch. 10 para. 19)

C173

Ss. 54-106 applied (14.4.2020) by The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020 (S.I. 2020/325), arts. 1, 10(4) (with art. 7)

C174

Pt. 3 modified (30.4.2020) by The A585 Windy Harbour to Skippool Highway Development Consent Order 2020 (S.I. 2020/402), arts. 1, 9(2) (with arts. 5, 44)

C175

S. 59 applied (30.4.2020) by The A585 Windy Harbour to Skippool Highway Development Consent Order 2020 (S.I. 2020/402), arts. 1, 9(4)(5) (with arts. 5, 44)

C176

Ss. 54-106 applied (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 11(3) (with art. 7)

C177

S. 59 applied (with modifications) (21.5.2020) by The Lake Lothing (Lowestoft) Third Crossing Order 2020 (S.I. 2020/474), arts. 1, 7(4)(5) (with arts. 51, 57)

C178

S. 59 applied (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 13(4)(5) (with art. 37)

C179

Pt. 3 modified (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 13(1)(2) (with art. 37)

C180

Ss. 54-106 applied (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 12(3) (with art. 37)

C181

S. 59 applied (with modifications) (18.6.2020) by The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (S.I. 2020/556), arts. 1, 9(4)(5) (with arts. 5, 44)

C182

Pt. 3 modified (18.6.2020) by The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (S.I. 2020/556), arts. 1, 9(1)(2) (with arts. 5, 44)

C183

Pt. 3 modified (6.8.2020) by The A19 Downhill Lane Junction Development Consent Order 2020 (S.I. 2020/746), arts. 1, 9(1)(2) (with art. 5)

C184

S. 59 applied (with modifications) (6.8.2020) by The A19 Downhill Lane Junction Development Consent Order 2020 (S.I. 2020/746), arts. 1, 9(4)(5) (with art. 5)

C185

Ss. 54-106 applied (1.9.2020) by The Immingham Open Cycle Gas Turbine Order 2020 (S.I. 2020/847), arts. 1, 9(3) (with Sch. 9 para. 144)

C186

S. 59 applied (with modifications) (15.10.2020) by The Great Yarmouth Third River Crossing Development Consent Order 2020 (S.I. 2020/1075), arts. 1, 11(5)

C187

Pt. 3 modified (15.10.2020) by The Great Yarmouth Third River Crossing Development Consent Order 2020 (S.I. 2020/1075), arts. 1, 11(1)(2)

C188

Pt. 3 modified (29.10.2020) by The Southampton to London Pipeline Development Consent Order 2020 (S.I. 2020/1099), arts. 1, 12(1)(2) (with art. 32, Sch. 9 para. 36)

C189

S. 59 applied (with modifications) (29.10.2020) by The Southampton to London Pipeline Development Consent Order 2020 (S.I. 2020/1099), arts. 1, 12(4)(5)(d) (with art. 32, Sch. 9 para. 36)

C190

Pt. 3 applied (31.12.2020) by The Network Rail (Cambridgeshire Level Crossing Reduction) Order 2020 (S.I. 2020/1485), arts. 1, 3(1)

C191

S. 59 applied (31.12.2020) by The Network Rail (Cambridgeshire Level Crossing Reduction) Order 2020 (S.I. 2020/1485), arts. 1, 3(2)(3)

C192

S. 59 applied (with modifications) (19.1.2021) by The Network Rail (Suffolk Level Crossing Reduction) Order 2020 (S.I. 2020/1663), arts. 1, 3(2)(3)

C193

Pt. 3 modified (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 10(1)(2) (with art. 5, Sch. 27 para. 36)

C194

Ss. 54-106 applied (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 12(3) (with art. 5, Sch. 27 para. 36)

C195

S. 59 applied (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 10(4)(5) (with art. 5, Sch. 27 para. 36)

C196

S. 59 applied (with modifications) (19.2.2021) by The A303 Sparkford to Ilchester Dualling Development Consent Order 2021 (S.I. 2021/125), arts. 1, 12(4)(5) (with arts. 4, 47)

C197

S. 59 applied (1.9.2021) by The Network Rail (Teddington Station Access for All) Order 2021 (S.I. 2021/937), arts. 1, 3(3)(d)

C198

Ss. 54-106 applied (22.12.2021) by The Morlais Demonstration Zone Order 2021 (S.I. 2021/1478), arts. 1, 7, Sch. 10 para. 2 (with arts. 15, 50, Sch. 11 para. 29)

C199

Ss. 54-106 applied (10.3.2022) by The Thurrock Flexible Generation Plant Development Consent Order 2022 (S.I. 2022/157), arts. 1, 11(3) (with Sch. 8 Pt. 6 para. 19)

C200

S. 59 applied (with modifications) (10.3.2022) by The Thurrock Flexible Generation Plant Development Consent Order 2022 (S.I. 2022/157), arts. 1, 12(4)(5) (with Sch. 8 Pt. 6 para. 19)

C201

Pt. 3 modified (25.3.2022) by The Bridgwater Tidal Barrier Order 2022 (S.I. 2022/299), arts. 1, 3(1)(2) (with art. 55)

C202

S. 59 applied (with modifications) (25.3.2022) by The Bridgwater Tidal Barrier Order 2022 (S.I. 2022/299), arts. 1, 3(4)(5) (with art. 55)

C203

S. 59 applied (with modifications) (12.5.2022) by The M54 to M6 Link Road Development Consent Order 2022 (S.I. 2022/475), arts. 1, 9(4)(5)

C204

Pt. 3 modified (12.5.2022) by The M54 to M6 Link Road Development Consent Order 2022 (S.I. 2022/475), arts. 1, 9(2)

C205

S. 59 applied (with modifications) (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), arts. 1, 11(4)(5) (with arts. 6, 34)

C206

Pt. 3 modified (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), arts. 1, 11(1)(2) (with arts. 6, 34)

C207

Pt. 3 modified (6.6.2022) by The M25 Junction 28 Development Consent Order 2022 (S.I. 2022/573), arts. 1, 10(1)(2) (with arts. 5, 36) (as amended (7.2.2024) by S.I. 2024/129, art. 1, Sch.)

C208

S. 59 applied (6.6.2022) by The M25 Junction 28 Development Consent Order 2022 (S.I. 2022/573), arts. 1, 10(4)(5) (with arts. 5, 36)

C209

S. 59 applied (with modifications) (30.6.2022) by The Network Rail (Essex and Others Level Crossing Reduction) Order 2022 (S.I. 2022/651), arts. 1, 3(2)(3)

C210

S. 59 applied (with modifications) (13.7.2022) by The A47 Blofield to North Burlingham Development Consent Order 2022 (S.I. 2022/738), arts. 1, 11(4)(5) (with arts. 4, 50)

C211

Ss. 54-106 applied (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 14(4) (with arts. 15, 62, 76, 87)

S. 59 applied (with modifications) (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 15(3)(4) (with arts. 62, 76, 87)

C212

S. 59 applied (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 10(4)(5) (with arts. 4, 53)

C213

Ss. 54-106 applied (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 14(3) (with arts. 4, 53)

C214

Pt. 3 modified (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 15(1) (with arts. 62, 76, 87)

Pt. 3 modified (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 10(1)(2) (with arts. 4, 53)

C215

S. 59 applied (with modifications) (8.9.2022) by The Manston Airport Development Consent Order 2022 (S.I. 2022/922), arts. 1, 10(4)(5) (with arts. 5, 40)

C216

S. 59 applied (with modifications) (8.9.2022) by The A428 Black Cat to Caxton Gibbet Development Consent Order 2022 (S.I. 2022/934), arts. 1, 11(4)(5)

C217

Pt. 3 modified (8.9.2022) by The A428 Black Cat to Caxton Gibbet Development Consent Order 2022 (S.I. 2022/934), arts. 1, 11(2)

C218

Pt. 3 modified (8.9.2022) by The Manston Airport Development Consent Order 2022 (S.I. 2022/922), arts. 1, 10(2) (with arts. 5, 40)

C219

S. 59 applied (with modifications) (3.11.2022) by The Network Rail (Huddersfield to Westtown (Dewsbury) Improvements) Order 2022 (S.I. 2022/1067), arts. 1, 4(3)(4)

C220

Pt. 3 modified (3.11.2022) by The Network Rail (Huddersfield to Westtown (Dewsbury) Improvements) Order 2022 (S.I. 2022/1067), arts. 1, 4(1)

C221

S. 59 applied (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 11(4)(5)(d) (with arts. 4, 52, Sch. 9 para. 82)

C222

Pt. 3 modified (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 11(1)(2) (with arts. 4, 52, Sch. 9 para. 82)

C223

Pt. 3 modified (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 11(1)(2) (with arts. 4, 52, Sch. 9 para. 82)

C224

Ss. 54-106 applied (with modifications) (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 15(3) (with arts. 4, 52, Sch. 9 para. 82)

C225

S. 59 applied (5.12.2022) by The Portishead Branch Line (MetroWest Phase 1) Order 2022 (S.I. 2022/1194), arts. 1, 12(4)(5)(d) (with art. 51)

C226

Pt. 3 modified (5.12.2022) by The Portishead Branch Line (MetroWest Phase 1) Order 2022 (S.I. 2022/1194), arts. 1, 12(1)(2) (with art. 51)

C227

Pt. 3 modified (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 11(1)(2) (with art. 5)

C228

Pt. 3 modified (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 12(1)(2) (with art. 4)

C229

Ss. 54-106 applied (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 10(3) (with arts. 5, 11)

C230

Ss. 54-106 applied (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 11(3) (with arts. 4, 12)

C231

S. 59 applied (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 12(4)(5) (with art. 4)

C232

S. 59 applied (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 11(4)(5) (with art. 5)

C233

Ss. 54-106 applied (29.12.2022) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022 (S.I. 2022/1396), arts. 1, 9(3) (with art. 32, Sch. 10 paras. 26(2), 68)

C234

Pt. 3 modified (11.1.2023) by The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (S.I. 2022/1406), arts. 1, 4(1) (with art. 34(2), Sch. 12 paras. 5, 47, 79)

C235

S. 59 applied (11.1.2023) by The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (S.I. 2022/1406), arts. 1, 4(4) (with art. 34(2), Sch. 12 paras. 5, 47, 79)

C236

S. 59 applied (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 11(4)(5) (with arts. 4, 50)

C237

Ss. 54-106 applied (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 15(3) (with arts. 4, 50)

C238

Pt. 3 modified (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 11(1)(2) (with arts. 4, 50)

C239

Ss. 54-106 applied (18.7.2023) by The Longfield Solar Farm Order 2023 (S.I. 2023/734), arts. 1, 8(3)

C240

Ss. 54-106 applied (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 10(3) (with arts. 5, 53, Sch. 8 paras. 6, 64)

C241

Pt. 3 modified (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 11(2) (with arts. 5, 53, Sch. 8 paras. 6, 64)

C242

S. 59 applied (with modifications) (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 11(4)(5) (with arts. 5, 53, Sch. 8 paras. 6, 64)

C243

S. 59 applied (with modifications) (2.8.2023) by The Rother Valley Railway (Bodiam to Robertsbridge Junction) Order 2023 (S.I. 2023/815), arts. 1, 4(2)(3) (with art. 42)

C244

Pt. 3 modified (4.8.2023) by The A303 (Amesbury to Berwick Down) Development Consent Order 2023 (S.I. 2023/834), arts. 1, 8(1)(2) (with arts. 6(2), 18, Sch. 11 paras. 5, 30)

C245

S. 59 applied (with modifications) (4.8.2023) by The A303 (Amesbury to Berwick Down) Development Consent Order 2023 (S.I. 2023/834), arts. 1, 8(4)(5) (with arts. 6(2), 18, Sch. 11 paras. 5, 30)

C246

S. 59 applied (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 12(4)(5) (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))

C247

Pt. 3 modified (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 12(1)(2) (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))

C248

Ss. 54-106 applied (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 11(3) (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))

C249

Ss. 54-106 applied (7.2.2024) by The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024 (S.I. 2024/70), arts. 1, 9(3) (with art. 43, Sch. 12 paras. 5, 24)

C250

Pt. 3 modified (9.2.2024) by The A12 Chelmsford to A120 Widening Development Consent Order 2024 (S.I. 2024/60), arts. 1, 12(1)(2) (with arts. 4, 52, Sch. 11 paras. 6, 24, 39(1), 55(1), 84)

C251

S. 59 applied (9.2.2024) by The A12 Chelmsford to A120 Widening Development Consent Order 2024 (S.I. 2024/60), arts. 1, 12(4)(5) (with arts. 4, 52, Sch. 11 paras. 6, 24, 39(1), 55(1), 84)

C252

Ss. 54-106 applied (11.3.2024) by The Net Zero Teesside Order 2024 (S.I. 2024/174), arts. 1, 11(3) (with arts. 42, 43, Sch. 12 paras. 5, 51, 91, 129, 136, 234, 345, 356)

C253

Ss. 54-106 applied (13.3.2024) by The Medworth Energy from Waste Combined Heatnd Power Facility Order 2024 (S.I. 2024/230), arts. 1, 10 (with Sch. 11 paras. 5, 22, 37, 47, 82, 110)

C254

S. 59 applied (28.3.2024) by The A66 Northern Trans-Pennine Development Consent Order 2024 (S.I. 2024/360), arts. 1, 8(4)(5) (with arts. 18, 35, Sch. 9)

C255

Pt. 3 modified (28.3.2024) by The A66 Northern Trans-Pennine Development Consent Order 2024 (S.I. 2024/360), arts. 1, 8(2) (with arts. 18, 35, Sch. 9)

C256

S. 59 applied (5.4.2024) by The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024 (S.I. 2024/393), arts. 1, 12(4)(5) (with art. 44, Sch. 15)

C257

Pt. 3 modified (5.4.2024) by The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024 (S.I. 2024/393), arts. 1, 12(2) (with art. 44, Sch. 15)

C258

S. 59 applied (25.4.2024) by The Network Rail (Church Fenton Level Crossing Reduction) Order 2024 (S.I. 2024/526), arts. 1, 4(3)(4)

C259

Ss. 54-106 applied (14.6.2024) by The A1 in Northumberland: Morpeth to Ellingham Development Consent Order 2024 (S.I. 2024/733), arts. 1, 13(3) (with art. 6, Sch. 10)

C260

S. 59 applied (14.6.2024) by The A1 in Northumberland: Morpeth to Ellingham Development Consent Order 2024 (S.I. 2024/733), arts. 1, 11(4)(5) (with art. 6, Sch. 10)

C261

Pt. 3 modified (14.6.2024) by The A1 in Northumberland: Morpeth to Ellingham Development Consent Order 2024 (S.I. 2024/733), arts. 1, 11(2) (with art. 6, Sch. 10)

C262

Ss. 54-106 applied (3.8.2024) by The Mallard Pass Solar Farm Order 2024 (S.I. 2024/796), arts. 1, 8(3) (with Sch. 15)

C263

Ss. 54-106 applied (3.8.2024) by The Gate Burton Energy Park Order 2024 (S.I. 2024/807), arts. 1, 8(3) (with art. 45, Sch. 14)

C264

Ss. 54-106 applied (3.8.2024) by The Sunnica Energy Farm Order 2024 (S.I. 2024/802), arts. 1, 8(4) (with art. 44, Sch. 12)

C265

Ss. 54-106 applied (27.9.2024) by The Cottam Solar Project Order 2024 (S.I. 2024/943), arts. 1, 8(3) (with art. 48, Sch. 15)

Ss. 54-106 applied (9.10.2024) by The M3 Junction 9 Development Consent Order 2024 (S.I. 2024/753), arts. 1, 11(3) (with arts. 4, 13, Sch. 10) (as amended by S.I. 2024/1020, Sch.)

C266

S. 59 applied (4.10.2024) by The National Grid (Bramford to Twinstead Reinforcement) Order 2024 (S.I. 2024/958), arts. 1, 13(5)(6) (with art. 40, Sch. 14)

S. 59 applied (9.10.2024) by The M3 Junction 9 Development Consent Order 2024 (S.I. 2024/753), arts. 1, 13(4)(5) (with arts. 4, 13(8), Sch. 10) (as amended by S.I. 2024/1020, Sch.)

C267

Pt. 3 modified (4.10.2024) by The National Grid (Bramford to Twinstead Reinforcement) Order 2024 (S.I. 2024/958), arts. 1, 13(2) (with art. 40, Sch. 14)

Pt. 3 modified (9.10.2024) by The M3 Junction 9 Development Consent Order 2024 (S.I. 2024/753), arts. 1, 13(2) (with arts. 4, 13(8), Sch. 10) (as amended by S.I. 2024/1020, Sch.)

C268

S. 59 applied (18.12.2024) by The Network Rail (Leeds to Micklefield Enhancements) Order 2024 (S.I. 2024/1284), arts. 1, 4(3)(4) (with Sch. 15)

C269

Pt. 3 modified (18.12.2024) by The Network Rail (Leeds to Micklefield Enhancements) Order 2024 (S.I. 2024/1284), arts. 1, 4(1) (with Sch. 15)

C270

Ss. 54-106 applied (15.2.2025) by The West Burton Solar Project Order 2025 (S.I. 2025/116), arts. 1, 8 (with art. 47, Sch. 15)

C271

Ss. 54-106 applied (17.2.2025) by The Heckington Fen Solar Park Order 2025 (S.I. 2025/85), arts. 1, 8(3) (with art. 43, Sch. 13)

C272

S. 59 applied (27.2.2025) by The Associated British Ports (Immingham Green Energy Terminal) Order 2025 (S.I. 2025/165), arts. 1, 8(4)(5) (with arts. 48, 59, Sch. 14)

C273

Pt. 3 modified (27.2.2025) by The Associated British Ports (Immingham Green Energy Terminal) Order 2025 (S.I. 2025/165), arts. 1, 8(1)(2) (with arts. 48, 59, Sch. 14)

C274

Ss. 54-106 applied (4.4.2025) by The North Lincolnshire Green Energy Park Order 2025 (S.I. 2025/362), arts. 1, 12(6) (with Sch. 14)

C275

Pt. 3 modified (15.4.2025) by The A122 (Lower Thames Crossing) Development Consent Order 2025 (S.I. 2025/462), arts. 1, 9(1)(2) (with arts. 5, 43, 53(7), Sch. 14)

C276

Pt. 3 applied (15.4.2025) by The A122 (Lower Thames Crossing) Development Consent Order 2025 (S.I. 2025/462), art. 1, Sch. 14 para. 50(3) (with arts. 5, 43, 53(7), 54(2), Sch. 14)

C277

S. 59 applied (15.4.2025) by The A122 (Lower Thames Crossing) Development Consent Order 2025 (S.I. 2025/462), arts. 1, 9(4)(5) (with arts. 5, 43, 53(7), Sch. 14)

C278

Ss. 54-106 applied (24.4.2025) by The London Luton Airport Expansion Development Consent Order 2025 (S.I. 2025/463), arts. 1, 10(3) (with Sch. 8 paras. 36(3), 87)

C279

Pt. 3 modified (24.4.2025) by The London Luton Airport Expansion Development Consent Order 2025 (S.I. 2025/463), arts. 1, 9(2) (with Sch. 8 paras. 36(3), 87)

C280

S. 59 applied (with modifications) (24.4.2025) by The London Luton Airport Expansion Development Consent Order 2025 (S.I. 2025/463), arts. 1, 9(4)(5) (with Sch. 8 paras. 36(3), 87)

C281

Ss. 54-106 applied (31.5.2025) by The East Yorkshire Solar Farm Order 2025 (S.I. 2025/585), arts. 1, 8(3) (with art. 49, Sch. 14)

C282

Ss. 54-106 applied (25.6.2025) by The M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), arts. 1, 11(3) (with arts. 4, 43, Sch. 9)

C283

Pt. 3 modified (25.6.2025) by The M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), arts. 1, 12(1)(2) (with arts. 4, 43, Sch. 9)

C284

S. 59 applied (25.6.2025) by The M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), arts. 1, 12(4)(5) (with arts. 4, 43, Sch. 9)

C285

Ss. 54-106 applied (11.7.2025) by The Oaklands Farm Solar Park Order 2025 (S.I. 2025/739), arts. 1, 8(4) (with Sch. 10)

C286

Ss. 54-106 applied (30.9.2025) by The M60/M62/M66 Simister Island Interchange Development Consent Order 2025 (S.I. 2025/1018), arts. 1, 10(3) (with arts. 5, 34, Sch. 9)

C287

S. 59 applied (30.9.2025) by The M60/M62/M66 Simister Island Interchange Development Consent Order 2025 (S.I. 2025/1018), arts. 1, 11(4)(5) (with arts. 5, 34, Sch. 9)

C288

Ss. 54-106 applied (12.10.2025) by The Gatwick Airport (Northern Runway Project) Development Consent Order 2025 (S.I. 2025/1054), arts. 1, 11(3) (with arts. 5, 9(6), 43, Sch. 9)

C289

S. 59 applied (12.10.2025) by The Gatwick Airport (Northern Runway Project) Development Consent Order 2025 (S.I. 2025/1054), arts. 1, 10(4)(5) (with arts. 5, 9(6), 43, Sch. 9)

C290

S. 59 applied (22.10.2025) by The A46 Newark Bypass Development Consent Order 2025 (S.I. 2025/1090), arts. 1, 13(4)(5) (with arts. 4, 9, 51, Sch. 9)

C291

Ss. 54-106 applied (5.11.2025) by The Tillbridge Solar Order 2025 (S.I. 2025/1105), arts. 1, 8(3) (with art. 49, Sch. 15)

C292

Ss. 54-106 applied (13.11.2025) by The Stonestreet Green Solar Order 2025 (S.I. 2025/1175), arts. 1, 10(3) (with art. 40, Sch. 13)

C293

Ss. 54-106 applied (27.11.2025) by The Cory Decarbonisation Project Order 2025 (S.I. 2025/1227), arts. 1, 13(3) (with Sch. 12)

C294

Ss. 54-106 applied (29.12.2025) by The Helios Renewable Energy Project Order 2025 (S.I. 2025/1372), arts. 1, 9(3) (with Sch. 9)

C295

Ss. 54-106 applied (25.2.2026) by The A46 Coventry Junctions (Walsgrave) Development Consent Order 2026 (S.I. 2026/125), arts. 1, 11(3) (with arts. 40, 45, Sch. 9) (which affecting provisions were superseded by S.I. 2026/537, arts. 1, 11(3) (with arts. 40, 45, Sch. 9))

C296

S. 59 applied (25.2.2026) by The A46 Coventry Junctions (Walsgrave) Development Consent Order 2026 (S.I. 2026/125), arts. 1, 10(4)(5) (with arts. 40, 45, Sch. 9) (which affecting provisions were superseded by S.I. 2026/537, arts. 1, 10(4)(5) (with arts. 40, 45, Sch. 9))

C297

Ss. 54-106 applied (11.3.2026) by The Fenwick Solar Farm Order 2026 (S.I. 2026/151), arts. 1, 8(3) (with Sch. 14)

C298

Ss. 54-106 applied (30.4.2026) by The Springwell Solar Farm Order 2026 (S.I. 2026/419), arts. 1, 8(3) (with art. 48)

C299

Ss. 54-106 applied (23.7.2026) by The Peartree Hill Solar Farm Order 2026 (S.I. 2026/869), arts. 1, 10(3) (with art. 37, Sch. 11)

C300

S. 59 applied (23.7.2026) by The Peartree Hill Solar Farm Order 2026 (S.I. 2026/869), arts. 1, 11(4)(5) (with art. 37, Sch. 11)

C301

S. 59 applied (24.7.2026) by The Dean Moor Solar Farm Order 2026 (S.I. 2026/754), arts. 1, 11(4)(5) (with Sch. 13)

C302

Ss. 54-106 applied (24.7.2026) by The Dean Moor Solar Farm Order 2026 (S.I. 2026/754), arts. 1, 10(3) (with Sch. 13)

C303

Ss. 54-106 applied (30.7.2026) by The One Earth Solar Farm Order 2026 (S.I. 2026/934), arts. 1, 8(3) (with art. 47)

C304

Ss. 54-106 applied (14.9.2026) by The Beacon Fen Energy Park Order 2026 (S.I. 2026/1025), arts. 1, 11(3) (with art. 39, Sch. 11 para. 131)

C305

Ss. 54-106 applied (30.10.2026) by The Green Hill Solar Farm Order 2026 (S.I. 2026/1074), arts. 1, 8(3) (with Sch. 15)

C306

Ss. 54-106 applied (31.10.2026) by The Steeple Renewables Project Order 2026 (S.I. 2026/1086), arts. 1, 8(3) (with Sch. 10)

Commencement

I1

S. 59 wholly in force: s. 59(1)(2)(4)-(6) in force at 1.1.1993, see s. 170 and S.I. 1992/2984, art. 2(2), Sch. 2; s. 59(3) in force at 14.7.1992 by S.I. 1992/1686, art. 3, Sch.

Notes on Part III

Modifications

C1

Pt. 3 (ss. 48-106) modified (14.3.2002) by The Chester Guided Busway Order 2002 (S.I. 2002/412), arts. 3(1)(2) (with art. 38);

Pt. 3 (ss. 48-106) modified (30.4.2002) by The Docklands Light Railway (Silvertown and London City Airport Extension) Order 2002 (S.I. 2002/1066), art. 3(1)

C2

Pt. 3 (ss. 48-106) applied (6.11.2000) by 2000 c. 26, s. 95, Sch. 6 para. 1(3); S.I. 2000/2957, art. 2(1), Sch. 1

Pt. 3 (ss. 48-106) modified (29.3.2001) by S.I. 2001/1348, art. 21(2)

Pt. 3 (ss. 48-106) amended (24.7.2001) by S.I. 2001/3627, art. 4(1)

C3

Definition in Pt. 3 (ss. 48-106) applied (1.12.1991) by Water Industry Act 1991 (c. 56, SIF 130), ss. 71-84, 162-172, 219(1), 223(2), Sch. 6 para. 6(3)(a).

C4

Definition in Pt. 3 (ss. 48-106) applied (1.12.1991) by Water Resources Act 1991 (c. 57, SIF 130), ss. 178, 221(1), 225(2), Sch. 22 para. 3(2).

C5

Pt. 3 excluded (16.3.1992) by Avon Weir Act 1992 (c. v), s. 6(3) (with s. 61(1))

C6

Pt. 3 modified (1.1.1993) by Pipelines Act 1962 (c. 58), s. 16(1) (as substituted (1.1.1993) by New Roads and Street Works Act 1991 (c. 22), s. 168(1), Sch. 8 Pt. 3 para. 101(3); S.I. 1992/2984, art. 2(2), Sch.2)

Pt. 3 modified (27.7.1993) by 1993 c. xv, s. 4(1)

Pt. 3 (ss. 48-106) excluded (27.7.1993) by 1993 c. xv, s. 4(2)

C7

Pt. 3 applied (with modifications) (21.7.1994) by 1994 c. xv, s. 4(1)

Pt. 3 applied (21.7.1994) by 1994 c. xv, s. 45(5)(a)

Pt. 3 excluded (21.7.1994) by 1994 c. xv, s. 21(2)

Pt. 3 restricted (21.7.1994) by 1994 c. xv, s. 4(2)

C8

Pt. 3 excluded (18.12.1996) by 1996 c. 61, s. 52, Sch. 15 para. 1(3)

Pt. 3 modified (18.12.1996) by 1996 c. 61, s. 3, Sch. 3 para. 8

C9

Pt. 3 extended (28.7.1998) by 1998 c. iv, s. 3

C10

Pt. 3 applied (27.8.1998) by S.I. 1998/1936, arts. 1, 41, Sch. 10 paras. 2(8), 3(2)

Pt. 3 modified (13.1.1999) by S.I. 1998/3269, art. 4(1)

C26

Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 3 para. 8

C27

Pt. 3 excluded (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 17 para. 1(3)

C57

Pt. 3 modified (23.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(1), Sch. 4 para. 8(1) (with Sch. 4 para. 8(2))

C58

Pt. 3 excluded (23.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(1), Sch. 33 para. 1(3)

C62

Pt. 3 modified (19.12.2017) by The Network Rail (Buxton Sidings Extension) Order 2017 (S.I. 2017/1150), arts. 1, 4(1) (with art. 32(2))

C83

Pt. 3 excluded (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 32 para. 1(3) (with Sch. 32 para. 1(1))

C84

Pt. 3 modified (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 4 paras. 10(1), 14(3) (with Sch. 4 para. 10(2))

C85

Pt. 3 applied (2.12.2021) by The South Humber Bank Energy Centre Order 2021 (S.I. 2021/1259), arts. 1, 10(3) (with Sch. 8 para. 48)

C112

Pt. 3 modified (23.4.2025) by The Cambridge Waste Water Treatment Plant Relocation Order 2025 (S.I. 2025/452), arts. 1, 10(4)

C115

Pt. 3 modified (14.8.2025) by The Byers Gill Solar Order 2025 (S.I. 2025/934), arts. 1, 10(2) (with art. 43, Sch. 11)

C116

Pt. 3 modified (30.9.2025) by The M60/M62/M66 Simister Island Interchange Development Consent Order 2025 (S.I. 2025/1018), arts. 1, 11(2) (with arts. 5, 34, Sch. 9)

C117

Pt. 3 modified (12.10.2025) by The Gatwick Airport (Northern Runway Project) Development Consent Order 2025 (S.I. 2025/1054), arts. 1, 10(2) (with arts. 5, 9(6), 43, Sch. 9)

C118

Pt. 3 modified (22.10.2025) by The A46 Newark Bypass Development Consent Order 2025 (S.I. 2025/1090), arts. 1, 13(2) (with arts. 4, 9, 51, Sch. 9)

C119

Pt. 3 modified (25.2.2026) by The A46 Coventry Junctions (Walsgrave) Development Consent Order 2026 (S.I. 2026/125), arts. 1, 10(1) (with arts. 40, 45, Sch. 9) (which affecting provisions were superseded by S.I. 2026/537, arts. 1, 10(1) (with arts. 40, 45, Sch. 9))

C120

Pt. 3 modified (23.7.2026) by The Peartree Hill Solar Farm Order 2026 (S.I. 2026/869), arts. 1, 11(1)(2) (with art. 37, Sch. 11)

C121

Pt. 3 modified (24.7.2026) by The Dean Moor Solar Farm Order 2026 (S.I. 2026/754), arts. 1, 11(2) (with Sch. 13)

C122

Pt. 3 modified (31.10.2026) by The Steeple Renewables Project Order 2026 (S.I. 2026/1086), arts. 1, 9(9) (with Sch. 10)