Section 59 General duty of street authority to co-ordinate works.C5C8C9C13C14C16C19C20C21C23C28C31C35C36C37C40C41C44C46C48C52C55C60C63C64C67C70C71C74C77C80C82C86C90C99C108C110C111C115C116C118C119C127C132C134C139C143C145C148C149C150C153C155C157C158C162C167C170C172C174C179C182C183C187C188C190C193C201C204C206C207C214C217C218C220C222C223C226C227C228C234C238C241C244C247C250I1C1C2C3C4C6C7C10C11C12C15C17C18C22C24C25C26C27C29C30C32C33C34C38C39C42C43C45C47C49C50C51C53C54C56C57C58C59C61C62C65C66C68C69C72C73C75C76C78C79C81C83C84C85C87C88C89C91C92C93C94C95C96C97C98C100C101C102C103C104C105C106C107C109C112C113C114C117C120C121C122C123C124C125C126C128C129C130C131C133C135C136C137C138C140C141C142C144C146C147C151C152C154C156C159C160C161C163C164C165C166C168C169C171C173C175C176C177C178C180C181C184C185C186C189C191C192C194C195C196C197C198C199C200C202C203C205C208C209C210C211C212C213C215C216C219C221C224C225C229C230C231C232C233C235C236C237C239C240C242C243C245C246C248C249C251C252C253C254C255C256C257C258C259C260C261C262C263C264C265C266C267C268C269C270C271C272C273C274C275C276C277C278C279C280C281C282C283C284C285C286C287C288C289C290C291C292C293C294C295C296C297C298C299C300C301C302C303C304C305C306
England and Wales
A street authority shall use their best endeavours to co-ordinate the execution of works of all kinds (including works for road purposes) F1and the carrying out of relevant activities in the streets for which they are responsible—
in the interests of safety,
to minimise the inconvenience to persons using the street (having regard, in particular, to the needs of people with a disability), and
to protect the structure of the street and the integrity of apparatus in it.
That duty extends to co-ordination with other street authorities where works F2or relevant activities in a street for which one authority are responsible affect streets for which other authorities are responsible.
The Secretary of State shall issue or approve for the purposes of this section codes of practice giving practical guidance as to the matters mentioned above; and in discharging their general duty of co-ordination a street authority shall have regard to any such code of practice.
If it appears to the Secretary of State that a street authority are not properly discharging their general duty of co-ordination, he may direct the authority to supply him with such information as he considers necessary to enable him to decide whether that is the case and if so what action to take.
The direction shall specify the information to be provided and the period within which it is to be provided.
If after the end of that period (whether or not the direction has been complied with) it appears to the Secretary of State that the authority are not properly discharging their general duty of co-ordination, he may direct the authority to take such steps as he considers appropriate for the purpose of discharging that duty.
The direction shall specify the steps to be taken and the period within which they are to be taken, and may include a requirement to make a report or periodic reports to the Secretary of State as to what steps have been taken and the results of taking them.
A direction under this section may be varied or revoked by a further direction.
In this section “relevant activities” means any activity, other than the execution of works in the street or the use of the street by traffic (including pedestrians), which—
involves the temporary occupation or use of space in a street;
is subject to regulation by the street authority by virtue of provision made by or under any Act other than this Act; and
is prescribed by regulations made by the Secretary of State.
Annotations
Textual amendments
- F1
Words in s. 59(1) inserted (29.6.2007 for E. for specified purposes, 26.11.2007 for W. for specified purposes) by Traffic Management Act 2004 (c. 18), ss. 42(2), 99(1); S.I. 2007/1890, art. 2, Sch.; S.I. 2007/3174, art. 2, Sch.
- F2
Words in s. 59(2) inserted (29.6.2007 for E. for specified purposes, 26.11.2007 for W. for specified purposes) by Traffic Management Act 2004 (c. 18), ss. 42(3), 99(1); S.I. 2007/1890, art. 2, Sch.; S.I. 2007/3174, art. 2, Sch.
- F3
S. 59(7) inserted (29.6.2007 for E. for specified purposes, 26.11.2007 for W. for specified purposes) by Traffic Management Act 2004 (c. 18), ss. 42(4), 99(1); S.I. 2007/1890, art. 2, Sch.; S.I. 2007/3174, art. 2, Sch.
Modifications
- C1
S. 59 applied (4.4.1996) by S.I. 1996/937, art. 8(4)(5)
S. 59 applied (13.1.1999) by S.I. 1998/3269, art. 4(2)(3)
S. 59 applied (27.8.1998) by S.I. 1998/1936, art. 4(3)
S. 59 applied (21.5.1997) by S.I. 1997/1266, art. 5(2)(3)
S. 59 applied (10.2.1997) by S.I. 1997/264, art. 8(6)(7)
S. 59 applied (with modifications) (30.4.1999) by S.I. 1999/1306, art. 8(4)(5)
S. 59 applied (with modifications) (21.7.1999) by S.I. 1999/2129, art. 8(5)(6)
S. 59 applied (with modifications) (20.8.1999) by S.I. 1999/2336, art. 9(5)(6)(8)
S. 59 applied (with modifications) (23.8.1999) by S.I. 1999/2981, art. 7(5)(6)
S. 59 applied (with modifications) (11.11.1996) by S.I. 1996/2714, art. 4(2)(3)
S. 59: functions of a local authority made exercisable by, or by employees of, such person as may be authorised in that behalf by the local highway authority whose function it is (23.7.1999) by S.I. 1999/2106, art. 2, Sch. 2 para. 1(c)
S. 59 applied (with modifications) (29.3.2001) by S.I. 2001/1348, art. 21(3)-(5)
S. 59 applied (with modifications) (29.3.2001) by S.I. 2001/1347, art. 3(3)
S. 59 applied (with modifications) (18.7.2001) by S.I. 2001/2870, art. 10(6)
S. 59 applied (with modifications) (24.7.2001) by S.I. 2001/3627, art. 4(3)(4)
S. 59 applied (with modifications) (9.11.2001) by S.I. 2001/3682, art. 8(6)
- C2
S. 59 applied (with modifications) (14.3.2002) by The Chester Guided Busway Order 2002 (S.I. 2002/412), art. 9(4)(5) (with art. 38);
S. 59 applied (with modifications) (30.4.2002) by The Docklands Light Railway (Silvertown and London City Airport Extension) Order 2002 (S.I. 2002/1066), art. 3(3)(4);
S. 59 applied (with modifications) (31.5.2002) by The Greater Manchester (Light Rapid Transit System) (Trafford Depot) Order 2002 (S.I. 2002/1327), art. 3(3)
- C3
S. 59 applied (with modifications) (28.4.2003) by The Network Rail (West Coast Main Line) Order 2003 (S.I. 2003/1075), arts. 1, 13(6)(7)(8) (with art. 40)
- C4
S. 59 applied (with modifications) (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), arts. 1, 3(3)(4)
- C5
Pt. 3 modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), arts. 1, 3(1)
- C6
S. 59 applied (with modifications) (19.11.2004) by The Scarweather Sands Offshore Wind Farm Order 2004 (S.I. 2004/3054), arts. 1, 6(4)(5) (with art. 38)
- C7
S. 59 applied (with modifications) (11.2.2005) by The Merseytram (Liverpool City Centre to Kirkby) Order 2005 (S.I. 2005/120), arts. 1, 4(4)(5) (with arts. 65, 66)
- C8
Pt. 3 modified (11.2.2005) by The Merseytram (Liverpool City Centre to Kirkby) Order 2005 (S.I. 2005/120), arts. 1, 4(1)(2) (with arts. 65, 66)
- C9
Pt. 3 modified (22.3.2005) by The Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), art. 3(1)(2) (with art. 51)
- C10
S. 59 applied (with modifications) (22.3.2005) by The Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), art. 3(3)(4) (with art. 51)
- C11
S. 59 applied (with modifications) (4.5.2005) by The Telford Railfreight Terminal (Donnington) Order 2005 (S.I. 2005/1163), arts. 1, 12(7)
- C12
S. 59 applied (with modifications) (22.7.2005) by The Midland Metro (Birmingham City Centre Extension, etc.) Order 2005 (S.I. 2005/1794), arts. 1, 3(3)(4) (with art. 47)
- C13
Pt. 3 modified (22.7.2005) by The Midland Metro (Birmingham City Centre Extension, etc.) Order 2005 (S.I. 2005/1794), arts. 1, 3(1)(2) (with art. 47)
- C14
Pt. 3 applied (3.8.2005) by The Greater Manchester (Leigh Busway) Order 2005 (S.I. 2005/1918), arts. 1, 3(1)
- C15
S. 59 applied (with modifications) (3.8.2005) by The Greater Manchester (Leigh Busway) Order 2005 (S.I. 2005/1918), arts. 1, 3(3)(4)
- C16
Pt. 3 modified (26.8.2005) by The River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), arts. 1, 8(7) (with arts. 45(1), 48, Sch. 10 paras. 21, 29)
- C17
S. 59 applied (with modifications) (26.8.2005) by The River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), arts. 1, 8(9)(10) (with arts. 45(1), 48, Sch. 10 paras. 21, 29)
- C18
Ss. 59, 60 applied (with modifications) (8.10.2005) by The Leicestershire County Council (Ashby de la Zouch Canal Extension) Order 2005 (S.I. 2005/2786), arts. 1, 9(2)(3)
- C19
Pt. 3 restricted (8.10.2005) by The Leicestershire County Council (Ashby de la Zouch Canal Extension) Order 2005 (S.I. 2005/2786), arts. 1, 10(3)
- C20
Pt. 3 modified (8.10.2005) by The Leicestershire County Council (Ashby de la Zouch Canal Extension) Order 2005 (S.I. 2005/2786), arts. 1, 9(1)
- C21
Pt. 3 modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), arts. 1, 3(1) (with arts. 3(5), 15(3))
- C22
S. 59 applied (with modifications) (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), arts. 1, 3(4) (with arts. 3(5), 15(3))
- C23
Pt. 3 applied (11.1.2006) by The Cambridgeshire Guided Busway Order 2005 (S.I. 2005/3523), arts. 1, 3(1) (with art. 52)
- C24
S. 59 applied (with modifications) (11.1.2006) by The Cambridgeshire Guided Busway Order 2005 (S.I. 2005/3523), arts. 1, 3(3)(4) (with art. 52)
- C25
S. 59 applied (with modifications) (3.7.2006) by The Port of Blyth (Battleship Wharf Railway) Order 2006 (S.I. 2006/1518), arts. 1, 4
- C26
S. 59 applied (with modifications) (14.9.2006) by The Borough of Poole (Poole Harbour Opening Bridges) Order 2006 (S.I. 2006/2310), arts. 1, 9(5)(6) (with art. 40, Sch. 7 para. 12)
- C27
S. 59 applied (with modifications) (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), arts. 1, 3(4)(5) (with art. 43)
- C28
Pt. 3 modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), arts. 1, 3(1)(2) (with art. 43)
- C29
S. 59 applied (with modifications) (13.12.2006) by The Network Rail (Thameslink 2000) Order 2006 (S.I. 2006/3117), arts. 1, 16(6)(7) (with arts. 34, 35(2))
- C30
S. 59 applied (with modifications) (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), arts. 1, 10(5)(6)
- C31
Pt. 3 modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), arts. 1, 3
- C32
S. 59 applied (with modifications) (19.3.2007) by The Ouseburn Barrage Order 2007 (S.I. 2007/608), arts. 1, 8(2) (with arts. 46-48, Sch. 6 para. 23)
- C33
S. 59 applied (with modifications) (23.8.2007) by The Docklands Light Railway (Capacity Enhancement and 2012 Games Preparation) Order 2007 (S.I. 2007/2297), arts. 1, 3(4)(5) (with arts. 3(6), 12(3))
- C34
S. 59 applied (with modifications) (28.9.2007) by The London Gateway Logistics and Commercial Centre Order 2007 (S.I. 2007/2657), arts. 1, 3(2)(3) (with arts. 19, 28, Sch. 3 para. 13(2))
- C35
Pt. 3 modified (28.9.2007) by The London Gateway Logistics and Commercial Centre Order 2007 (S.I. 2007/2657), arts. 1, 3(1) (with arts. 19, 28, Sch. 3 para. 13(2))
- C36
Pt. 3 modified (16.5.2008) by The London Gateway Port Harbour Empowerment Order 2008 (S.I. 2008/1261), arts. 1, 6(6) (with arts. 41(1), 45, 54(2), 55, 56, 57, 58(6))
- C37
Pt. 3 modified (16.5.2008) by The London Gateway Port Harbour Empowerment Order 2008 (S.I. 2008/1261), arts. 1, 6(1) (with arts. 41(1), 45, 54(2), 55, 56, 57, 58(6))
- C38
S. 59 applied (with modifications) (16.5.2008) by The London Gateway Port Harbour Empowerment Order 2008 (S.I. 2008/1261), arts. 1, 6(3)(4) (with arts. 41(1), 45, 54(2), 55, 56, 57, 58(6))
- C39
S. 59 applied (with modifications) (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), arts. 1, 4(2)(3) (with art. 36(3))
- C40
Pt. 3 modified (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), arts. 1, 4(1) (with art. 36(3))
- C41
Pt. 3 modified (9.6.2009) by The Nottingham Express Transit System Order 2009 (S.I. 2009/1300), arts. 1, 4(1)(2) (with Sch. 13 para. 14(2), Sch. 14 para. 19, Sch. 16)
- C42
S. 59 applied (9.6.2009) by The Nottingham Express Transit System Order 2009 (S.I. 2009/1300), arts. 1, 4(4)(5) (with Sch. 13 para. 14(2), Sch. 14 para. 19, Sch. 16)
- C43
S. 59 applied (with modifications) (18.9.2009) by The London Underground (Victoria Station Upgrade) Order 2009 (S.I. 2009/2364), arts. 1, 3(4)(5)
- C44
Pt. 3 modified (18.9.2009) by The London Underground (Victoria Station Upgrade) Order 2009 (S.I. 2009/2364), arts. 1, 3(1)(2)
- C45
S. 59 applied (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), arts. 1, 4(1)(2)
- C46
Pt. 3 modified (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 3(1) (with art. 51, Sch. 10 paras. 68, 85)
- C47
S. 59 applied (with modifications) (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 3(2)(3) (with art. 51, Sch. 10 paras. 68, 85)
- C48
Pt. 3 modified (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 4(1)
- C49
S. 59 applied (with modifications) (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 4(2)-(3)
- C50
S. 59 applied (26.9.2012) by The Network Rail (Ipswich Chord) Order 2012 (S.I. 2012/2284), arts. 1, 10(2) (with art. 26(2))
- C51
S. 59 applied (6.11.2012) by The Network Rail (North Doncaster Chord) Order 2012 (S.I. 2012/2635), arts. 1, 14(2)(3) (with art. 35(2))
- C52
Pt. 3 modified (13.11.2012) by The Chiltern Railways (Bicester to Oxford Improvements) Order 2012 (S.I. 2012/2679), arts. 1, 4(1) (with art. 42(2))
- C53
S. 59 applied (13.11.2012) by The Chiltern Railways (Bicester to Oxford Improvements) Order 2012 (S.I. 2012/2679), arts. 1, 4(2)(3) (with art. 42(2))
- C54
Ss. 54-106 applied (28.2.2013) by The Rookery South (Resource Recovery Facility) Order 2011 2013 (S.I. 2013/680), art. 10(3)
- C55
Pt. 3 applied (with modifications) (9.4.2013) by The Hinkley Point C (Nuclear Generating Station) Order 2013 (S.I. 2013/648), arts. 1, 9 (with arts. 48, 68, 79)
- C56
Ss. 54-106 applied (9.4.2013) by The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road)) Order 2013 (S.I. 2013/675), arts. 1, 9(2)
- C57
Ss. 54-106 applied (15.6.2013) by The Galloper Wind Farm Order 2013 (S.I. 2013/1203), arts. 1, 13(3) (with arts. 11, 12)
- C58
Ss. 54-106 applied (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 9(3) (with art. 30)
- C59
S. 59 applied (with modifications) (21.8.2013) by The Croxley Rail Link Order 2013 (S.I. 2013/1967), arts. 1, 4(1)(2)
- C60
Pt. 3 modified (22.8.2013) by The Leeds Railway Station (Southern Entrance) Order 2013 (S.I. 2013/1933), arts. 1, 3(1)
- C61
S. 59 applied (with modifications) (22.8.2013) by The Leeds Railway Station (Southern Entrance) Order 2013 (S.I. 2013/1933), arts. 1, 3(3)(4)
- C62
S. 59 applied (with modifications) (6.11.2013) by The Transport for Greater Manchester (Light Rapid Transit System) (Second City Crossing) Order 2013 (S.I. 2013/2587), arts. 1, 4(4)(5) (with arts. 42, 43)
- C63
Pt. 3 modified (6.11.2013) by The Transport for Greater Manchester (Light Rapid Transit System) (Second City Crossing) Order 2013 (S.I. 2013/2587), arts. 1, 4(1)(2) (with arts. 42, 43)
- C64
Pt. 3 modified (20.11.2013) by The M1 Junction 10a (Grade Separation) Order 2013 (S.I. 2013/2808), arts. 1, 8(1)(2)
- C65
S. 59 applied (20.11.2013) by The M1 Junction 10a (Grade Separation) Order 2013 (S.I. 2013/2808), arts. 1, 8(4)(5)
- C66
S. 59 applied (with modifications) (21.11.2013) by The Network Rail (Redditch Branch Enhancement) Order 2013 (S.I. 2013/2809), arts. 1, 10(2)(3) (with arts. 27(2), 39, Sch. 10 para. 4)
- C67
Pt. 3 modified (9.1.2014) by The National Grid (King’s Lynn B Power Station Connection) Order 2013 (S.I. 2013/3200), arts. 1, 9(1)
- C68
S. 59 applied (with modifications) (9.1.2014) by The National Grid (King’s Lynn B Power Station Connection) Order 2013 (S.I. 2013/3200), arts. 1, 9(2)(3)
- C69
S. 59 applied (with modifications) (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(4)(5) (with arts. 57, 58, Sch. 11 para. 19)
- C70
Pt. 3 applied (with modifications) (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(9) (with arts. 57, 58, Sch. 11 para. 19)
- C71
Pt. 3 modified (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(1)(2) (with arts. 57, 58, Sch. 11 para. 19)
- C72
S. 59 applied (with modifications) (21.4.2014) by The Network Rail (Norton Bridge Area Improvements) Order 2014 (S.I. 2014/909), arts. 1, 12(3)(4) (with art. 34(2))
- C73
S. 59 applied (with modifications) (7.5.2014) by The National Grid (North London Reinforcement Project) Order 2014 (S.I. 2014/1052), arts. 1, 13(2)(3)
- C74
Pt. 3 modified (7.5.2014) by The National Grid (North London Reinforcement Project) Order 2014 (S.I. 2014/1052), arts. 1, 13(1)
- C75
Ss. 54-106 applied (7.7.2014) by The East Anglia ONE Offshore Wind Farm Order 2014 (S.I. 2014/1599), arts. 1, 8(3) (with arts. 37, 38, Sch. 9 para. 19)
- C76
Ss. 54-106 applied (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), arts. 1, 15(3) (with arts. 7(6), 12, 13, Sch. 12 Pt. 1 para. 19, Sch. 12 Pt. 2 para. 6, sch. 12 Pt. 3 para. 5, Sch. 12 Pt. 4 para. 4, Sch. 12 Pt. 5 para. 4)
- C77
Pt. 3 restricted (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), art. 1, Sch. 12 Pt. 2 para. 3 (with arts. 12, 13, Sch. 12 Pt. 1 paras. 6(3), 19, Pt. 2 paras. 3, 6, 13, Pt. 3 para. 5, Pt. 4 para. 4, Pt. 5 para. 4)
- C78
S. 59 applied (with modifications) (19.8.2014) by The Network Rail (Huyton) Order 2014 (S.I. 2014/2027), arts. 1, 4(4) (with art. 31(2))
- C79
S. 59 applied (with modifications) (18.9.2014) by The A556 (Knutsford to Bowdon Improvement) Development Consent Order 2014 (S.I. 2014/2269), arts. 1, 8(4)(5)
- C80
Pt. 3 modified (18.9.2014) by The A556 (Knutsford to Bowdon Improvement) Development Consent Order 2014 (S.I. 2014/2269), arts. 1, 8(1)(2)
- C81
Ss. 54-106 applied (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(4), 11(5) (with arts. 55, 56)
- C82
Pt. 3 modified (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(5), 11(4)
- C83
Ss. 54-106 applied (2.10.2014) by The North Killingholme (Generating Station) Order 2014 (S.I. 2014/2434), arts. 1, 9(3) (with arts. 6, 9(4), 13, Sch. 8 Pt. 1 para. 6, Sch. 8 Pt. 3 paras. 4(3), 6, 17, Sch. 8 Pt. 5 para. 9)
- C84
S. 59 applied (2.10.2014) by The Clocaenog Forest Wind Farm Order 2014 (S.I. 2014/2441), arts. 1, 13(2)(3) (with art. 33)
- C85
S. 59 applied (with modifications) (21.10.2014) by The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014 (S.I. 2014/2637), arts. 1, 8(4)(5)
- C86
Pt. 3 modified (21.10.2014) by The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014 (S.I. 2014/2637), arts. 1, 8(1)(2)
- C87
Ss. 54-106 applied (29.10.2014) by The Able Marine Energy Park Development Consent Order 2014 (S.I. 2014/2935), art. 15(3) (with arts. 30(4), 53)
- C88
Ss. 54-106 applied (28.11.2014) by The Walney Extension Offshore Wind Farm Order 2014 (S.I. 2014/2950), arts. 1, 10(3) (with arts. 38, 39)
- C89
S. 59 applied (with modifications) (15.12.2014) by The London Underground (Northern Line Extension) Order 2014 (S.I. 2014/3102), arts. 1, 3(4)(5) (with Sch. 8 para. 45)
- C90
Pt. 3 modified (15.12.2014) by The London Underground (Northern Line Extension) Order 2014 (S.I. 2014/3102), arts. 1, 3(2) (with Sch. 8 para. 45)
- C91
S. 59 applied (with modifications) (31.12.2014) by The Hornsea One Offshore Wind Farm Order 2014 (S.I. 2014/3331), arts. 1, 7(1)(2) (with arts. 37, 38)
- C92
Ss. 54-106 applied (7.1.2015) by The Willington C Gas Pipeline Order 2014 (S.I. 2014/3328), arts. 1, 10(3)
- C93
Ss. 54-106 applied (2.2.2015) by The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015 (S.I. 2015/23), arts. 1, 9(2)
- C94
S. 59 applied (with modifications) (25.2.2015) by The A160/A180 (Port of Immingham Improvement) Development Consent Order 2015 (S.I. 2015/129), arts. 1, 9(4)(5)
- C95
Ss. 54-106 applied (26.2.2015) by The Cornwall Council (A30 Temple to Higher Carblake Improvement) Order 2015 (S.I. 2015/147), arts. 1, 9(3)
- C96
Ss. 54-106 applied (11.3.2015) by The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 (S.I. 2015/318), arts. 1, 13(3) (with arts. 8(5), 35, 40, 41, Sch. 12 Pt. 1 paras. 4, 9(2), 10, Pt. 2 paras. 4(2)(3), 19, Pt. 4 paras. 3, 4, 16)
- C97
Ss. 54-106 applied (1.4.2015) by The Knottingley Power Plant Order 2015 (S.I. 2015/680), arts. 1, 10(3) (with art. 7(6), Sch. 8 para. 10)
- C98
S. 59 applied (with modifications) (21.4.2015) by The Network Rail (Ordsall Chord) Order 2015 (S.I. 2015/780), arts. 1, 4(2)(3) (with art. 36(2))
- C99
Pt. 3 modified (21.4.2015) by The Network Rail (Ordsall Chord) Order 2015 (S.I. 2015/780), arts. 1, 4(1) (with art. 36(2))
- C100
Ss. 54-106 applied (23.6.2015) by The Norfolk County Council (Norwich Northern Distributor Road (A1067 to A47(T))) Order 2015 (S.I. 2015/1347), arts. 1, 9(2)
- C101
Ss. 54-106 applied (30.6.2015) by The Swansea Bay Tidal Generating Station Order 2015 (S.I. 2015/1386), arts. 1, 9(3) (with arts. 51, 53)
- C102
Ss. 54-106 applied (7.8.2015) by The Preesall Underground Gas Storage Facility Order 2015 (S.I. 2015/1561), arts. 1, 9(3) (with art. 44)
- C103
Ss. 54-106 applied (14.8.2015) by The Progress Power (Gas Fired Power Station) Order 2015 (S.I. 2015/1570), arts. 1, 10(3)
- C104
Ss. 54-106 applied (26.8.2015) by The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (S.I. 2015/1592), arts. 1, 14(3) (with arts. 35, 40, 41)
- C105
Ss. 54-106 applied (19.11.2015) by The Ferrybridge Multifuel 2 Power Station Order 2015 (S.I. 2015/1832), arts. 1(2), 9(3)
- C106
Ss. 54-106 applied (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 9(3) (with art. 26)
- C107
S. 59 applied (with modifications) (12.1.2016) by The London Underground (Bank Station Capacity Upgrade) Order 2015 (S.I. 2015/2044), arts. 1, 4(4)(5)
- C108
Pt. 3 modified (12.1.2016) by The London Underground (Bank Station Capacity Upgrade) Order 2015 (S.I. 2015/2044), arts. 1, 4(1)(2)
- C109
S. 59 modified (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 11(2)(3) (with art. 32)
- C110
Pt. 3 modified (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 11(1) (with art. 32)
- C111
Pt. 3 modified (18.2.2016) by The A19/A1058 Coast Road (Junction Improvement) Development Consent Order 2016 (S.I. 2016/73), arts. 1, 8(2) (with art. 37)
- C112
S. 59 applied (18.2.2016) by The A19/A1058 Coast Road (Junction Improvement) Development Consent Order 2016 (S.I. 2016/73), arts. 1, 8(4)(5) (with art. 37)
- C113
Ss. 54-106 applied (with modifications) (25.3.2016) by The Thorpe Marsh Gas Pipeline Order 2016 (S.I. 2016/297), arts. 1, 12(3) (with art. 39)
- C114
S. 59 applied (with modifications) (1.6.2016) by The A14 Cambridge to Huntingdon Improvement Scheme Development Consent Order 2016 (S.I. 2016/547), arts. 1, 10(4)(5) (with arts. 4, 5(3))
- C115
Pt. 3 modified (1.6.2016) by The A14 Cambridge to Huntingdon Improvement Scheme Development Consent Order 2016 (S.I. 2016/547), arts. 1, 10(1)(2) (with arts. 4, 5(3))
- C116
Pt. 3 applied (14.6.2016) by The Midland Metro (Birmingham City Centre Extension, etc.) (Land Acquisition and Variation) Order 2016 (S.I. 2016/545), arts. 1, 3(1) (with art. 39)
- C117
S. 59 applied (with modifications) (14.6.2016) by The Midland Metro (Birmingham City Centre Extension, etc.) (Land Acquisition and Variation) Order 2016 (S.I. 2016/545), arts. 1, 3(3)(4) (with art. 39)
- C118
Pt. 3 modified (14.6.2016) by The Midland Metro (Birmingham City Centre Extension, etc.) (Land Acquisition and Variation) Order 2016 (S.I. 2016/545), arts. 1, 3(2) (with art. 39)
- C119
Pt. 3 applied (with modifications) (2.8.2016) by The Midland Metro (Wolverhampton City Centre Extension) Order 2016 (S.I. 2016/684), arts. 1, 5(1)(2) (with arts. 46, 47, Sch. 8 para. 2(7), Sch. 9 para. 4, Sch. 10 para. 12(2))
- C120
S. 59 applied (with modifications) (2.8.2016) by The Midland Metro (Wolverhampton City Centre Extension) Order 2016 (S.I. 2016/684), arts. 1, 5(3)(4) (with arts. 46, 47, Sch. 9 para. 4, Sch. 10 para. 12(2))
- C121
Ss. 54-106 applied (2.8.2016) by The Meaford Gas Fired Generating Station Order 2016 (S.I. 2016/779), arts. 1, 11(3)
- C122
Ss. 54-106 applied (10.8.2016) by The York Potash Harbour Facilities Order 2016 (S.I. 2016/772), arts. 1, 10(3) (with arts. 35, 36)
- C123
Ss. 54-106 applied (19.8.2016) by The North Wales Wind Farms Connection Order 2016 (S.I. 2016/818), arts. 1, 10(5) (with art. 35)
- C124
S. 59 applied (with modifications) (7.9.2016) by The Hornsea Two Offshore Wind Farm Order 2016 (S.I. 2016/844), arts. 1(2), 10(2)(d) (with arts. 37, 38)
- C125
Ss. 54-106 applied (with modifications) (15.9.2016) by The River Humber Gas Pipeline Replacement Order 2016 (S.I. 2016/853), arts. 1, 11(3) (with art. 43)
- C126
S. 59 applied (with modifications) (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 9(4)(5)
- C127
Pt. 3 modified (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 9(2)
- C128
Ss. 54-106 applied (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 11(3)
- C129
Ss. 54-106 applied (27.9.2016) by The Triton Knoll Electrical System Order 2016 (S.I. 2016/880), arts. 1(2), 8(3) (with arts. 39, 40, Sch. 8 para. 19)
- C130
S. 59 applied (28.10.2016) by The Brechfa Forest Wind Farm Connection Order 2016 (S.I. 2016/987), arts. 1, 8(3)(e) (with art. 37)
- C131
S. 59 applied (with modifications) (24.11.2016) by The Transport for Greater Manchester (Light Rapid Transit System) (Trafford Park Extension) Order 2016 (S.I. 2016/1035), arts. 1, 4(4)(5) (with arts. 43, 44)
- C132
Pt. 3 modified (24.11.2016) by The Transport for Greater Manchester (Light Rapid Transit System) (Trafford Park Extension) Order 2016 (S.I. 2016/1035), arts. 1, 4(1)(2) (with arts. 43, 44)
- C133
Ss. 54-106 applied (18.3.2017) by The North London Heat and Power Generating Station Order 2017 (S.I. 2017/215), arts. 1, 10(3)
- C134
Pt. 3 modified (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 12(1) (with art. 31)
- C135
S. 59 applied (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 12(2)(3)(d) (with art. 31)
- C136
Ss. 54-106 applied (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 10(3) (with art. 31)
- C137
Ss. 54-106 applied (5.4.2017) by The Keuper Underground Gas Storage Facility Order 2017 (S.I. 2017/433), arts. 1, 10(4)
- C138
Ss. 54-106 applied (8.8.2017) by The Wrexham Gas Fired Generating Station Order 2017 (S.I. 2017/766), arts. 1, 10(3)
- C139
Pt. 3 applied (with modifications) (24.8.2017) by The National Grid (Richborough Connection Project) Development Consent Order 2017 (S.I. 2017/817), arts. 1, 9(1) (with art. 22)
- C140
S. 59 applied (with modifications) (24.8.2017) by The National Grid (Richborough Connection Project) Development Consent Order 2017 (S.I. 2017/817), arts. 1, 11(3)(d) (with art. 22)
- C141
Ss. 54-106 applied (29.8.2017) by The East Anglia THREE Offshore Wind Farm Order 2017 (S.I. 2017/826), arts. 1, 8(3) (with arts. 5(9), 36, 37, Sch. 8 para. 34)
- C142
S. 59 applied (with modifications) (5.9.2017) by The London Overground (Barking Riverside Extension) Order 2017 (S.I. 2017/830), arts. 1, 3(4)(5) (with Sch. 8 para. 20)
- C143
Pt. 3 modified (5.9.2017) by The London Overground (Barking Riverside Extension) Order 2017 (S.I. 2017/830), arts. 1, 3(2) (with Sch. 8 para. 20)
- C144
S. 59 applied (with modifications) (19.12.2017) by The Network Rail (Buxton Sidings Extension) Order 2017 (S.I. 2017/1150), arts. 1, 4(3)(4) (with art. 32(2))
- C145
Pt. 3 modified (22.12.2017) by The M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202), arts. 1, 11(1)(2) (with arts. 4, 37)
- C146
S. 59 applied (22.12.2017) by The M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202), arts. 1, 11(4)(5) (with arts. 4, 37)
- C147
S. 59 applied (with modifcations) (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), arts. 1, 3(4)(5) (with arts. 55-57, Sch. 8 para. 13)
- C148
Pt. 3 applied (with modifications) (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), arts. 1, 3(2) (with arts. 55-57, Sch. 8 para. 13)
- C149
Pt. 3 modified (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), arts. 1, 3(2) (with arts. 55-57, Sch. 8 para. 13)
- C150
Pt. 3 applied (with modifications) (4.1.2018) by The Blackpool Tramway (Blackpool North Extension) Order 2017 (S.I. 2017/1214), arts. 1, 5(1)(2) (with arts. 58, 59)
- C151
S. 59 applied (4.1.2018) by The Blackpool Tramway (Blackpool North Extension) Order 2017 (S.I. 2017/1214), arts. 1, 5(4)(5) (with arts. 5(7), 58, 59)
- C152
S. 59 applied (18.4.2018) by The Network Rail (Hope Valley Capacity) Order 2018 (S.I. 2018/446), arts. 1, 4(3)(4) (with arts. 24(8), 33(2))
- C153
Pt. 3 applied (18.4.2018) by The Network Rail (Hope Valley Capacity) Order 2018 (S.I. 2018/446), arts. 1, 4(1) (with arts. 24(8), 33(2))
- C154
S. 59 applied (31.5.2018) by The Silvertown Tunnel Order 2018 (S.I. 2018/574), arts. 1(2), 7(4)(5)
- C155
Pt. 3 modified (31.5.2018) by The Silvertown Tunnel Order 2018 (S.I. 2018/574), arts. 1(2), 7(2)
- C156
S. 59 applied (with modifications) (24.8.2018) by The Network Rail (Werrington Grade Separation) Order 2018 (S.I. 2018/923), arts. 1, 4(2)(3) (with art. 31(2))
- C157
Pt. 3 modified (24.8.2018) by The Network Rail (Werrington Grade Separation) Order 2018 (S.I. 2018/923), arts. 1, 4(1) (with art. 31(2))
- C158
Pt. 3 modified (3.10.2018) by The A19/A184 Testo's Junction Alteration Development Consent Order 2018 (S.I. 2018/994), arts. 1, 9(1)(2) (with arts. 3(3), 5)
- C159
S. 59 applied (3.10.2018) by The A19/A184 Testo's Junction Alteration Development Consent Order 2018 (S.I. 2018/994), arts. 1, 9(4)(5) (with arts. 3(3), 5)
- C160
Ss. 54-106 applied (12.10.2018) by The Eggborough Gas Fired Generating Station Order 2018 (S.I. 2018/1020), arts. 1, 8(3) (with arts. 6, 42)
- C161
S. 59 applied (with modifications) (13.3.2019) by The Port of Tilbury (Expansion) Order 2019 (S.I. 2019/359), arts. 1, 9(4)(5) (with arts. 55, 56)
- C162
Pt. 3 modified (13.3.2019) by The Port of Tilbury (Expansion) Order 2019 (S.I. 2019/359), arts. 1, 9(1)(2)(8) (with arts. 55, 56)
- C163
Ss. 54-106 applied (3.4.2019) by The Millbrook Gas Fired Generating Station Order 2019 (S.I. 2019/578), arts. 1, 9(3)
- C164
Ss. 54-106 applied (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), arts. 1, 9(3)
- C165
Ss. 54-106 applied (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), arts. 1, 9(3)
- C166
S. 59 applied (with modifications) (25.2.2020) by The Network Rail (East West Rail) (Bicester to Bedford Improvements) Order 2020 (S.I. 2020/114), arts. 1, 4(3)(4) (with art. 37(2))
- C167
Pt. 3 modified (25.2.2020) by The Network Rail (East West Rail) (Bicester to Bedford Improvements) Order 2020 (S.I. 2020/114), arts. 1, 4(1) (with art. 37(2))
- C168
Ss. 54-106 applied (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 11(3) (with art. 3(1))
- C169
S. 59 applied (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 12(4)(5)(d) (with art. 3(1))
- C170
Pt. 3 applied (with modifications) (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 12(1)(2) (with art. 3(1))
- C171
S. 59 applied (with modifications) (4.3.2020) by The Midland Metro (Birmingham Eastside Extension) Order 2020 (S.I. 2020/141), arts. 1, 5(3)(4) (with arts. 47, 48, Sch. 10 para. 19)
- C172
Pt. 3 applied (with modifications) (4.3.2020) by The Midland Metro (Birmingham Eastside Extension) Order 2020 (S.I. 2020/141), arts. 1, 5(1)(2) (with arts. 47, 48, Sch. 10 para. 19)
- C173
Ss. 54-106 applied (14.4.2020) by The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020 (S.I. 2020/325), arts. 1, 10(4) (with art. 7)
- C174
Pt. 3 modified (30.4.2020) by The A585 Windy Harbour to Skippool Highway Development Consent Order 2020 (S.I. 2020/402), arts. 1, 9(2) (with arts. 5, 44)
- C175
S. 59 applied (30.4.2020) by The A585 Windy Harbour to Skippool Highway Development Consent Order 2020 (S.I. 2020/402), arts. 1, 9(4)(5) (with arts. 5, 44)
- C176
Ss. 54-106 applied (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 11(3) (with art. 7)
- C177
S. 59 applied (with modifications) (21.5.2020) by The Lake Lothing (Lowestoft) Third Crossing Order 2020 (S.I. 2020/474), arts. 1, 7(4)(5) (with arts. 51, 57)
- C178
S. 59 applied (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 13(4)(5) (with art. 37)
- C179
Pt. 3 modified (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 13(1)(2) (with art. 37)
- C180
Ss. 54-106 applied (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 12(3) (with art. 37)
- C181
S. 59 applied (with modifications) (18.6.2020) by The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (S.I. 2020/556), arts. 1, 9(4)(5) (with arts. 5, 44)
- C182
Pt. 3 modified (18.6.2020) by The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (S.I. 2020/556), arts. 1, 9(1)(2) (with arts. 5, 44)
- C183
Pt. 3 modified (6.8.2020) by The A19 Downhill Lane Junction Development Consent Order 2020 (S.I. 2020/746), arts. 1, 9(1)(2) (with art. 5)
- C184
S. 59 applied (with modifications) (6.8.2020) by The A19 Downhill Lane Junction Development Consent Order 2020 (S.I. 2020/746), arts. 1, 9(4)(5) (with art. 5)
- C185
Ss. 54-106 applied (1.9.2020) by The Immingham Open Cycle Gas Turbine Order 2020 (S.I. 2020/847), arts. 1, 9(3) (with Sch. 9 para. 144)
- C186
S. 59 applied (with modifications) (15.10.2020) by The Great Yarmouth Third River Crossing Development Consent Order 2020 (S.I. 2020/1075), arts. 1, 11(5)
- C187
Pt. 3 modified (15.10.2020) by The Great Yarmouth Third River Crossing Development Consent Order 2020 (S.I. 2020/1075), arts. 1, 11(1)(2)
- C188
Pt. 3 modified (29.10.2020) by The Southampton to London Pipeline Development Consent Order 2020 (S.I. 2020/1099), arts. 1, 12(1)(2) (with art. 32, Sch. 9 para. 36)
- C189
S. 59 applied (with modifications) (29.10.2020) by The Southampton to London Pipeline Development Consent Order 2020 (S.I. 2020/1099), arts. 1, 12(4)(5)(d) (with art. 32, Sch. 9 para. 36)
- C190
Pt. 3 applied (31.12.2020) by The Network Rail (Cambridgeshire Level Crossing Reduction) Order 2020 (S.I. 2020/1485), arts. 1, 3(1)
- C191
S. 59 applied (31.12.2020) by The Network Rail (Cambridgeshire Level Crossing Reduction) Order 2020 (S.I. 2020/1485), arts. 1, 3(2)(3)
- C192
S. 59 applied (with modifications) (19.1.2021) by The Network Rail (Suffolk Level Crossing Reduction) Order 2020 (S.I. 2020/1663), arts. 1, 3(2)(3)
- C193
Pt. 3 modified (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 10(1)(2) (with art. 5, Sch. 27 para. 36)
- C194
Ss. 54-106 applied (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 12(3) (with art. 5, Sch. 27 para. 36)
- C195
S. 59 applied (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 10(4)(5) (with art. 5, Sch. 27 para. 36)
- C196
S. 59 applied (with modifications) (19.2.2021) by The A303 Sparkford to Ilchester Dualling Development Consent Order 2021 (S.I. 2021/125), arts. 1, 12(4)(5) (with arts. 4, 47)
- C197
S. 59 applied (1.9.2021) by The Network Rail (Teddington Station Access for All) Order 2021 (S.I. 2021/937), arts. 1, 3(3)(d)
- C198
Ss. 54-106 applied (22.12.2021) by The Morlais Demonstration Zone Order 2021 (S.I. 2021/1478), arts. 1, 7, Sch. 10 para. 2 (with arts. 15, 50, Sch. 11 para. 29)
- C199
Ss. 54-106 applied (10.3.2022) by The Thurrock Flexible Generation Plant Development Consent Order 2022 (S.I. 2022/157), arts. 1, 11(3) (with Sch. 8 Pt. 6 para. 19)
- C200
S. 59 applied (with modifications) (10.3.2022) by The Thurrock Flexible Generation Plant Development Consent Order 2022 (S.I. 2022/157), arts. 1, 12(4)(5) (with Sch. 8 Pt. 6 para. 19)
- C201
Pt. 3 modified (25.3.2022) by The Bridgwater Tidal Barrier Order 2022 (S.I. 2022/299), arts. 1, 3(1)(2) (with art. 55)
- C202
S. 59 applied (with modifications) (25.3.2022) by The Bridgwater Tidal Barrier Order 2022 (S.I. 2022/299), arts. 1, 3(4)(5) (with art. 55)
- C203
S. 59 applied (with modifications) (12.5.2022) by The M54 to M6 Link Road Development Consent Order 2022 (S.I. 2022/475), arts. 1, 9(4)(5)
- C204
Pt. 3 modified (12.5.2022) by The M54 to M6 Link Road Development Consent Order 2022 (S.I. 2022/475), arts. 1, 9(2)
- C205
S. 59 applied (with modifications) (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), arts. 1, 11(4)(5) (with arts. 6, 34)
- C206
Pt. 3 modified (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), arts. 1, 11(1)(2) (with arts. 6, 34)
- C207
Pt. 3 modified (6.6.2022) by The M25 Junction 28 Development Consent Order 2022 (S.I. 2022/573), arts. 1, 10(1)(2) (with arts. 5, 36) (as amended (7.2.2024) by S.I. 2024/129, art. 1, Sch.)
- C208
S. 59 applied (6.6.2022) by The M25 Junction 28 Development Consent Order 2022 (S.I. 2022/573), arts. 1, 10(4)(5) (with arts. 5, 36)
- C209
S. 59 applied (with modifications) (30.6.2022) by The Network Rail (Essex and Others Level Crossing Reduction) Order 2022 (S.I. 2022/651), arts. 1, 3(2)(3)
- C210
S. 59 applied (with modifications) (13.7.2022) by The A47 Blofield to North Burlingham Development Consent Order 2022 (S.I. 2022/738), arts. 1, 11(4)(5) (with arts. 4, 50)
- C211
Ss. 54-106 applied (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 14(4) (with arts. 15, 62, 76, 87)
S. 59 applied (with modifications) (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 15(3)(4) (with arts. 62, 76, 87)
- C212
S. 59 applied (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 10(4)(5) (with arts. 4, 53)
- C213
Ss. 54-106 applied (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 14(3) (with arts. 4, 53)
- C214
Pt. 3 modified (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 15(1) (with arts. 62, 76, 87)
Pt. 3 modified (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 10(1)(2) (with arts. 4, 53)
- C215
S. 59 applied (with modifications) (8.9.2022) by The Manston Airport Development Consent Order 2022 (S.I. 2022/922), arts. 1, 10(4)(5) (with arts. 5, 40)
- C216
S. 59 applied (with modifications) (8.9.2022) by The A428 Black Cat to Caxton Gibbet Development Consent Order 2022 (S.I. 2022/934), arts. 1, 11(4)(5)
- C217
Pt. 3 modified (8.9.2022) by The A428 Black Cat to Caxton Gibbet Development Consent Order 2022 (S.I. 2022/934), arts. 1, 11(2)
- C218
Pt. 3 modified (8.9.2022) by The Manston Airport Development Consent Order 2022 (S.I. 2022/922), arts. 1, 10(2) (with arts. 5, 40)
- C219
S. 59 applied (with modifications) (3.11.2022) by The Network Rail (Huddersfield to Westtown (Dewsbury) Improvements) Order 2022 (S.I. 2022/1067), arts. 1, 4(3)(4)
- C220
Pt. 3 modified (3.11.2022) by The Network Rail (Huddersfield to Westtown (Dewsbury) Improvements) Order 2022 (S.I. 2022/1067), arts. 1, 4(1)
- C221
S. 59 applied (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 11(4)(5)(d) (with arts. 4, 52, Sch. 9 para. 82)
- C222
Pt. 3 modified (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 11(1)(2) (with arts. 4, 52, Sch. 9 para. 82)
- C223
Pt. 3 modified (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 11(1)(2) (with arts. 4, 52, Sch. 9 para. 82)
- C224
Ss. 54-106 applied (with modifications) (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 15(3) (with arts. 4, 52, Sch. 9 para. 82)
- C225
S. 59 applied (5.12.2022) by The Portishead Branch Line (MetroWest Phase 1) Order 2022 (S.I. 2022/1194), arts. 1, 12(4)(5)(d) (with art. 51)
- C226
Pt. 3 modified (5.12.2022) by The Portishead Branch Line (MetroWest Phase 1) Order 2022 (S.I. 2022/1194), arts. 1, 12(1)(2) (with art. 51)
- C227
Pt. 3 modified (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 11(1)(2) (with art. 5)
- C228
Pt. 3 modified (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 12(1)(2) (with art. 4)
- C229
Ss. 54-106 applied (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 10(3) (with arts. 5, 11)
- C230
Ss. 54-106 applied (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 11(3) (with arts. 4, 12)
- C231
S. 59 applied (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 12(4)(5) (with art. 4)
- C232
S. 59 applied (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 11(4)(5) (with art. 5)
- C233
Ss. 54-106 applied (29.12.2022) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022 (S.I. 2022/1396), arts. 1, 9(3) (with art. 32, Sch. 10 paras. 26(2), 68)
- C234
Pt. 3 modified (11.1.2023) by The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (S.I. 2022/1406), arts. 1, 4(1) (with art. 34(2), Sch. 12 paras. 5, 47, 79)
- C235
S. 59 applied (11.1.2023) by The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (S.I. 2022/1406), arts. 1, 4(4) (with art. 34(2), Sch. 12 paras. 5, 47, 79)
- C236
S. 59 applied (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 11(4)(5) (with arts. 4, 50)
- C237
Ss. 54-106 applied (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 15(3) (with arts. 4, 50)
- C238
Pt. 3 modified (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 11(1)(2) (with arts. 4, 50)
- C239
Ss. 54-106 applied (18.7.2023) by The Longfield Solar Farm Order 2023 (S.I. 2023/734), arts. 1, 8(3)
- C240
Ss. 54-106 applied (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 10(3) (with arts. 5, 53, Sch. 8 paras. 6, 64)
- C241
Pt. 3 modified (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 11(2) (with arts. 5, 53, Sch. 8 paras. 6, 64)
- C242
S. 59 applied (with modifications) (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 11(4)(5) (with arts. 5, 53, Sch. 8 paras. 6, 64)
- C243
S. 59 applied (with modifications) (2.8.2023) by The Rother Valley Railway (Bodiam to Robertsbridge Junction) Order 2023 (S.I. 2023/815), arts. 1, 4(2)(3) (with art. 42)
- C244
Pt. 3 modified (4.8.2023) by The A303 (Amesbury to Berwick Down) Development Consent Order 2023 (S.I. 2023/834), arts. 1, 8(1)(2) (with arts. 6(2), 18, Sch. 11 paras. 5, 30)
- C245
S. 59 applied (with modifications) (4.8.2023) by The A303 (Amesbury to Berwick Down) Development Consent Order 2023 (S.I. 2023/834), arts. 1, 8(4)(5) (with arts. 6(2), 18, Sch. 11 paras. 5, 30)
- C246
S. 59 applied (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 12(4)(5) (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))
- C247
Pt. 3 modified (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 12(1)(2) (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))
- C248
Ss. 54-106 applied (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 11(3) (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))
- C249
Ss. 54-106 applied (7.2.2024) by The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024 (S.I. 2024/70), arts. 1, 9(3) (with art. 43, Sch. 12 paras. 5, 24)
- C250
Pt. 3 modified (9.2.2024) by The A12 Chelmsford to A120 Widening Development Consent Order 2024 (S.I. 2024/60), arts. 1, 12(1)(2) (with arts. 4, 52, Sch. 11 paras. 6, 24, 39(1), 55(1), 84)
- C251
S. 59 applied (9.2.2024) by The A12 Chelmsford to A120 Widening Development Consent Order 2024 (S.I. 2024/60), arts. 1, 12(4)(5) (with arts. 4, 52, Sch. 11 paras. 6, 24, 39(1), 55(1), 84)
- C252
Ss. 54-106 applied (11.3.2024) by The Net Zero Teesside Order 2024 (S.I. 2024/174), arts. 1, 11(3) (with arts. 42, 43, Sch. 12 paras. 5, 51, 91, 129, 136, 234, 345, 356)
- C253
Ss. 54-106 applied (13.3.2024) by The Medworth Energy from Waste Combined Heatnd Power Facility Order 2024 (S.I. 2024/230), arts. 1, 10 (with Sch. 11 paras. 5, 22, 37, 47, 82, 110)
- C254
S. 59 applied (28.3.2024) by The A66 Northern Trans-Pennine Development Consent Order 2024 (S.I. 2024/360), arts. 1, 8(4)(5) (with arts. 18, 35, Sch. 9)
- C255
Pt. 3 modified (28.3.2024) by The A66 Northern Trans-Pennine Development Consent Order 2024 (S.I. 2024/360), arts. 1, 8(2) (with arts. 18, 35, Sch. 9)
- C256
S. 59 applied (5.4.2024) by The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024 (S.I. 2024/393), arts. 1, 12(4)(5) (with art. 44, Sch. 15)
- C257
Pt. 3 modified (5.4.2024) by The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024 (S.I. 2024/393), arts. 1, 12(2) (with art. 44, Sch. 15)
- C258
S. 59 applied (25.4.2024) by The Network Rail (Church Fenton Level Crossing Reduction) Order 2024 (S.I. 2024/526), arts. 1, 4(3)(4)
- C259
Ss. 54-106 applied (14.6.2024) by The A1 in Northumberland: Morpeth to Ellingham Development Consent Order 2024 (S.I. 2024/733), arts. 1, 13(3) (with art. 6, Sch. 10)
- C260
S. 59 applied (14.6.2024) by The A1 in Northumberland: Morpeth to Ellingham Development Consent Order 2024 (S.I. 2024/733), arts. 1, 11(4)(5) (with art. 6, Sch. 10)
- C261
Pt. 3 modified (14.6.2024) by The A1 in Northumberland: Morpeth to Ellingham Development Consent Order 2024 (S.I. 2024/733), arts. 1, 11(2) (with art. 6, Sch. 10)
- C262
Ss. 54-106 applied (3.8.2024) by The Mallard Pass Solar Farm Order 2024 (S.I. 2024/796), arts. 1, 8(3) (with Sch. 15)
- C263
Ss. 54-106 applied (3.8.2024) by The Gate Burton Energy Park Order 2024 (S.I. 2024/807), arts. 1, 8(3) (with art. 45, Sch. 14)
- C264
Ss. 54-106 applied (3.8.2024) by The Sunnica Energy Farm Order 2024 (S.I. 2024/802), arts. 1, 8(4) (with art. 44, Sch. 12)
- C265
Ss. 54-106 applied (27.9.2024) by The Cottam Solar Project Order 2024 (S.I. 2024/943), arts. 1, 8(3) (with art. 48, Sch. 15)
Ss. 54-106 applied (9.10.2024) by The M3 Junction 9 Development Consent Order 2024 (S.I. 2024/753), arts. 1, 11(3) (with arts. 4, 13, Sch. 10) (as amended by S.I. 2024/1020, Sch.)
- C266
S. 59 applied (4.10.2024) by The National Grid (Bramford to Twinstead Reinforcement) Order 2024 (S.I. 2024/958), arts. 1, 13(5)(6) (with art. 40, Sch. 14)
S. 59 applied (9.10.2024) by The M3 Junction 9 Development Consent Order 2024 (S.I. 2024/753), arts. 1, 13(4)(5) (with arts. 4, 13(8), Sch. 10) (as amended by S.I. 2024/1020, Sch.)
- C267
Pt. 3 modified (4.10.2024) by The National Grid (Bramford to Twinstead Reinforcement) Order 2024 (S.I. 2024/958), arts. 1, 13(2) (with art. 40, Sch. 14)
Pt. 3 modified (9.10.2024) by The M3 Junction 9 Development Consent Order 2024 (S.I. 2024/753), arts. 1, 13(2) (with arts. 4, 13(8), Sch. 10) (as amended by S.I. 2024/1020, Sch.)
- C268
S. 59 applied (18.12.2024) by The Network Rail (Leeds to Micklefield Enhancements) Order 2024 (S.I. 2024/1284), arts. 1, 4(3)(4) (with Sch. 15)
- C269
Pt. 3 modified (18.12.2024) by The Network Rail (Leeds to Micklefield Enhancements) Order 2024 (S.I. 2024/1284), arts. 1, 4(1) (with Sch. 15)
- C270
Ss. 54-106 applied (15.2.2025) by The West Burton Solar Project Order 2025 (S.I. 2025/116), arts. 1, 8 (with art. 47, Sch. 15)
- C271
Ss. 54-106 applied (17.2.2025) by The Heckington Fen Solar Park Order 2025 (S.I. 2025/85), arts. 1, 8(3) (with art. 43, Sch. 13)
- C272
S. 59 applied (27.2.2025) by The Associated British Ports (Immingham Green Energy Terminal) Order 2025 (S.I. 2025/165), arts. 1, 8(4)(5) (with arts. 48, 59, Sch. 14)
- C273
Pt. 3 modified (27.2.2025) by The Associated British Ports (Immingham Green Energy Terminal) Order 2025 (S.I. 2025/165), arts. 1, 8(1)(2) (with arts. 48, 59, Sch. 14)
- C274
Ss. 54-106 applied (4.4.2025) by The North Lincolnshire Green Energy Park Order 2025 (S.I. 2025/362), arts. 1, 12(6) (with Sch. 14)
- C275
Pt. 3 modified (15.4.2025) by The A122 (Lower Thames Crossing) Development Consent Order 2025 (S.I. 2025/462), arts. 1, 9(1)(2) (with arts. 5, 43, 53(7), Sch. 14)
- C276
Pt. 3 applied (15.4.2025) by The A122 (Lower Thames Crossing) Development Consent Order 2025 (S.I. 2025/462), art. 1, Sch. 14 para. 50(3) (with arts. 5, 43, 53(7), 54(2), Sch. 14)
- C277
S. 59 applied (15.4.2025) by The A122 (Lower Thames Crossing) Development Consent Order 2025 (S.I. 2025/462), arts. 1, 9(4)(5) (with arts. 5, 43, 53(7), Sch. 14)
- C278
Ss. 54-106 applied (24.4.2025) by The London Luton Airport Expansion Development Consent Order 2025 (S.I. 2025/463), arts. 1, 10(3) (with Sch. 8 paras. 36(3), 87)
- C279
Pt. 3 modified (24.4.2025) by The London Luton Airport Expansion Development Consent Order 2025 (S.I. 2025/463), arts. 1, 9(2) (with Sch. 8 paras. 36(3), 87)
- C280
S. 59 applied (with modifications) (24.4.2025) by The London Luton Airport Expansion Development Consent Order 2025 (S.I. 2025/463), arts. 1, 9(4)(5) (with Sch. 8 paras. 36(3), 87)
- C281
Ss. 54-106 applied (31.5.2025) by The East Yorkshire Solar Farm Order 2025 (S.I. 2025/585), arts. 1, 8(3) (with art. 49, Sch. 14)
- C282
Ss. 54-106 applied (25.6.2025) by The M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), arts. 1, 11(3) (with arts. 4, 43, Sch. 9)
- C283
Pt. 3 modified (25.6.2025) by The M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), arts. 1, 12(1)(2) (with arts. 4, 43, Sch. 9)
- C284
S. 59 applied (25.6.2025) by The M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), arts. 1, 12(4)(5) (with arts. 4, 43, Sch. 9)
- C285
Ss. 54-106 applied (11.7.2025) by The Oaklands Farm Solar Park Order 2025 (S.I. 2025/739), arts. 1, 8(4) (with Sch. 10)
- C286
Ss. 54-106 applied (30.9.2025) by The M60/M62/M66 Simister Island Interchange Development Consent Order 2025 (S.I. 2025/1018), arts. 1, 10(3) (with arts. 5, 34, Sch. 9)
- C287
S. 59 applied (30.9.2025) by The M60/M62/M66 Simister Island Interchange Development Consent Order 2025 (S.I. 2025/1018), arts. 1, 11(4)(5) (with arts. 5, 34, Sch. 9)
- C288
Ss. 54-106 applied (12.10.2025) by The Gatwick Airport (Northern Runway Project) Development Consent Order 2025 (S.I. 2025/1054), arts. 1, 11(3) (with arts. 5, 9(6), 43, Sch. 9)
- C289
S. 59 applied (12.10.2025) by The Gatwick Airport (Northern Runway Project) Development Consent Order 2025 (S.I. 2025/1054), arts. 1, 10(4)(5) (with arts. 5, 9(6), 43, Sch. 9)
- C290
S. 59 applied (22.10.2025) by The A46 Newark Bypass Development Consent Order 2025 (S.I. 2025/1090), arts. 1, 13(4)(5) (with arts. 4, 9, 51, Sch. 9)
- C291
Ss. 54-106 applied (5.11.2025) by The Tillbridge Solar Order 2025 (S.I. 2025/1105), arts. 1, 8(3) (with art. 49, Sch. 15)
- C292
Ss. 54-106 applied (13.11.2025) by The Stonestreet Green Solar Order 2025 (S.I. 2025/1175), arts. 1, 10(3) (with art. 40, Sch. 13)
- C293
Ss. 54-106 applied (27.11.2025) by The Cory Decarbonisation Project Order 2025 (S.I. 2025/1227), arts. 1, 13(3) (with Sch. 12)
- C294
Ss. 54-106 applied (29.12.2025) by The Helios Renewable Energy Project Order 2025 (S.I. 2025/1372), arts. 1, 9(3) (with Sch. 9)
- C295
Ss. 54-106 applied (25.2.2026) by The A46 Coventry Junctions (Walsgrave) Development Consent Order 2026 (S.I. 2026/125), arts. 1, 11(3) (with arts. 40, 45, Sch. 9) (which affecting provisions were superseded by S.I. 2026/537, arts. 1, 11(3) (with arts. 40, 45, Sch. 9))
- C296
S. 59 applied (25.2.2026) by The A46 Coventry Junctions (Walsgrave) Development Consent Order 2026 (S.I. 2026/125), arts. 1, 10(4)(5) (with arts. 40, 45, Sch. 9) (which affecting provisions were superseded by S.I. 2026/537, arts. 1, 10(4)(5) (with arts. 40, 45, Sch. 9))
- C297
Ss. 54-106 applied (11.3.2026) by The Fenwick Solar Farm Order 2026 (S.I. 2026/151), arts. 1, 8(3) (with Sch. 14)
- C298
Ss. 54-106 applied (30.4.2026) by The Springwell Solar Farm Order 2026 (S.I. 2026/419), arts. 1, 8(3) (with art. 48)
- C299
Ss. 54-106 applied (23.7.2026) by The Peartree Hill Solar Farm Order 2026 (S.I. 2026/869), arts. 1, 10(3) (with art. 37, Sch. 11)
- C300
S. 59 applied (23.7.2026) by The Peartree Hill Solar Farm Order 2026 (S.I. 2026/869), arts. 1, 11(4)(5) (with art. 37, Sch. 11)
- C301
S. 59 applied (24.7.2026) by The Dean Moor Solar Farm Order 2026 (S.I. 2026/754), arts. 1, 11(4)(5) (with Sch. 13)
- C302
Ss. 54-106 applied (24.7.2026) by The Dean Moor Solar Farm Order 2026 (S.I. 2026/754), arts. 1, 10(3) (with Sch. 13)
- C303
Ss. 54-106 applied (30.7.2026) by The One Earth Solar Farm Order 2026 (S.I. 2026/934), arts. 1, 8(3) (with art. 47)
- C304
Ss. 54-106 applied (14.9.2026) by The Beacon Fen Energy Park Order 2026 (S.I. 2026/1025), arts. 1, 11(3) (with art. 39, Sch. 11 para. 131)
- C305
Ss. 54-106 applied (30.10.2026) by The Green Hill Solar Farm Order 2026 (S.I. 2026/1074), arts. 1, 8(3) (with Sch. 15)
- C306
Ss. 54-106 applied (31.10.2026) by The Steeple Renewables Project Order 2026 (S.I. 2026/1086), arts. 1, 8(3) (with Sch. 10)
Commencement
- I1
S. 59 wholly in force: s. 59(1)(2)(4)-(6) in force at 1.1.1993, see s. 170 and S.I. 1992/2984, art. 2(2), Sch. 2; s. 59(3) in force at 14.7.1992 by S.I. 1992/1686, art. 3, Sch.
Notes on Part III
Modifications
- C1
Pt. 3 (ss. 48-106) modified (14.3.2002) by The Chester Guided Busway Order 2002 (S.I. 2002/412), arts. 3(1)(2) (with art. 38);
Pt. 3 (ss. 48-106) modified (30.4.2002) by The Docklands Light Railway (Silvertown and London City Airport Extension) Order 2002 (S.I. 2002/1066), art. 3(1)
- C2
Pt. 3 (ss. 48-106) applied (6.11.2000) by 2000 c. 26, s. 95, Sch. 6 para. 1(3); S.I. 2000/2957, art. 2(1), Sch. 1
Pt. 3 (ss. 48-106) modified (29.3.2001) by S.I. 2001/1348, art. 21(2)
Pt. 3 (ss. 48-106) amended (24.7.2001) by S.I. 2001/3627, art. 4(1)
- C3
Definition in Pt. 3 (ss. 48-106) applied (1.12.1991) by Water Industry Act 1991 (c. 56, SIF 130), ss. 71-84, 162-172, 219(1), 223(2), Sch. 6 para. 6(3)(a).
- C4
Definition in Pt. 3 (ss. 48-106) applied (1.12.1991) by Water Resources Act 1991 (c. 57, SIF 130), ss. 178, 221(1), 225(2), Sch. 22 para. 3(2).
- C5
Pt. 3 excluded (16.3.1992) by Avon Weir Act 1992 (c. v), s. 6(3) (with s. 61(1))
- C6
Pt. 3 modified (1.1.1993) by Pipelines Act 1962 (c. 58), s. 16(1) (as substituted (1.1.1993) by New Roads and Street Works Act 1991 (c. 22), s. 168(1), Sch. 8 Pt. 3 para. 101(3); S.I. 1992/2984, art. 2(2), Sch.2)
Pt. 3 modified (27.7.1993) by 1993 c. xv, s. 4(1)
Pt. 3 (ss. 48-106) excluded (27.7.1993) by 1993 c. xv, s. 4(2)
- C7
Pt. 3 applied (with modifications) (21.7.1994) by 1994 c. xv, s. 4(1)
Pt. 3 applied (21.7.1994) by 1994 c. xv, s. 45(5)(a)
Pt. 3 excluded (21.7.1994) by 1994 c. xv, s. 21(2)
Pt. 3 restricted (21.7.1994) by 1994 c. xv, s. 4(2)
- C8
Pt. 3 excluded (18.12.1996) by 1996 c. 61, s. 52, Sch. 15 para. 1(3)
Pt. 3 modified (18.12.1996) by 1996 c. 61, s. 3, Sch. 3 para. 8
- C9
Pt. 3 extended (28.7.1998) by 1998 c. iv, s. 3
- C10
Pt. 3 applied (27.8.1998) by S.I. 1998/1936, arts. 1, 41, Sch. 10 paras. 2(8), 3(2)
Pt. 3 modified (13.1.1999) by S.I. 1998/3269, art. 4(1)
- C26
Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 3 para. 8
- C27
Pt. 3 excluded (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 17 para. 1(3)
- C57
Pt. 3 modified (23.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(1), Sch. 4 para. 8(1) (with Sch. 4 para. 8(2))
- C58
Pt. 3 excluded (23.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(1), Sch. 33 para. 1(3)
- C62
Pt. 3 modified (19.12.2017) by The Network Rail (Buxton Sidings Extension) Order 2017 (S.I. 2017/1150), arts. 1, 4(1) (with art. 32(2))
- C83
Pt. 3 excluded (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 32 para. 1(3) (with Sch. 32 para. 1(1))
- C84
Pt. 3 modified (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 4 paras. 10(1), 14(3) (with Sch. 4 para. 10(2))
- C85
Pt. 3 applied (2.12.2021) by The South Humber Bank Energy Centre Order 2021 (S.I. 2021/1259), arts. 1, 10(3) (with Sch. 8 para. 48)
- C112
Pt. 3 modified (23.4.2025) by The Cambridge Waste Water Treatment Plant Relocation Order 2025 (S.I. 2025/452), arts. 1, 10(4)
- C115
Pt. 3 modified (14.8.2025) by The Byers Gill Solar Order 2025 (S.I. 2025/934), arts. 1, 10(2) (with art. 43, Sch. 11)
- C116
Pt. 3 modified (30.9.2025) by The M60/M62/M66 Simister Island Interchange Development Consent Order 2025 (S.I. 2025/1018), arts. 1, 11(2) (with arts. 5, 34, Sch. 9)
- C117
Pt. 3 modified (12.10.2025) by The Gatwick Airport (Northern Runway Project) Development Consent Order 2025 (S.I. 2025/1054), arts. 1, 10(2) (with arts. 5, 9(6), 43, Sch. 9)
- C118
Pt. 3 modified (22.10.2025) by The A46 Newark Bypass Development Consent Order 2025 (S.I. 2025/1090), arts. 1, 13(2) (with arts. 4, 9, 51, Sch. 9)
- C119
Pt. 3 modified (25.2.2026) by The A46 Coventry Junctions (Walsgrave) Development Consent Order 2026 (S.I. 2026/125), arts. 1, 10(1) (with arts. 40, 45, Sch. 9) (which affecting provisions were superseded by S.I. 2026/537, arts. 1, 10(1) (with arts. 40, 45, Sch. 9))
- C120
Pt. 3 modified (23.7.2026) by The Peartree Hill Solar Farm Order 2026 (S.I. 2026/869), arts. 1, 11(1)(2) (with art. 37, Sch. 11)
- C121
Pt. 3 modified (24.7.2026) by The Dean Moor Solar Farm Order 2026 (S.I. 2026/754), arts. 1, 11(2) (with Sch. 13)
- C122
Pt. 3 modified (31.10.2026) by The Steeple Renewables Project Order 2026 (S.I. 2026/1086), arts. 1, 9(9) (with Sch. 10)